2019-098-RS-SW&SR
- Let date
- Friday, March 6, 2020
- Contract
- 62J88 · job page
- District
- District 1
- County
- Cook
- Highway
- Limits
- 4.4 miles of HMA surface removal, patching, resurfacing, ADA sidewalk repairs, HMA shoulders and drainage improvements on Des Plaines River Road from Foster Avenue to IL 171 (1st Avenue) and Lawrence Avenue from East River Road to Ridgewood Avenue within the Villages of Schiller Park, Norridge, Franklin Park and River Grove.
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | R. W. Dunteman Company Low bidder | $4,948,861 | ||
| 2 | K-Five Construction Corporation | $4,957,520 | +0.2% | |
| 3 | Arrow Road Construction Co. | $5,244,404 | +6.0% | |
| 4 | Builders Paving, LLC | $5,469,888 | +10.5% | |
| 5 | Plote Construction, Inc. | $5,634,807 | +13.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 R. W. Dunteman … | #2 K-Five Construc… | #3 Arrow Road Cons… | #4 Builders Paving… | #5 Plote Construct… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $5,000.00 | $10,000.00 | $5,000.00 | $8,606.64 | $15,000.00 | |
| 2 | X2020110 | GRADING & SHAP SHLDRS | 115 | UNIT | $297.47 | $155.68 | $130.00 | $90.00 | $195.00 | |
| 3 | X2700003 | GRV RCSD PVT MRKG 8 | 5,778 | FOOT | $0.7000 | $1.10 | $1.00 | $0.7000 | $0.7000 | |
| 4 | X2700004 | PREF PL PM TB LINE 7 | 2,030 | FOOT | $7.50 | $5.50 | $5.00 | $7.50 | $7.50 | |
| 5 | X4421790 | CL D PATCH T2 12 SPL | 16 | SQ YD | $160.50 | $145.00 | $440.00 | $250.00 | $200.00 | |
| 6 | X5537800 | SS CLEANED 12 | 1,140 | FOOT | $2.00 | $2.20 | $3.50 | $2.00 | $3.00 | |
| 7 | X6030310 | FR & LIDS ADJUST SPL | 65 | EACH | $675.00 | $743.04 | $650.00 | $675.00 | $650.00 | |
| 8 | X7030005 | TEMP PAVT MKING REMOV | 2,566 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 9 | Z0004562 | COMB C C&G REM & REPL | 1,414 | FOOT | $36.00 | $38.61 | $42.00 | $36.00 | $46.00 | |
| 10 | Z0018500 | DRAINAGE STR CLEANED | 56 | EACH | $325.00 | $347.56 | $335.00 | $325.00 | $325.00 | |
| 11 | Z0018600 | DRAINAGE STR RECONST | 12 | EACH | $1,800.00 | $1,375.31 | $1,250.00 | $1,800.00 | $1,150.00 | |
| 12 | Z0030850 | TEMP INFO SIGNING | 51.4 | SQ FT | $20.00 | $13.20 | $12.00 | $20.00 | $20.00 | |
| 13 | Z0033700 | LONG JOINT SEALANT | 62,168 | FOOT | $2.41 | $2.42 | $2.25 | $2.35 | $2.15 | |
| 14 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $5,000.00 | $5,300.00 | $5,500.00 | $15,000.00 | $3,500.00 | |
| 15 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 16 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 17 | 20200100 | EARTH EXCAVATION | 22 | CU YD | $5.04 | $45.00 | $150.00 | $85.00 | $295.00 | |
| 18 | 20200600 | EXC & GR EX SHOULDER | 117 | UNIT | $100.00 | $600.47 | $450.00 | $588.00 | $690.00 | |
| 19 | 21101615 | TOPSOIL F & P 4 | 331 | SQ YD | $7.20 | $8.00 | $15.00 | $7.20 | $10.00 | |
| 20 | 25000210 | SEEDING CL 2A | 1 | ACRE | $2,517.00 | $2,812.51 | $3,000.00 | $2,517.00 | $1,500.00 | |
| 21 | 25003210 | INTERSEED CL 2A | 7 | ACRE | $1,583.00 | $1,933.61 | $2,900.00 | $1,583.00 | $15.00 | |
| 22 | 25100630 | EROSION CONTR BLANKET | 3,500 | SQ YD | $0.8000 | $1.05 | $1.25 | $0.8000 | $2.00 | |
| 23 | 25200110 | SODDING SALT TOLERANT | 331 | SQ YD | $9.00 | $10.40 | $25.00 | $9.00 | $15.00 | |
| 24 | 35501308 | HMA BASE CSE 6 | 82 | SQ YD | $28.72 | $79.14 | $50.00 | $81.00 | $50.00 | |
| 25 | 35501316 | HMA BASE CSE 8 | 156 | SQ YD | $37.88 | $87.92 | $65.00 | $108.00 | $70.00 | |
| 26 | 40600290 | BIT MATLS TACK CT | 82,747 | POUND | $0.7200 | $0.0100 | $1.25 | $0.0100 | $0.0100 | |
| 27 | 40600400 | MIX CR JTS FLANGEWYS | 184 | TON | $500.00 | $50.00 | $100.00 | $500.00 | $250.00 | |
| 28 | 40600982 | HMA SURF REM BUTT JT | 908 | SQ YD | $9.09 | $13.50 | $4.50 | $25.00 | $19.00 | |
| 29 | 40602985 | HMA BC IL-9.5 N70 | 13,730 | TON | $82.18 | $68.00 | $64.20 | $73.00 | $70.00 | |
| 30 | 40604060 | HMA SC IL-9.5 D N50 | 35 | TON | $77.11 | $179.47 | $294.50 | $240.00 | $400.00 | |
| 31 | 40604062 | HMA SC IL-9.5 D N70 | 1,655 | TON | $84.93 | $10.00 | $1.00 | $0.0100 | $6.90 | |
| 32 | 40605026 | P HMA SC SMA 9.5 F N80 | 12,014 | TON | $98.47 | $112.00 | $103.30 | $100.00 | $90.00 | |
| 33 | 42001300 | PROTECTIVE COAT | 1,100 | SQ YD | $2.00 | $1.00 | $2.00 | $2.00 | $2.00 | |
| 34 | 42300200 | PCC DRIVEWAY PAVT 6 | 47 | SQ YD | $76.00 | $63.61 | $85.00 | $76.00 | $90.00 | |
| 35 | 42300400 | PCC DRIVEWAY PAVT 8 | 64 | SQ YD | $80.00 | $66.01 | $96.00 | $80.00 | $97.00 | |
| 36 | 42400200 | PC CONC SIDEWALK 5 | 4,031 | SQ FT | $8.50 | $7.45 | $8.50 | $8.50 | $9.50 | |
| 37 | 42400800 | DETECTABLE WARNINGS | 149 | SQ FT | $35.00 | $34.51 | $40.00 | $35.00 | $42.00 | |
| 38 | 44000164 | HMA SURF REM 3 3/4 | 122,588 | SQ YD | $5.52 | $4.80 | $8.90 | $6.50 | $8.50 | |
| 39 | 44000200 | DRIVE PAVEMENT REM | 385 | SQ YD | $26.00 | $19.50 | $18.00 | $45.00 | $18.00 | |
| 40 | 44000600 | SIDEWALK REM | 3,780 | SQ FT | $2.45 | $2.43 | $2.50 | $2.25 | $2.50 | |
| 41 | 44004250 | PAVED SHLD REMOVAL | 265 | SQ YD | $22.87 | $13.52 | $12.15 | $15.00 | $15.00 | |
| 42 | 44200050 | WELDED WIRE REINF | 523 | SQ YD | $25.00 | $15.00 | $25.00 | $25.00 | $25.00 | |
| 43 | 44200970 | CL B PATCH T2 10 | 840 | SQ YD | $120.00 | $100.00 | $96.50 | $134.00 | $85.00 | |
| 44 | 44200974 | CL B PATCH T3 10 | 305 | SQ YD | $120.00 | $100.00 | $92.50 | $132.88 | $85.00 | |
| 45 | 44200976 | CL B PATCH T4 10 | 220 | SQ YD | $115.00 | $95.00 | $91.55 | $120.63 | $85.00 | |
| 46 | 44201299 | DOWEL BARS 1 1/2 | 2,260 | EACH | $13.00 | $12.00 | $20.00 | $13.00 | $20.00 | |
| 47 | 44201815 | CL D PATCH T2 14 | 1,226 | SQ YD | $40.01 | $100.00 | $40.00 | $158.00 | $95.00 | |
| 48 | 44201819 | CL D PATCH T3 14 | 1,336 | SQ YD | $30.00 | $100.00 | $40.00 | $136.00 | $94.00 | |
| 49 | 44201821 | CL D PATCH T4 14 | 1,491 | SQ YD | $22.00 | $95.00 | $40.00 | $117.00 | $93.00 | |
| 50 | 44213200 | SAW CUTS | 67,683 | FOOT | $0.1000 | $0.0100 | $0.0100 | $2.00 | $0.0100 | |
| 51 | 44213208 | TIE BARS 1 1/4 | 174 | EACH | $8.00 | $7.00 | $25.00 | $8.00 | $25.00 | |
| 52 | 48102100 | AGG WEDGE SHLD TYPE B | 459 | TON | $4.35 | $44.09 | $51.45 | $45.00 | $70.00 | |
| 53 | 48203029 | HMA SHOULDERS 8 | 4,991 | SQ YD | $35.74 | $39.00 | $40.40 | $32.00 | $50.00 | |
| 54 | 550A0050 | STORM SEW CL A 1 12 | 50 | FOOT | $100.00 | $110.08 | $92.50 | $100.00 | $81.00 | |
| 55 | 60200105 | CB TA 4 DIA T1F OL | 2 | EACH | $4,400.00 | $4,435.76 | $6,950.00 | $4,400.00 | $7,000.00 | |
| 56 | 60250400 | CB ADJ NEW T1F OL | 5 | EACH | $700.00 | $655.12 | $800.00 | $700.00 | $900.00 | |
| 57 | 60250500 | CB ADJ NEW T1F CL | 8 | EACH | $700.00 | $655.12 | $800.00 | $700.00 | $900.00 | |
| 58 | 60261530 | INLETS ADJ NEW T23F&G | 5 | EACH | $750.00 | $774.13 | $800.00 | $750.00 | $900.00 | |
| 59 | 60266600 | VALVE BOX ADJ | 1 | EACH | $250.00 | $275.20 | $285.00 | $250.00 | $300.00 | |
| 60 | 60300105 | FR & GRATES ADJUST | 12 | EACH | $450.00 | $340.08 | $400.00 | $450.00 | $400.00 | |
| 61 | 60300305 | FR & LIDS ADJUST | 45 | EACH | $325.00 | $327.56 | $450.00 | $325.00 | $500.00 | |
| 62 | 60404950 | FR & GRATES T24 | 3 | EACH | $475.00 | $522.58 | $450.00 | $475.00 | $500.00 | |
| 63 | 60406000 | FR & LIDS T1 OL | 12 | EACH | $325.00 | $287.56 | $385.00 | $325.00 | $400.00 | |
| 64 | 60406100 | FR & LIDS T1 CL | 23 | EACH | $325.00 | $287.56 | $385.00 | $325.00 | $400.00 | |
| 65 | 60500080 | REMOV CB - MAIN FLOW | 2 | EACH | $250.00 | $625.04 | $525.00 | $250.00 | $500.00 | |
| 66 | 66900200 | NON SPL WASTE DISPOSL | 78 | CU YD | $99.12 | $40.00 | $150.00 | $85.00 | $125.00 | |
| 67 | 66900530 | SOIL DISPOSAL ANALY | 8 | EACH | $1,350.00 | $1,816.33 | $1,200.00 | $1,800.00 | $900.00 | |
| 68 | 66901001 | REG SUB P-CONST PLAN | 1 | LSUM | $2,500.00 | $3,247.37 | $2,500.00 | $3,000.00 | $2,500.00 | |
| 69 | 66901003 | REG SUB F CON REPORT | 1 | LSUM | $1,950.00 | $990.72 | $1,400.00 | $3,000.00 | $3,000.00 | |
| 70 | 66901006 | REG SUB MON | 30 | CAL DA | $820.00 | $748.55 | $650.00 | $750.00 | $250.00 | |
| 71 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,250.00 | $3,900.00 | $2,500.00 | $1,800.00 | $4,000.00 | |
| 72 | 67100100 | MOBILIZATION | 1 | L SUM | $287,220.89 | $305,000.00 | $235,000.00 | $328,000.00 | $330,000.00 | |
| 73 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 74 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $1.00 | $55,000.00 | $226,777.00 | $1.00 | $1.00 | |
| 75 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $15,000.00 | $1.00 | $1.00 | $25,000.00 | $325,000.00 | |
| 76 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 77 | 70102634 | TR CONT & PROT 701611 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 78 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 79 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $5,000.00 | $1.00 | $1.00 | $10,000.00 | $57,000.00 | |
| 80 | 70300100 | SHORT TERM PAVT MKING | 15,398 | FOOT | $1.00 | $1.50 | $0.5000 | $1.00 | $0.9500 | |
| 81 | 70300150 | SHRT TRM PAVT MK REM | 2,567 | SQ FT | $1.59 | $1.00 | $3.00 | $1.75 | $0.0100 | |
| 82 | 70300210 | TEMP PVT MK LTR & SYM | 515 | SQ FT | $1.00 | $0.0100 | $0.0100 | $1.00 | $1.00 | |
| 83 | 70300220 | TEMP PVT MK LINE 4 | 49,412 | FOOT | $0.2000 | $0.0100 | $0.0100 | $0.2000 | $0.2000 | |
| 84 | 70300240 | TEMP PVT MK LINE 6 | 4,061 | FOOT | $0.3000 | $0.0100 | $0.0100 | $0.3000 | $0.3000 | |
| 85 | 70300250 | TEMP PVT MK LINE 8 | 601 | FOOT | $0.5000 | $0.0100 | $0.0100 | $0.5000 | $0.5000 | |
| 86 | 70300260 | TEMP PVT MK LINE 12 | 1,082 | FOOT | $1.00 | $0.0100 | $0.0100 | $1.00 | $1.00 | |
| 87 | 70300280 | TEMP PVT MK LINE 24 | 1,116 | FOOT | $1.25 | $0.0100 | $0.0100 | $1.25 | $1.25 | |
| 88 | 70300520 | PAVT MARK TAPE T3 4 | 7,699 | FOOT | $1.10 | $1.50 | $1.00 | $1.10 | $1.30 | |
| 89 | 78000100 | THPL PVT MK LTR & SYM | 515 | SQ FT | $4.70 | $4.40 | $4.00 | $4.70 | $4.70 | |
| 90 | 78000200 | THPL PVT MK LINE 4 | 49,412 | FOOT | $0.5400 | $0.5500 | $0.5000 | $0.5400 | $0.5400 | |
| 91 | 78000400 | THPL PVT MK LINE 6 | 4,061 | FOOT | $1.10 | $0.8300 | $0.7500 | $1.10 | $1.10 | |
| 92 | 78000500 | THPL PVT MK LINE 8 | 601 | FOOT | $1.20 | $1.10 | $1.00 | $1.20 | $1.20 | |
| 93 | 78000600 | THPL PVT MK LINE 12 | 1,082 | FOOT | $2.20 | $1.65 | $1.50 | $2.20 | $2.20 | |
| 94 | 78000650 | THPL PVT MK LINE 24 | 1,116 | FOOT | $4.60 | $4.40 | $4.00 | $4.60 | $4.60 | |
| 95 | 78009000 | MOD URETH PM LTR-SYM | 364 | SQ FT | $5.00 | $5.50 | $5.00 | $5.00 | $5.00 | |
| 96 | 78009004 | MOD URETH PM LINE 4 | 3,748 | FOOT | $0.6000 | $0.7200 | $0.6500 | $0.6000 | $0.6000 | |
| 97 | 78009006 | MOD URETH PM LINE 6 | 1,307 | FOOT | $0.7500 | $1.10 | $1.00 | $0.7500 | $0.7500 | |
| 98 | 78100100 | RAISED REFL PAVT MKR | 2,407 | EACH | $23.00 | $22.02 | $20.00 | $23.00 | $23.00 | |
| 99 | 78300200 | RAISED REF PVT MK REM | 2,188 | EACH | $9.54 | $10.35 | $6.50 | $9.00 | $8.49 | |
| 100 | 85000200 | MAIN EX TR SIG INSTAL | 3 | EACH | $1,190.00 | $3,000.00 | $2,100.00 | $1,190.60 | $2,100.00 | |
| 101 | 88600600 | DET LOOP REPL | 3,068 | FOOT | $15.80 | $18.38 | $16.70 | $15.80 | $16.70 | |
| 102 | 89500400 | RELOC EX PED PUSH-BUT | 1 | EACH | $480.50 | $451.33 | $410.00 | $480.50 | $410.00 | |
| 103 | 89502376 | REBUILD EX HANDHOLE | 3 | EACH | $2,084.60 | $2,399.75 | $2,180.00 | $2,084.60 | $2,180.00 | |
| 104 | 89502378 | REBLD EX HH TO HD HH | 2 | EACH | $2,074.20 | $2,862.09 | $2,600.00 | $2,074.20 | $2,600.00 |