9Y-RS-7
- Let date
- Friday, April 27, 2018
- Contract
- 62F56 · job page
- District
- District 1
- County
- Cook, Dupage
- Highway
- Limits
- Resurfacing and pedestrian ramps on US 34 in the Village of Hinsdale.
- Classification
- ·
- Project number
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | R. W. Dunteman Company Low bidder | $1,772,682 | ||
| 2 | Arrow Road Construction Co. | $1,796,090 | +1.3% | |
| 3 | K-Five Construction Corporation | $2,045,692 | +15.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 R. W. Dunteman … | #2 Arrow Road Cons… | #3 K-Five Construc… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $5,500.00 | $6,500.00 | $5,000.00 | |
| 2 | X0325222 | WEED CONT BASAL TRTMT | 4 | GALLON | $750.00 | $750.00 | $750.00 | |
| 3 | X0327611 | REM & REIN BRIC PAVER | 100 | SQ FT | $20.00 | $10.00 | $20.00 | |
| 4 | X2700004 | PREF PL PM TB LINE 7 | 160 | FOOT | $20.00 | $20.00 | $6.00 | |
| 5 | X4060004 | P HMA SC SMA 9.5 N80 | 5,367 | TON | $90.13 | $97.70 | $88.00 | |
| 6 | X5537800 | SS CLEANED 12 | 124 | FOOT | $3.00 | $3.50 | $1.50 | |
| 7 | X6030310 | FR & LIDS ADJUST SPL | 68 | EACH | $600.00 | $600.00 | $590.00 | |
| 8 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $12,000.00 | $156,870.00 | $192,950.00 | |
| 9 | X7030005 | TEMP PAVT MKING REMOV | 14,730 | SQ FT | $0.5000 | $0.0100 | $0.0100 | |
| 10 | X7830070 | GRV RCSD PVT MRKG 5 | 160 | FOOT | $15.00 | $12.00 | $2.00 | |
| 11 | Z0001800 | APPROACH SL REP (PD) | 135 | SQ YD | $240.00 | $650.00 | $1,050.00 | |
| 12 | Z0004562 | COMB C C&G REM & REPL | 1,612 | FOOT | $31.69 | $28.08 | $30.00 | |
| 13 | Z0018500 | DRAINAGE STR CLEANED | 21 | EACH | $312.00 | $325.00 | $250.00 | |
| 14 | Z0030850 | TEMP INFO SIGNING | 104 | SQ FT | $16.00 | $15.00 | $16.00 | |
| 15 | Z0064800 | SELECTIVE CLEARING | 10 | UNIT | $300.00 | $320.00 | $320.00 | |
| 16 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 17 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 18 | 20100110 | TREE REMOV 6-15 | 120 | UNIT | $35.00 | $20.00 | $20.00 | |
| 19 | 20100210 | TREE REMOV OVER 15 | 60 | UNIT | $42.00 | $40.00 | $40.00 | |
| 20 | 20101350 | TREE PRUN OVER 10 | 10 | EACH | $200.00 | $80.00 | $80.00 | |
| 21 | 20200100 | EARTH EXCAVATION | 33 | CU YD | $44.93 | $37.60 | $180.00 | |
| 22 | 21101615 | TOPSOIL F & P 4 | 215 | SQ YD | $8.98 | $6.00 | $9.00 | |
| 23 | 25000400 | NITROGEN FERT NUTR | 3 | POUND | $4.00 | $4.00 | $4.00 | |
| 24 | 25000500 | PHOSPHORUS FERT NUTR | 3 | POUND | $4.00 | $4.00 | $4.00 | |
| 25 | 25000600 | POTASSIUM FERT NUTR | 3 | POUND | $4.00 | $4.00 | $4.00 | |
| 26 | 25200110 | SODDING SALT TOLERANT | 237 | SQ YD | $13.00 | $6.00 | $13.00 | |
| 27 | 25200200 | SUPPLE WATERING | 10 | UNIT | $75.00 | $90.00 | $75.00 | |
| 28 | 35501308 | HMA BASE CSE 6 | 9 | SQ YD | $129.98 | $110.00 | $52.00 | |
| 29 | 35501316 | HMA BASE CSE 8 | 42 | SQ YD | $75.80 | $115.00 | $80.00 | |
| 30 | 40600290 | BIT MATLS TACK CT | 36,760 | POUND | $0.0100 | $1.05 | $0.0100 | |
| 31 | 40600400 | MIX CR JTS FLANGEWYS | 83 | TON | $50.00 | $85.00 | $50.00 | |
| 32 | 40600827 | P LB MM IL-4.75 N50 | 2,260 | TON | $83.12 | $81.40 | $81.00 | |
| 33 | 40600982 | HMA SURF REM BUTT JT | 489 | SQ YD | $10.82 | $5.00 | $8.50 | |
| 34 | 40601005 | HMA REPL OVER PATCH | 1,480 | TON | $60.82 | $40.00 | $50.00 | |
| 35 | 40603335 | HMA SC "D" N50 | 6 | TON | $146.78 | $280.00 | $200.00 | |
| 36 | 42001300 | PROTECTIVE COAT | 461 | SQ YD | $1.00 | $1.04 | $1.00 | |
| 37 | 42300400 | PCC DRIVEWAY PAVT 8 | 60 | SQ YD | $72.00 | $72.80 | $80.00 | |
| 38 | 42400200 | PC CONC SIDEWALK 5 | 3,237 | SQ FT | $5.00 | $6.50 | $7.00 | |
| 39 | 42400800 | DETECTABLE WARNINGS | 266 | SQ FT | $30.00 | $29.12 | $30.00 | |
| 40 | 44000156 | HMA SURF REM 1 3/4 | 1,050 | SQ YD | $4.85 | $2.70 | $2.25 | |
| 41 | 44000159 | HMA SURF REM 2 1/2 | 53,710 | SQ YD | $5.36 | $3.10 | $6.00 | |
| 42 | 44000200 | DRIVE PAVEMENT REM | 51 | SQ YD | $14.30 | $18.72 | $85.71 | |
| 43 | 44000600 | SIDEWALK REM | 3,180 | SQ FT | $1.10 | $2.08 | $2.50 | |
| 44 | 44002214 | HMA RM OV PATCH 3 1/2 | 485 | SQ YD | $7.35 | $3.00 | $6.00 | |
| 45 | 44002236 | HMA RM OV PATCH 9 | 2,738 | SQ YD | $9.49 | $6.00 | $7.00 | |
| 46 | 44201737 | CL D PATCH T1 8 | 137 | SQ YD | $50.19 | $19.00 | $30.00 | |
| 47 | 44201741 | CL D PATCH T2 8 | 548 | SQ YD | $43.49 | $18.00 | $30.00 | |
| 48 | 44201745 | CL D PATCH T3 8 | 685 | SQ YD | $37.58 | $18.00 | $30.00 | |
| 49 | 44201747 | CL D PATCH T4 8 | 1,369 | SQ YD | $31.28 | $17.00 | $30.00 | |
| 50 | 44201798 | CL D PATCH T1 13 | 25 | SQ YD | $102.00 | $32.00 | $50.00 | |
| 51 | 44201803 | CL D PATCH T2 13 | 97 | SQ YD | $92.19 | $31.00 | $50.00 | |
| 52 | 44201807 | CL D PATCH T3 13 | 122 | SQ YD | $84.97 | $31.00 | $50.00 | |
| 53 | 44201809 | CL D PATCH T4 13 | 243 | SQ YD | $74.37 | $30.00 | $50.00 | |
| 54 | 60250200 | CB ADJUST | 4 | EACH | $325.00 | $325.00 | $325.00 | |
| 55 | 60250400 | CB ADJ NEW T1F OL | 1 | EACH | $625.00 | $625.00 | $625.00 | |
| 56 | 60252800 | CB RECONST | 2 | EACH | $1,000.00 | $1,000.00 | $1,000.00 | |
| 57 | 60255500 | MAN ADJUST | 3 | EACH | $375.00 | $375.00 | $375.00 | |
| 58 | 60260100 | INLETS ADJUST | 5 | EACH | $300.00 | $300.00 | $300.00 | |
| 59 | 60262700 | INLETS RECONST | 2 | EACH | $900.00 | $900.00 | $900.00 | |
| 60 | 60300105 | FR & GRATES ADJUST | 16 | EACH | $375.00 | $375.00 | $375.00 | |
| 61 | 60400210 | FRAMES T3 | 1 | EACH | $400.00 | $400.00 | $400.00 | |
| 62 | 60406000 | FR & LIDS T1 OL | 5 | EACH | $315.00 | $315.00 | $310.00 | |
| 63 | 60406100 | FR & LIDS T1 CL | 5 | EACH | $315.00 | $315.00 | $310.00 | |
| 64 | 66900200 | NON SPL WASTE DISPOSL | 33 | CU YD | $100.00 | $130.00 | $0.0100 | |
| 65 | 66900450 | SPL WASTE PLNS/REPORT | 1 | L SUM | $3,000.00 | $1,500.00 | $4,250.00 | |
| 66 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,450.00 | $1,700.00 | $950.00 | |
| 67 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,800.00 | $2,500.00 | $3,300.00 | |
| 68 | 67100100 | MOBILIZATION | 1 | L SUM | $103,029.60 | $126,000.00 | $125,000.00 | |
| 69 | 70300100 | SHORT TERM PAVT MKING | 17,520 | FOOT | $1.00 | $0.3500 | $1.00 | |
| 70 | 70300150 | SHRT TRM PAVT MK REM | 10,050 | SQ FT | $1.25 | $0.5500 | $2.00 | |
| 71 | 70300210 | TEMP PVT MK LTR & SYM | 580 | SQ FT | $1.00 | $0.0100 | $0.0100 | |
| 72 | 70300220 | TEMP PVT MK LINE 4 | 25,040 | FOOT | $0.1900 | $0.0100 | $0.0100 | |
| 73 | 70300240 | TEMP PVT MK LINE 6 | 3,090 | FOOT | $0.2800 | $0.0100 | $0.0100 | |
| 74 | 70300250 | TEMP PVT MK LINE 8 | 750 | FOOT | $0.4000 | $0.0100 | $0.0100 | |
| 75 | 70300260 | TEMP PVT MK LINE 12 | 920 | FOOT | $0.6000 | $0.0100 | $0.0100 | |
| 76 | 70300280 | TEMP PVT MK LINE 24 | 440 | FOOT | $1.00 | $0.0100 | $0.0100 | |
| 77 | 70300520 | PAVT MARK TAPE T3 4 | 5,840 | FOOT | $0.5500 | $1.25 | $0.5500 | |
| 78 | 70300904 | PAVT MARK TAPE T4 4 | 7,800 | FOOT | $0.8500 | $0.8500 | $0.8500 | |
| 79 | 70300908 | PAVT MARK TAPE T4 8 | 2,400 | FOOT | $1.30 | $1.05 | $1.30 | |
| 80 | 78000100 | THPL PVT MK LTR & SYM | 580 | SQ FT | $3.25 | $3.25 | $3.50 | |
| 81 | 78000200 | THPL PVT MK LINE 4 | 25,040 | FOOT | $0.5000 | $0.5000 | $0.5500 | |
| 82 | 78000400 | THPL PVT MK LINE 6 | 3,090 | FOOT | $0.7500 | $0.7500 | $0.8500 | |
| 83 | 78000500 | THPL PVT MK LINE 8 | 750 | FOOT | $1.00 | $1.00 | $1.28 | |
| 84 | 78000600 | THPL PVT MK LINE 12 | 920 | FOOT | $1.50 | $1.50 | $1.91 | |
| 85 | 78000650 | THPL PVT MK LINE 24 | 440 | FOOT | $3.25 | $3.25 | $3.50 | |
| 86 | 78008210 | POLYUREA PM T1 LN 4 | 200 | FOOT | $10.00 | $10.00 | $4.50 | |
| 87 | 78008240 | POLYUREA PM T1 LN 8 | 200 | FOOT | $20.00 | $20.00 | $9.00 | |
| 88 | 78100100 | RAISED REFL PAVT MKR | 825 | EACH | $22.00 | $22.00 | $25.50 | |
| 89 | 78300200 | RAISED REF PVT MK REM | 743 | EACH | $8.08 | $7.47 | $10.00 | |
| 90 | 85000200 | MAIN EX TR SIG INSTAL | 1 | EACH | $2,500.00 | $2,500.00 | $2,500.00 | |
| 91 | 88600600 | DET LOOP REPL | 2,503 | FOOT | $17.00 | $17.00 | $17.00 | |
| 92 | 89500400 | RELOC EX PED PUSH-BUT | 10 | EACH | $310.00 | $310.00 | $310.00 | |