2019-097-RS&SW
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | K-Five Construction Corporation Low bidder | $4,658,002 | ||
| 2 | MAT Construction Leasing, Inc. | $4,705,577 | +1.0% | |
| 3 | Bigane Paving Company | $5,209,233 | +11.8% | |
| 4 | Gallagher Asphalt Corporation | $5,579,978 | +19.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 K-Five Construc… | #2 MAT Constructio… | #3 Bigane Paving C… | #4 Gallagher Aspha… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $5,500.00 | $3,500.00 | $8,000.00 | $4,700.00 | |
| 2 | X4021000 | TEMP ACCESS- PRIV ENT | 7 | EACH | $375.00 | $50.00 | $250.00 | $50.00 | |
| 3 | X4022000 | TEMP ACCESS- COM ENT | 11 | EACH | $500.00 | $50.00 | $350.00 | $50.00 | |
| 4 | X4240800 | DETECTABLE WARN SPL | 244 | SQ FT | $38.00 | $30.00 | $30.00 | $35.00 | |
| 5 | X4405020 | LONG PAR DEP REM 2 | 2,000 | FOOT | $6.75 | $3.50 | $10.00 | $6.75 | |
| 6 | X5537800 | SS CLEANED 12 | 2,250 | FOOT | $2.00 | $1.90 | $4.00 | $12.00 | |
| 7 | X6030310 | FR & LIDS ADJUST SPL | 260 | EACH | $675.00 | $600.00 | $625.00 | $600.00 | |
| 8 | X7030005 | TEMP PAVT MKING REMOV | 35,698 | SQ FT | $0.1000 | $0.0100 | $0.2000 | $0.0100 | |
| 9 | Z0001110 | GAS VALVE ADJUSTED | 1 | EACH | $200.00 | $200.00 | $900.00 | $500.00 | |
| 10 | Z0004562 | COMB C C&G REM & REPL | 3,087 | FOOT | $42.00 | $30.00 | $32.00 | $28.00 | |
| 11 | Z0018500 | DRAINAGE STR CLEANED | 225 | EACH | $350.00 | $325.00 | $325.00 | $275.00 | |
| 12 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $15.00 | $16.00 | $15.00 | $25.00 | |
| 13 | Z0033700 | LONG JOINT SEALANT | 60,791 | FOOT | $2.50 | $2.06 | $2.25 | $6.00 | |
| 14 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $5,000.00 | $6,000.00 | $10,000.00 | $24,500.00 | |
| 15 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 16 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 17 | 20200100 | EARTH EXCAVATION | 9 | CU YD | $125.00 | $100.00 | $75.00 | $75.00 | |
| 18 | 21101615 | TOPSOIL F & P 4 | 472 | SQ YD | $9.70 | $7.00 | $8.00 | $3.00 | |
| 19 | 25200110 | SODDING SALT TOLERANT | 472 | SQ YD | $23.00 | $10.00 | $14.00 | $12.00 | |
| 20 | 35501308 | HMA BASE CSE 6 | 19 | SQ YD | $110.00 | $52.00 | $300.00 | $74.00 | |
| 21 | 40600290 | BIT MATLS TACK CT | 119,037 | POUND | $0.0100 | $0.5500 | $1.00 | $0.0100 | |
| 22 | 40600400 | MIX CR JTS FLANGEWYS | 265 | TON | $50.00 | $100.00 | $150.00 | $380.00 | |
| 23 | 40600982 | HMA SURF REM BUTT JT | 1,853 | SQ YD | $0.0100 | $2.50 | $20.00 | $17.00 | |
| 24 | 40601005 | HMA REPL OVER PATCH | 3,153 | TON | $50.00 | $30.00 | $90.00 | $81.00 | |
| 25 | 40603200 | P HMA BC IL-4.75 N50 | 7,257 | TON | $105.00 | $102.00 | $100.00 | $109.00 | |
| 26 | 40604060 | HMA SC IL-9.5 D N50 | 3 | TON | $110.00 | $76.50 | $150.00 | $230.00 | |
| 27 | 40604062 | HMA SC IL-9.5 D N70 | 14,777 | TON | $90.00 | $76.50 | $77.50 | $82.00 | |
| 28 | 42001300 | PROTECTIVE COAT | 2,877 | SQ YD | $1.00 | $0.9500 | $0.5000 | $0.2500 | |
| 29 | 42300200 | PCC DRIVEWAY PAVT 6 | 105 | SQ YD | $75.00 | $60.00 | $65.00 | $54.00 | |
| 30 | 42300400 | PCC DRIVEWAY PAVT 8 | 187 | SQ YD | $80.00 | $65.00 | $72.00 | $72.00 | |
| 31 | 42400200 | PC CONC SIDEWALK 5 | 1,573 | SQ FT | $8.50 | $6.64 | $6.50 | $6.00 | |
| 32 | 42400410 | PC CONC SIDEWALK 8 | 467 | SQ FT | $12.00 | $9.49 | $7.50 | $8.00 | |
| 33 | 44000158 | HMA SURF REM 2 1/4 | 175,906 | SQ YD | $3.25 | $2.50 | $3.75 | $3.20 | |
| 34 | 44000200 | DRIVE PAVEMENT REM | 311 | SQ YD | $20.00 | $18.97 | $20.00 | $16.00 | |
| 35 | 44000600 | SIDEWALK REM | 2,040 | SQ FT | $2.50 | $1.90 | $1.75 | $1.75 | |
| 36 | 44002216 | HMA RM OV PATCH 4 | 14,074 | SQ YD | $10.00 | $1.20 | $10.00 | $6.50 | |
| 37 | 44201777 | CL D PATCH T2 11 | 4,352 | SQ YD | $30.00 | $89.00 | $55.00 | $91.50 | |
| 38 | 44201781 | CL D PATCH T3 11 | 242 | SQ YD | $30.00 | $90.00 | $55.00 | $81.50 | |
| 39 | 44201783 | CL D PATCH T4 11 | 9,480 | SQ YD | $30.00 | $88.50 | $55.00 | $75.00 | |
| 40 | 44209000 | LONG PART DEPTH PATCH | 75 | TON | $175.00 | $100.00 | $150.00 | $280.00 | |
| 41 | 60250200 | CB ADJUST | 19 | EACH | $350.00 | $350.00 | $375.00 | $375.00 | |
| 42 | 60252800 | CB RECONST | 4 | EACH | $1,500.00 | $1,500.00 | $1,500.00 | $1,000.00 | |
| 43 | 60265700 | VV ADJUST | 11 | EACH | $500.00 | $500.00 | $350.00 | $275.00 | |
| 44 | 60266600 | VALVE BOX ADJ | 43 | EACH | $240.00 | $231.00 | $300.00 | $350.00 | |
| 45 | 60300105 | FR & GRATES ADJUST | 27 | EACH | $400.00 | $400.00 | $350.00 | $375.00 | |
| 46 | 60300305 | FR & LIDS ADJUST | 18 | EACH | $600.00 | $500.00 | $350.00 | $375.00 | |
| 47 | 60406000 | FR & LIDS T1 OL | 15 | EACH | $350.00 | $325.00 | $350.00 | $300.00 | |
| 48 | 60406100 | FR & LIDS T1 CL | 34 | EACH | $350.00 | $325.00 | $350.00 | $300.00 | |
| 49 | 66900200 | NON SPL WASTE DISPOSL | 9 | CU YD | $100.00 | $60.00 | $100.00 | $150.00 | |
| 50 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,500.00 | $1,750.00 | $1,500.00 | $1,500.00 | |
| 51 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $3,000.00 | $3,000.00 | $3,000.00 | $2,700.00 | |
| 52 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $2,200.00 | $2,500.00 | $1,000.00 | $2,100.00 | |
| 53 | 66901006 | REG SUB MON | 5 | CAL DA | $900.00 | $760.00 | $800.00 | $1,000.00 | |
| 54 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $3,300.00 | $1,500.00 | $3,300.00 | $3,500.00 | |
| 55 | 67100100 | MOBILIZATION | 1 | L SUM | $286,000.00 | $110,000.00 | $300,000.00 | $231,096.64 | |
| 56 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $37,200.00 | $1.00 | $12,000.00 | |
| 57 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $50,985.00 | $1.00 | $90,000.00 | $1.00 | |
| 58 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $14,000.00 | |
| 59 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | |
| 60 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $12,000.00 | |
| 61 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $12,525.00 | |
| 62 | 70300100 | SHORT TERM PAVT MKING | 32,708 | FOOT | $0.5000 | $0.7500 | $1.00 | $0.6500 | |
| 63 | 70300150 | SHRT TRM PAVT MK REM | 10,903 | SQ FT | $1.00 | $1.00 | $1.00 | $0.0100 | |
| 64 | 70300210 | TEMP PVT MK LTR & SYM | 1,394 | SQ FT | $0.7500 | $1.30 | $1.25 | $1.50 | |
| 65 | 70300220 | TEMP PVT MK LINE 4 | 42,062 | FOOT | $0.1000 | $0.4000 | $0.2000 | $0.3000 | |
| 66 | 70300240 | TEMP PVT MK LINE 6 | 4,834 | FOOT | $0.1500 | $0.6000 | $0.3000 | $0.5000 | |
| 67 | 70300250 | TEMP PVT MK LINE 8 | 1,191 | FOOT | $0.2000 | $0.1000 | $0.4000 | $0.7500 | |
| 68 | 70300260 | TEMP PVT MK LINE 12 | 862 | FOOT | $0.3000 | $1.00 | $0.6000 | $0.9500 | |
| 69 | 70300280 | TEMP PVT MK LINE 24 | 9,671 | FOOT | $0.6000 | $1.00 | $1.20 | $1.50 | |
| 70 | 70300520 | PAVT MARK TAPE T3 4 | 4,807 | FOOT | $0.9000 | $0.9500 | $0.9000 | $6.00 | |
| 71 | 78000100 | THPL PVT MK LTR & SYM | 1,394 | SQ FT | $3.95 | $3.95 | $4.00 | $5.25 | |
| 72 | 78000200 | THPL PVT MK LINE 4 | 42,062 | FOOT | $0.6000 | $0.6000 | $0.7000 | $0.6000 | |
| 73 | 78000400 | THPL PVT MK LINE 6 | 4,834 | FOOT | $0.8200 | $0.8200 | $1.00 | $1.10 | |
| 74 | 78000500 | THPL PVT MK LINE 8 | 1,191 | FOOT | $1.09 | $1.09 | $1.00 | $1.50 | |
| 75 | 78000600 | THPL PVT MK LINE 12 | 862 | FOOT | $1.75 | $1.75 | $2.00 | $2.25 | |
| 76 | 78000650 | THPL PVT MK LINE 24 | 9,671 | FOOT | $3.95 | $3.95 | $4.50 | $5.25 |