2021-014-RS
- Let date
- Friday, November 5, 2021
- Contract
- 62N55 · job page
- District
- District 1
- County
- Kane
- Highway
- Limits
- (1.64-mile) Standard Overlay, Milled Rumble Strip and ADA improvements project, consisting of HMA removal, pavement patching, HMA resurfacing, curb ramps (ADA) improvements, pavement markings install. Located on IL 25 from Hazel Avenue to the Kendall County Line in the City of Aurora and the Village of Montgomery.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Geneva Construction Company Low bidder | $1,031,471 | ||
| 2 | K-Five Construction Corporation | $1,032,276 | +0.1% | |
| 3 | Builders Paving, LLC | $1,053,000 | +2.1% | |
| 4 | D. Construction, Inc. | $1,173,581 | +13.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Geneva Construc… | #2 K-Five Construc… | #3 Builders Paving… | #4 D. Construction… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $2,727.00 | $1,000.00 | $1,800.00 | $53,588.00 | |
| 2 | X0326898 | CENTERLN RUM STRIP 16 | 1,558 | FOOT | $2.55 | $3.85 | $6.00 | $5.00 | |
| 3 | X0327120 | WEED CTRL NTV LSCP EN | 1.17 | ACRE | $2,000.00 | $5,500.00 | $3,500.00 | $6,050.00 | |
| 4 | X2010100 | TREE LIMB REM 4-10 | 4 | EACH | $200.00 | $200.00 | $200.00 | $220.00 | |
| 5 | X2010350 | TREE REMOV ACRES SPL | 1 | ACRE | $10,800.00 | $14,040.00 | $10,800.00 | $15,444.00 | |
| 6 | X2020110 | GRADING & SHAP SHLDRS | 117 | UNIT | $43.18 | $50.00 | $62.00 | $100.00 | |
| 7 | X4400501 | COMB C&G REMOV REPL < = 10FT | 150 | FOOT | $55.00 | $45.00 | $82.50 | $63.80 | |
| 8 | X5537800 | SS CLEANED 12 | 325 | FOOT | $3.00 | $3.00 | $3.00 | $2.75 | |
| 9 | X6030310 | FR & LIDS ADJUST SPL | 18 | EACH | $900.00 | $900.00 | $900.00 | $770.00 | |
| 10 | X7800815 | HS THPL PM LN 4 | 3,116 | FOOT | $1.20 | $1.50 | $1.50 | $0.7700 | |
| 11 | Z0004562 | COMB C C&G REM & REPL | 200 | FOOT | $52.00 | $45.00 | $73.00 | $63.80 | |
| 12 | Z0018100 | DRAINAGE STR ADJ SPL | 18 | EACH | $900.00 | $900.00 | $900.00 | $990.00 | |
| 13 | Z0018500 | DRAINAGE STR CLEANED | 26 | EACH | $400.00 | $400.00 | $400.00 | $319.00 | |
| 14 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $20.00 | $20.00 | $12.00 | $25.00 | |
| 15 | Z0033700 | LONG JOINT SEALANT | 11,932 | FOOT | $2.30 | $2.15 | $2.35 | $2.21 | |
| 16 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 17 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 18 | 20100110 | TREE REMOV 6-15 | 22 | UNIT | $45.00 | $60.00 | $45.00 | $66.00 | |
| 19 | 20101350 | TREE PRUN OVER 10 | 8 | EACH | $100.00 | $240.00 | $100.00 | $264.00 | |
| 20 | 20200100 | EARTH EXCAVATION | 15 | CU YD | $100.00 | $65.00 | $70.00 | $55.00 | |
| 21 | 21101615 | TOPSOIL F & P 4 | 34 | SQ YD | $8.00 | $20.00 | $70.00 | $22.00 | |
| 22 | 25000210 | SEEDING CL 2A | 1 | ACRE | $4,500.00 | $2,775.00 | $6,050.00 | $3,052.50 | |
| 23 | 25000400 | NITROGEN FERT NUTR | 5 | POUND | $2.00 | $5.00 | $8.00 | $5.50 | |
| 24 | 25000500 | PHOSPHORUS FERT NUTR | 5 | POUND | $2.00 | $5.00 | $8.00 | $5.50 | |
| 25 | 25000600 | POTASSIUM FERT NUTR | 5 | POUND | $2.00 | $5.00 | $8.00 | $5.50 | |
| 26 | 25100125 | MULCH METHOD 3 | 1 | ACRE | $3,000.00 | $2,695.00 | $100.00 | $2,964.50 | |
| 27 | 25200110 | SODDING SALT TOLERANT | 34 | SQ YD | $40.00 | $90.00 | $100.00 | $99.00 | |
| 28 | 25200200 | SUPPLE WATERING | 1 | UNIT | $50.00 | $60.00 | $800.00 | $66.00 | |
| 29 | 40600290 | BIT MATLS TACK CT | 20,202 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 30 | 40600400 | MIX CR JTS FLANGEWYS | 45 | TON | $100.00 | $50.00 | $530.00 | $50.00 | |
| 31 | 40600982 | HMA SURF REM BUTT JT | 287 | SQ YD | $10.00 | $0.0100 | $26.00 | $0.0100 | |
| 32 | 40603200 | P HMA BC IL-4.75 N50 | 1,235 | TON | $100.00 | $100.00 | $88.50 | $92.00 | |
| 33 | 40604062 | HMA SC IL-9.5 D N70 | 2,514 | TON | $72.00 | $95.00 | $73.00 | $71.00 | |
| 34 | 42001300 | PROTECTIVE COAT | 174 | SQ YD | $0.0100 | $1.00 | $3.00 | $0.1100 | |
| 35 | 42400200 | PC CONC SIDEWALK 5 | 953 | SQ FT | $10.00 | $15.00 | $10.00 | $9.90 | |
| 36 | 42400800 | DETECTABLE WARNINGS | 115 | SQ FT | $26.00 | $40.00 | $35.00 | $44.00 | |
| 37 | 44000100 | PAVEMENT REM | 54 | SQ YD | $15.00 | $18.00 | $18.00 | $20.00 | |
| 38 | 44000158 | HMA SURF REM 2 1/4 | 29,928 | SQ YD | $2.80 | $3.00 | $2.75 | $2.25 | |
| 39 | 44000600 | SIDEWALK REM | 434 | SQ FT | $2.00 | $10.00 | $4.00 | $7.15 | |
| 40 | 44201798 | CL D PATCH T1 13 | 20 | SQ YD | $140.00 | $35.00 | $60.00 | $135.00 | |
| 41 | 44201803 | CL D PATCH T2 13 | 800 | SQ YD | $96.00 | $35.00 | $60.00 | $110.00 | |
| 42 | 44201807 | CL D PATCH T3 13 | 150 | SQ YD | $90.00 | $35.00 | $60.00 | $110.00 | |
| 43 | 44201809 | CL D PATCH T4 13 | 2,300 | SQ YD | $68.00 | $35.00 | $60.00 | $105.00 | |
| 44 | 48102100 | AGG WEDGE SHLD TYPE B | 465 | TON | $41.00 | $45.00 | $37.00 | $30.00 | |
| 45 | 60260100 | INLETS ADJUST | 8 | EACH | $450.00 | $450.00 | $450.00 | $550.00 | |
| 46 | 60600605 | CONC CURB TB | 22 | FOOT | $28.00 | $45.00 | $32.00 | $44.00 | |
| 47 | 63000001 | SPBGR TY A 6FT POSTS | 75 | FOOT | $60.00 | $48.11 | $60.00 | $66.00 | |
| 48 | 63100167 | TR BAR TRM T1 SPL TAN | 1 | EACH | $7,600.00 | $4,020.00 | $7,600.00 | $8,360.00 | |
| 49 | 63200310 | GUARDRAIL REMOV | 75 | FOOT | $14.00 | $15.60 | $14.00 | $15.40 | |
| 50 | 66900200 | NON SPL WASTE DISPOSL | 15 | CU YD | $100.00 | $150.00 | $120.00 | $100.00 | |
| 51 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,390.00 | $1,950.00 | $1,500.00 | $1,650.00 | |
| 52 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,100.00 | $2,950.00 | $3,800.00 | $2,475.00 | |
| 53 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $1,900.00 | $900.00 | $500.00 | $2,475.00 | |
| 54 | 66901006 | REG SUB MON | 15 | CAL DA | $880.00 | $680.00 | $675.00 | $990.00 | |
| 55 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $2,000.00 | $3,300.00 | $2,250.00 | $4,250.00 | |
| 56 | 67100100 | MOBILIZATION | 1 | L SUM | $61,000.00 | $62,000.00 | $110,911.71 | $46,500.00 | |
| 57 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $25,000.00 | $63,400.00 | $6,200.00 | $10,000.00 | |
| 58 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $0.0100 | |
| 59 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $0.0100 | |
| 60 | 70300100 | SHORT TERM PAVT MKING | 3,292 | FOOT | $0.5500 | $1.00 | $1.00 | $0.0100 | |
| 61 | 70300150 | SHRT TRM PAVT MK REM | 549 | SQ FT | $1.00 | $10.00 | $3.00 | $0.0100 | |
| 62 | 70300210 | TEMP PVT MK LTR & SYM | 73 | SQ FT | $0.2500 | $0.0100 | $0.0100 | $0.0100 | |
| 63 | 70300220 | TEMP PVT MK LINE 4 | 24,239 | FOOT | $0.1000 | $0.0100 | $0.0100 | $0.0100 | |
| 64 | 70300240 | TEMP PVT MK LINE 6 | 680 | FOOT | $0.2000 | $0.0100 | $0.0100 | $0.0100 | |
| 65 | 70300250 | TEMP PVT MK LINE 8 | 129 | FOOT | $0.4000 | $0.0100 | $0.0100 | $0.0100 | |
| 66 | 70300260 | TEMP PVT MK LINE 12 | 744 | FOOT | $0.4000 | $0.0100 | $0.0100 | $0.0100 | |
| 67 | 70300280 | TEMP PVT MK LINE 24 | 270 | FOOT | $1.00 | $0.0100 | $0.0100 | $0.0100 | |
| 68 | 70300520 | PAVT MARK TAPE T3 4 | 1,646 | FOOT | $0.5500 | $0.0100 | $1.70 | $0.0100 | |
| 69 | 78000100 | THPL PVT MK LTR & SYM | 73 | SQ FT | $4.00 | $5.00 | $5.00 | $6.60 | |
| 70 | 78000200 | THPL PVT MK LINE 4 | 24,239 | FOOT | $0.5500 | $0.5800 | $0.5800 | $0.6600 | |
| 71 | 78000400 | THPL PVT MK LINE 6 | 680 | FOOT | $0.7500 | $0.9000 | $0.9000 | $1.27 | |
| 72 | 78000500 | THPL PVT MK LINE 8 | 129 | FOOT | $1.00 | $1.80 | $1.80 | $1.60 | |
| 73 | 78000600 | THPL PVT MK LINE 12 | 744 | FOOT | $1.50 | $3.60 | $3.60 | $2.37 | |
| 74 | 78000650 | THPL PVT MK LINE 24 | 270 | FOOT | $4.00 | $5.00 | $5.00 | $6.60 | |
| 75 | 78100100 | RAISED REFL PAVT MKR | 428 | EACH | $25.00 | $30.00 | $30.00 | $24.20 | |
| 76 | 78200006 | GRDRAIL REF TYPE B | 1 | EACH | $50.00 | $100.00 | $50.00 | $55.00 | |
| 77 | 78300200 | RAISED REF PVT MK REM | 385 | EACH | $5.00 | $10.25 | $15.00 | $10.00 | |
| 78 | 85000200 | MAIN EX TR SIG INSTAL | 2 | EACH | $1,700.00 | $1,700.00 | $1,700.00 | $1,870.00 | |
| 79 | 88600600 | DET LOOP REPL | 1,220 | FOOT | $15.70 | $15.70 | $15.70 | $17.27 | |
| 80 | 89502376 | REBUILD EX HANDHOLE | 3 | EACH | $1,700.00 | $1,700.00 | $1,700.00 | $1,870.00 |