2020-053-RS
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | P. T. Ferro Construction Co. Low bidder | $970,197 | ||
| 2 | Iroquois Paving Corporation | $987,581 | +1.8% | |
| 3 | Gallagher Asphalt Corporation | $998,142 | +2.9% | |
| 4 | K-Five Construction Corporation | $1,089,587 | +12.3% | |
| 5 | Austin Tyler Construction, Inc. | $1,205,962 | +24.3% | |
| 6 | D. Construction, Inc. | $1,246,284 | +28.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 P. T. Ferro Con… | #2 Iroquois Paving… | #3 Gallagher Aspha… | #4 K-Five Construc… | #5 Austin Tyler Co… | #6 D. Construction… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0326898 | CENTERLN RUM STRIP 16 | 5,275 | FOOT | $1.50 | $2.50 | $0.7000 | $2.00 | $2.40 | $3.35 | |
| 2 | X2020110 | GRADING & SHAP SHLDRS | 180 | UNIT | $0.0100 | $35.00 | $58.00 | $35.00 | $0.0100 | $40.00 | |
| 3 | X7030005 | TEMP PAVT MKING REMOV | 16,550 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 4 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $20.00 | $15.00 | $20.00 | $20.00 | $16.00 | $25.00 | |
| 5 | Z0033700 | LONG JOINT SEALANT | 31,500 | FOOT | $2.15 | $2.50 | $2.40 | $2.00 | $2.40 | $2.00 | |
| 6 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 7 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 8 | 40600290 | BIT MATLS TACK CT | 25,600 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 9 | 40600400 | MIX CR JTS FLANGEWYS | 85 | TON | $0.0100 | $0.0100 | $50.00 | $50.00 | $200.00 | $50.00 | |
| 10 | 40600982 | HMA SURF REM BUTT JT | 140 | SQ YD | $0.0100 | $0.0100 | $21.50 | $5.00 | $0.0100 | $0.0100 | |
| 11 | 40604062 | HMA SC IL-9.5 D N70 | 4,810 | TON | $60.00 | $61.00 | $59.00 | $69.00 | $75.00 | $73.00 | |
| 12 | 44000155 | HMA SURF REM 1 1/2 | 56,750 | SQ YD | $2.00 | $1.25 | $1.40 | $1.30 | $1.40 | $1.50 | |
| 13 | 44003510 | MEDIAN REMOVAL (PD) | 3,675 | SQ FT | $1.50 | $1.00 | $1.55 | $0.2000 | $1.75 | $0.5000 | |
| 14 | 44201815 | CL D PATCH T2 14 | 500 | SQ YD | $80.00 | $100.00 | $128.00 | $45.00 | $148.00 | $120.00 | |
| 15 | 44201819 | CL D PATCH T3 14 | 330 | SQ YD | $100.00 | $100.00 | $108.00 | $45.00 | $124.00 | $120.00 | |
| 16 | 44201821 | CL D PATCH T4 14 | 2,070 | SQ YD | $80.00 | $100.00 | $96.00 | $45.00 | $113.00 | $120.00 | |
| 17 | 44201851 | CL D PATCH T2 17 | 70 | SQ YD | $150.00 | $130.00 | $165.00 | $45.00 | $181.00 | $140.00 | |
| 18 | 44201855 | CL D PATCH T3 17 | 50 | SQ YD | $150.00 | $130.00 | $160.00 | $45.00 | $151.00 | $140.00 | |
| 19 | 44201857 | CL D PATCH T4 17 | 290 | SQ YD | $120.00 | $130.00 | $135.00 | $45.00 | $137.00 | $140.00 | |
| 20 | 48102100 | AGG WEDGE SHLD TYPE B | 675 | TON | $30.00 | $27.00 | $38.00 | $30.00 | $34.00 | $26.00 | |
| 21 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $0.0100 | $0.0100 | $500.00 | $1,500.00 | $3,000.00 | $4,000.00 | |
| 22 | 67100100 | MOBILIZATION | 1 | L SUM | $55,000.00 | $55,000.00 | $56,000.00 | $229,744.10 | $72,000.00 | $70,000.00 | |
| 23 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $45,000.00 | $36,200.00 | $11,200.00 | $93,000.00 | $20,000.00 | $101,750.00 | |
| 24 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $5,000.00 | $1.00 | $1.00 | $1.00 | $1.00 | $0.0100 | |
| 25 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $5,000.00 | $1.00 | $1.00 | $10,000.00 | $1.00 | $0.0100 | |
| 26 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $10,000.00 | $1.00 | $0.0100 | |
| 27 | 70300100 | SHORT TERM PAVT MKING | 9,000 | FOOT | $0.0100 | $0.0100 | $0.7000 | $0.0100 | $0.8000 | $0.0100 | |
| 28 | 70300150 | SHRT TRM PAVT MK REM | 1,500 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $1.00 | $0.0100 | |
| 29 | 70300210 | TEMP PVT MK LTR & SYM | 80 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $1.65 | $0.0100 | |
| 30 | 70300220 | TEMP PVT MK LINE 4 | 49,000 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.2500 | $0.0100 | |
| 31 | 70300240 | TEMP PVT MK LINE 6 | 310 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.3500 | $0.0100 | |
| 32 | 70300260 | TEMP PVT MK LINE 12 | 180 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.5500 | $0.0100 | |
| 33 | 70300280 | TEMP PVT MK LINE 24 | 225 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $1.10 | $0.0100 | |
| 34 | 70300520 | PAVT MARK TAPE T3 4 | 4,500 | FOOT | $0.0100 | $1.00 | $1.00 | $0.0100 | $1.00 | $0.0100 | |
| 35 | 78000100 | THPL PVT MK LTR & SYM | 80 | SQ FT | $4.00 | $4.00 | $4.00 | $5.00 | $4.00 | $4.40 | |
| 36 | 78000200 | THPL PVT MK LINE 4 | 48,900 | FOOT | $0.5000 | $0.5000 | $0.5000 | $0.5500 | $0.5500 | $0.5500 | |
| 37 | 78000400 | THPL PVT MK LINE 6 | 310 | FOOT | $0.7500 | $0.7500 | $0.7500 | $1.10 | $0.8000 | $0.8300 | |
| 38 | 78000600 | THPL PVT MK LINE 12 | 70 | FOOT | $1.50 | $1.50 | $1.50 | $3.00 | $1.65 | $1.65 | |
| 39 | 78000650 | THPL PVT MK LINE 24 | 205 | FOOT | $4.00 | $4.00 | $4.00 | $5.00 | $4.00 | $4.40 | |
| 40 | 78100100 | RAISED REFL PAVT MKR | 1,050 | EACH | $23.25 | $23.25 | $20.00 | $21.00 | $25.00 | $25.58 | |
| 41 | 78300200 | RAISED REF PVT MK REM | 470 | EACH | $0.0100 | $0.0100 | $8.00 | $7.15 | $0.0100 | $7.00 | |
| 42 | 88600600 | DET LOOP REPL | 225 | FOOT | $22.00 | $18.00 | $22.00 | $18.50 | $20.00 | $19.75 |