2019-101-RS&SW
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | K-Five Construction Corporation Low bidder | $1,026,000 | ||
| 2 | Lindahl Brothers, Inc. | $1,043,464 | +1.7% | |
| 3 | Gallagher Asphalt Corporation | $1,127,127 | +9.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 K-Five Construc… | #2 Lindahl Brother… | #3 Gallagher Aspha… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0327120 | WEED CTRL NTV LSCP EN | 8.87 | ACRE | $1,023.40 | $2,400.00 | $2,400.00 | |
| 2 | X2010350 | TREE REMOV ACRES SPL | 6.74 | ACRE | $3,474.40 | $7,900.00 | $7,900.00 | |
| 3 | X2020110 | GRADING & SHAP SHLDRS | 218 | UNIT | $65.00 | $21.50 | $95.00 | |
| 4 | X7030005 | TEMP PAVT MKING REMOV | 8,836 | SQ FT | $0.0500 | $0.2000 | $0.0100 | |
| 5 | Z0030850 | TEMP INFO SIGNING | 52 | SQ FT | $20.00 | $17.00 | $17.00 | |
| 6 | Z0033700 | LONG JOINT SEALANT | 11,533 | FOOT | $2.50 | $2.19 | $2.60 | |
| 7 | 20101300 | TREE PRUN 1-10 | 20 | EACH | $134.80 | $75.00 | $75.00 | |
| 8 | 20101350 | TREE PRUN OVER 10 | 25 | EACH | $215.00 | $85.00 | $85.00 | |
| 9 | 25003115 | INTERSEED CL 1B | 8.87 | ACRE | $842.63 | $2,000.00 | $3,500.00 | |
| 10 | 40600290 | BIT MATLS TACK CT | 21,150 | POUND | $0.0100 | $0.0100 | $0.0100 | |
| 11 | 40600400 | MIX CR JTS FLANGEWYS | 47 | TON | $50.00 | $275.00 | $420.00 | |
| 12 | 40600982 | HMA SURF REM BUTT JT | 30 | SQ YD | $5.00 | $10.00 | $31.00 | |
| 13 | 40601005 | HMA REPL OVER PATCH | 387 | TON | $75.00 | $94.00 | $125.00 | |
| 14 | 40602985 | HMA BC IL-9.5 N70 | 3,510 | TON | $78.00 | $67.00 | $71.00 | |
| 15 | 40604062 | HMA SC IL-9.5 D N70 | 3,071 | TON | $80.00 | $67.00 | $76.00 | |
| 16 | 44000164 | HMA SURF REM 3 3/4 | 31,332 | SQ YD | $5.25 | $6.00 | $3.25 | |
| 17 | 44002222 | HMA RM OV PATCH 5 1/2 | 1,254 | SQ YD | $8.00 | $14.00 | $27.00 | |
| 18 | 44201749 | CL D PATCH T1 9 | 63 | SQ YD | $10.00 | $60.00 | $120.00 | |
| 19 | 44201753 | CL D PATCH T2 9 | 125 | SQ YD | $38.00 | $60.00 | $109.00 | |
| 20 | 44201757 | CL D PATCH T3 9 | 376 | SQ YD | $38.00 | $60.00 | $96.00 | |
| 21 | 44201759 | CL D PATCH T4 9 | 690 | SQ YD | $38.00 | $60.00 | $84.00 | |
| 22 | 48102100 | AGG WEDGE SHLD TYPE B | 885 | TON | $10.00 | $19.00 | $31.00 | |
| 23 | 60250200 | CB ADJUST | 11 | EACH | $355.00 | $800.00 | $305.00 | |
| 24 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $3,300.00 | $5,000.00 | $1,500.00 | |
| 25 | 67100100 | MOBILIZATION | 1 | L SUM | $60,262.04 | $55,000.00 | $68,000.00 | |
| 26 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 27 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $15,000.00 | $1.00 | $1.00 | |
| 28 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $5,000.00 | $37,455.40 | |
| 29 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | |
| 30 | 70300100 | SHORT TERM PAVT MKING | 8,219 | FOOT | $3.00 | $1.00 | $0.0100 | |
| 31 | 70300150 | SHRT TRM PAVT MK REM | 2,740 | SQ FT | $4.55 | $2.00 | $0.0100 | |
| 32 | 70300210 | TEMP PVT MK LTR & SYM | 37 | SQ FT | $0.0100 | $3.00 | $0.0100 | |
| 33 | 70300220 | TEMP PVT MK LINE 4 | 30,137 | FOOT | $0.0100 | $0.2500 | $0.0100 | |
| 34 | 70300240 | TEMP PVT MK LINE 6 | 104 | FOOT | $0.0100 | $1.50 | $0.0100 | |
| 35 | 70300260 | TEMP PVT MK LINE 12 | 160 | FOOT | $0.0100 | $1.50 | $0.0100 | |
| 36 | 70300510 | PAVT MARK TAPE T3 L&S | 37 | SQ FT | $10.00 | $5.00 | $0.0100 | |
| 37 | 70300520 | PAVT MARK TAPE T3 4 | 2,055 | FOOT | $0.9000 | $1.00 | $0.0100 | |
| 38 | 78000100 | THPL PVT MK LTR & SYM | 37 | SQ FT | $5.50 | $4.00 | $4.00 | |
| 39 | 78000200 | THPL PVT MK LINE 4 | 30,137 | FOOT | $0.7200 | $0.5500 | $0.6500 | |
| 40 | 78000400 | THPL PVT MK LINE 6 | 104 | FOOT | $1.50 | $0.7500 | $1.00 | |
| 41 | 78000600 | THPL PVT MK LINE 12 | 160 | FOOT | $2.75 | $1.50 | $4.00 | |
| 42 | 88600600 | DET LOOP REPL | 40 | FOOT | $45.00 | $45.00 | $45.00 |