2018-0148-I
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Lion Construction 1, LLC Low bidder | $193,434 | ||
| 2 | Alliance Contractors, Inc. | $602,317 | +211.4% | |
| 3 | Lorig Construction Company | $1,422,529 | +635.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Lion Constructi… | #2 Alliance Contra… | #3 Lorig Construct… |
|---|---|---|---|---|---|---|---|---|
| 1 | X5870005 | BR DK CONC CRACK SEAL | 182,473 | SQ FT | $1.00 | $3.00 | $7.25 | |
| 2 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $1.00 | $300.00 | $3,000.00 | |
| 3 | 67100100 | MOBILIZATION | 1 | L SUM | $10,949.00 | $34,093.44 | $81,000.00 | |
| 4 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $1.00 | $1.00 | $100.00 | |
| 5 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $1.00 | $1.00 | $100.00 | |
| 6 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $1.00 | $19,000.00 | $100.00 | |
| 7 | 70102632 | TR CONT & PROT 701602 | 1 | L SUM | $1.00 | $1.00 | $100.00 | |
| 8 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $100.00 | |
| 9 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $1.00 | $1.00 | $100.00 |