2020-013-SW
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Davis Concrete Construction Co. Low bidder | $332,357 | ||
| 2 | Triggi Construction, Inc. | $341,415 | +2.7% | |
| 3 | J & J Newell Concrete Contractors, Inc. | $457,937 | +37.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Davis Concrete … | #2 Triggi Construc… | #3 J & J Newell Co… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $16,000.00 | $17,500.00 | $16,000.00 | |
| 2 | X0327036 | BIKE PATH REM | 128 | SQ YD | $10.00 | $20.00 | $15.00 | |
| 3 | X0327980 | PAVMT MRKG REM WTR BL | 3,725 | SQ FT | $1.25 | $1.25 | $1.25 | |
| 4 | X1200034 | INLET ADJ NEW LID SPL | 1 | EACH | $750.00 | $750.00 | $750.00 | |
| 5 | Z0004562 | COMB C C&G REM & REPL | 614 | FOOT | $55.00 | $50.00 | $100.00 | |
| 6 | Z0030850 | TEMP INFO SIGNING | 308 | SQ FT | $15.00 | $16.00 | $15.00 | |
| 7 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 8 | 20200100 | EARTH EXCAVATION | 68 | CU YD | $25.00 | $75.00 | $120.00 | |
| 9 | 21101615 | TOPSOIL F & P 4 | 253 | SQ YD | $15.00 | $1.00 | $35.00 | |
| 10 | 25000400 | NITROGEN FERT NUTR | 3 | POUND | $5.00 | $10.00 | $10.00 | |
| 11 | 25000500 | PHOSPHORUS FERT NUTR | 3 | POUND | $5.00 | $10.00 | $10.00 | |
| 12 | 25000600 | POTASSIUM FERT NUTR | 3 | POUND | $5.00 | $10.00 | $10.00 | |
| 13 | 25200110 | SODDING SALT TOLERANT | 253 | SQ YD | $25.00 | $25.00 | $35.00 | |
| 14 | 42001300 | PROTECTIVE COAT | 928 | SQ YD | $0.5000 | $2.00 | $2.00 | |
| 15 | 42400200 | PC CONC SIDEWALK 5 | 6,773 | SQ FT | $14.25 | $12.50 | $11.00 | |
| 16 | 42400800 | DETECTABLE WARNINGS | 692 | SQ FT | $25.00 | $25.00 | $40.00 | |
| 17 | 44000200 | DRIVE PAVEMENT REM | 1 | SQ YD | $100.00 | $35.00 | $15.00 | |
| 18 | 44000600 | SIDEWALK REM | 5,663 | SQ FT | $3.50 | $3.00 | $4.00 | |
| 19 | 44201341 | CL C PATCH T2 9 | 25 | SQ YD | $200.00 | $125.00 | $350.00 | |
| 20 | 44201345 | CL C PATCH T3 9 | 15 | SQ YD | $175.00 | $100.00 | $350.00 | |
| 21 | 44201753 | CL D PATCH T2 9 | 9 | SQ YD | $200.00 | $250.00 | $550.00 | |
| 22 | 44201757 | CL D PATCH T3 9 | 15 | SQ YD | $200.00 | $225.00 | $515.00 | |
| 23 | 60255500 | MAN ADJUST | 3 | EACH | $500.00 | $400.00 | $1,100.00 | |
| 24 | 60266600 | VALVE BOX ADJ | 3 | EACH | $500.00 | $250.00 | $100.00 | |
| 25 | 60300305 | FR & LIDS ADJUST | 5 | EACH | $500.00 | $400.00 | $500.00 | |
| 26 | 66900200 | NON SPL WASTE DISPOSL | 68 | CU YD | $50.00 | $100.00 | $250.00 | |
| 27 | 66900530 | SOIL DISPOSAL ANALY | 6 | EACH | $1,100.00 | $1,500.00 | $1,600.00 | |
| 28 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $3,000.00 | $5,000.00 | $1,700.00 | |
| 29 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $2,500.00 | $1,000.00 | $1,800.00 | |
| 30 | 66901006 | REG SUB MON | 15 | CAL DA | $676.00 | $600.00 | $600.00 | |
| 31 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,000.00 | $3,000.00 | $4,000.00 | |
| 32 | 67100100 | MOBILIZATION | 1 | L SUM | $37,600.00 | $15,000.00 | $88,000.00 | |
| 33 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $35,000.00 | $1.00 | |
| 34 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $5,000.00 | $5,000.00 | $4,999.00 | |
| 35 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 36 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 37 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 38 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 39 | 78000400 | THPL PVT MK LINE 6 | 1,536 | FOOT | $2.02 | $2.00 | $2.02 | |
| 40 | 78000600 | THPL PVT MK LINE 12 | 1,118 | FOOT | $4.04 | $3.50 | $4.04 | |
| 41 | 78000650 | THPL PVT MK LINE 24 | 608 | FOOT | $8.08 | $7.00 | $8.08 | |
| 42 | 78008230 | POLYUREA PM T1 LN 6 | 1,889 | FOOT | $1.92 | $3.00 | $1.92 | |
| 43 | 78008250 | POLYUREA PM T1 LN 12 | 373 | FOOT | $3.85 | $6.00 | $3.85 | |
| 44 | 78008270 | POLYUREA PM T1 LN 24 | 255 | FOOT | $7.65 | $12.00 | $7.65 |