3249-RS-3
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Iroquois Paving Corporation Low bidder | $3,189,418 | ||
| 2 | K-Five Construction Corporation | $3,369,550 | +5.6% | |
| 3 | D. Construction, Inc. | $3,634,690 | +14.0% | |
| 4 | Gallagher Asphalt Corporation | $3,679,278 | +15.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Iroquois Paving… | #2 K-Five Construc… | #3 D. Construction… | #4 Gallagher Aspha… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | K0026700 | TREE CARE | 5 | EACH | $140.00 | $325.00 | $154.00 | $140.00 | |
| 2 | X0100018 | TREE REMOV UNDER 6U | 70 | UNIT | $9.00 | $9.00 | $9.90 | $11.75 | |
| 3 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $5,500.00 | $3,200.00 | $10,000.00 | $23,000.00 | |
| 4 | X0327611 | REM & REIN BRIC PAVER | 730 | SQ FT | $20.00 | $20.00 | $22.00 | $20.00 | |
| 5 | X2020110 | GRADING & SHAP SHLDRS | 182 | UNIT | $41.25 | $45.00 | $30.00 | $33.00 | |
| 6 | X4060995 | TEMPORARY RAMP SPL | 275 | SQ YD | $22.00 | $75.00 | $0.0100 | $45.00 | |
| 7 | X4400501 | COMB C&G REMOV REPL < = 10FT | 400 | FOOT | $45.00 | $45.00 | $44.00 | $48.00 | |
| 8 | X5537800 | SS CLEANED 12 | 1,000 | FOOT | $2.00 | $3.00 | $3.30 | $2.00 | |
| 9 | X6030310 | FR & LIDS ADJUST SPL | 50 | EACH | $650.00 | $650.00 | $650.00 | $675.00 | |
| 10 | X7030005 | TEMP PAVT MKING REMOV | 5,900 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 11 | Z0004562 | COMB C C&G REM & REPL | 1,525 | FOOT | $36.25 | $36.00 | $40.70 | $38.00 | |
| 12 | Z0018500 | DRAINAGE STR CLEANED | 77 | EACH | $350.00 | $280.00 | $308.00 | $350.00 | |
| 13 | Z0030850 | TEMP INFO SIGNING | 102.8 | SQ FT | $18.00 | $18.00 | $25.00 | $15.00 | |
| 14 | Z0033700 | LONG JOINT SEALANT | 57,000 | FOOT | $2.15 | $2.02 | $2.13 | $2.55 | |
| 15 | Z0064800 | SELECTIVE CLEARING | 33 | UNIT | $300.00 | $300.00 | $330.00 | $460.00 | |
| 16 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 17 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | |
| 18 | 20100110 | TREE REMOV 6-15 | 175 | UNIT | $18.00 | $18.00 | $19.80 | $23.50 | |
| 19 | 20100210 | TREE REMOV OVER 15 | 250 | UNIT | $24.00 | $24.00 | $26.40 | $31.40 | |
| 20 | 20200100 | EARTH EXCAVATION | 55 | CU YD | $75.00 | $75.00 | $66.00 | $79.00 | |
| 21 | 21101615 | TOPSOIL F & P 4 | 667 | SQ YD | $6.00 | $6.00 | $6.60 | $6.00 | |
| 22 | 25000210 | SEEDING CL 2A | 1 | ACRE | $2,630.00 | $2,619.00 | $2,880.90 | $2,620.00 | |
| 23 | 25000750 | MOWING | 4 | ACRE | $350.00 | $350.00 | $385.00 | $350.00 | |
| 24 | 25100125 | MULCH METHOD 3 | 1 | ACRE | $1,780.00 | $1,755.00 | $1,930.50 | $1,755.00 | |
| 25 | 25200110 | SODDING SALT TOLERANT | 667 | SQ YD | $8.00 | $8.00 | $8.80 | $8.00 | |
| 26 | 25200200 | SUPPLE WATERING | 7 | UNIT | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 27 | 28100105 | STONE RIPRAP CL A3 | 185 | SQ YD | $77.00 | $25.00 | $55.00 | $70.00 | |
| 28 | 28200200 | FILTER FABRIC | 185 | SQ YD | $4.00 | $25.00 | $5.00 | $26.00 | |
| 29 | 35101800 | AGG BASE CSE B 6 | 380 | SQ YD | $15.85 | $27.70 | $10.00 | $24.00 | |
| 30 | 35501318 | HMA BASE CSE 8 1/2 | 380 | SQ YD | $37.00 | $54.00 | $38.00 | $45.00 | |
| 31 | 40600290 | BIT MATLS TACK CT | 72,020 | POUND | $0.0100 | $0.0100 | $0.0100 | $0.0100 | |
| 32 | 40600400 | MIX CR JTS FLANGEWYS | 153 | TON | $0.0100 | $50.00 | $0.0100 | $340.00 | |
| 33 | 40600982 | HMA SURF REM BUTT JT | 828 | SQ YD | $0.0100 | $5.00 | $0.0100 | $14.00 | |
| 34 | 40602985 | HMA BC IL-9.5 N70 | 11,196 | TON | $64.00 | $72.00 | $60.00 | $73.00 | |
| 35 | 40604062 | HMA SC IL-9.5 D N70 | 9,975 | TON | $66.00 | $78.00 | $62.00 | $74.00 | |
| 36 | 40604172 | P HMA SC IL-9.5 E N70 | 747 | TON | $88.50 | $100.00 | $81.00 | $99.00 | |
| 37 | 42001300 | PROTECTIVE COAT | 736 | SQ YD | $2.00 | $2.00 | $1.10 | $2.15 | |
| 38 | 42400200 | PC CONC SIDEWALK 5 | 5,775 | SQ FT | $6.80 | $6.00 | $9.90 | $6.40 | |
| 39 | 42400800 | DETECTABLE WARNINGS | 644 | SQ FT | $33.00 | $33.00 | $33.00 | $34.80 | |
| 40 | 44000156 | HMA SURF REM 1 3/4 | 7,614 | SQ YD | $3.15 | $1.75 | $1.75 | $2.00 | |
| 41 | 44000164 | HMA SURF REM 3 3/4 | 101,716 | SQ YD | $4.00 | $4.95 | $2.50 | $2.85 | |
| 42 | 44000200 | DRIVE PAVEMENT REM | 15 | SQ YD | $25.00 | $25.00 | $33.00 | $27.00 | |
| 43 | 44000600 | SIDEWALK REM | 5,685 | SQ FT | $2.25 | $2.25 | $2.20 | $2.40 | |
| 44 | 44003100 | MEDIAN REMOVAL | 3,415 | SQ FT | $2.85 | $6.55 | $7.00 | $4.70 | |
| 45 | 44201803 | CL D PATCH T2 13 | 2,072 | SQ YD | $30.00 | $30.00 | $50.00 | $85.00 | |
| 46 | 44201807 | CL D PATCH T3 13 | 938 | SQ YD | $30.00 | $25.00 | $45.00 | $70.00 | |
| 47 | 44201809 | CL D PATCH T4 13 | 5,910 | SQ YD | $30.00 | $20.00 | $45.00 | $55.00 | |
| 48 | 48102100 | AGG WEDGE SHLD TYPE B | 727 | TON | $31.00 | $18.00 | $23.00 | $31.00 | |
| 49 | 60250200 | CB ADJUST | 20 | EACH | $700.00 | $400.00 | $550.00 | $415.00 | |
| 50 | 60252800 | CB RECONST | 4 | EACH | $2,410.00 | $1,600.00 | $1,200.00 | $1,660.00 | |
| 51 | 60266600 | VALVE BOX ADJ | 10 | EACH | $460.00 | $250.00 | $280.00 | $260.00 | |
| 52 | 60300105 | FR & GRATES ADJUST | 20 | EACH | $750.00 | $450.00 | $650.00 | $470.00 | |
| 53 | 60404900 | FR & GRATES T12 | 6 | EACH | $760.00 | $450.00 | $600.00 | $470.00 | |
| 54 | 60404940 | FR & GRATES T23 | 2 | EACH | $760.00 | $450.00 | $400.00 | $470.00 | |
| 55 | 60404950 | FR & GRATES T24 | 4 | EACH | $830.00 | $475.00 | $400.00 | $500.00 | |
| 56 | 60406000 | FR & LIDS T1 OL | 2 | EACH | $705.00 | $350.00 | $375.00 | $370.00 | |
| 57 | 60406100 | FR & LIDS T1 CL | 2 | EACH | $705.00 | $350.00 | $375.00 | $370.00 | |
| 58 | 63000003 | SPBGR TY A 9FT POSTS | 450 | FOOT | $27.15 | $27.00 | $36.32 | $30.00 | |
| 59 | 63100167 | TR BAR TRM T1 SPL TAN | 2 | EACH | $3,115.00 | $3,100.00 | $2,542.58 | $3,750.00 | |
| 60 | 63200310 | GUARDRAIL REMOV | 550 | FOOT | $5.00 | $5.00 | $7.70 | $7.35 | |
| 61 | 66900200 | NON SPL WASTE DISPOSL | 55 | CU YD | $75.00 | $75.00 | $100.00 | $82.00 | |
| 62 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,500.00 | $1,900.00 | $1,650.00 | $1,400.00 | |
| 63 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,710.00 | $2,950.00 | $2,475.00 | $4,500.00 | |
| 64 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,210.00 | $900.00 | $2,475.00 | $200.00 | |
| 65 | 66901006 | REG SUB MON | 15 | CAL DA | $905.00 | $680.00 | $1,045.00 | $650.00 | |
| 66 | 67000400 | ENGR FIELD OFFICE A | 12 | CAL MO | $1,000.00 | $3,300.00 | $4,000.00 | $2,750.00 | |
| 67 | 67100100 | MOBILIZATION | 1 | L SUM | $180,000.00 | $194,048.71 | $150,000.00 | $210,439.76 | |
| 68 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $0.0100 | $1.00 | $0.0100 | $1.00 | |
| 69 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $0.0100 | $22,700.00 | $0.0100 | $42,000.00 | |
| 70 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $0.0100 | $1.00 | $0.0100 | $1.00 | |
| 71 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $0.0100 | $1.00 | $609,505.00 | $1.00 | |
| 72 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $0.0100 | $1.00 | $0.0100 | $1.00 | |
| 73 | 70300100 | SHORT TERM PAVT MKING | 13,568 | FOOT | $0.5000 | $0.0100 | $0.0100 | $0.7000 | |
| 74 | 70300150 | SHRT TRM PAVT MK REM | 2,261 | SQ FT | $1.80 | $0.0100 | $0.0100 | $0.0100 | |
| 75 | 70300210 | TEMP PVT MK LTR & SYM | 474 | SQ FT | $1.25 | $0.0100 | $0.0100 | $0.0100 | |
| 76 | 70300220 | TEMP PVT MK LINE 4 | 65,720 | FOOT | $0.2500 | $0.0100 | $0.0100 | $0.0100 | |
| 77 | 70300240 | TEMP PVT MK LINE 6 | 2,728 | FOOT | $0.2500 | $0.0100 | $0.0100 | $0.0100 | |
| 78 | 70300250 | TEMP PVT MK LINE 8 | 420 | FOOT | $0.5000 | $0.0100 | $0.0100 | $0.0100 | |
| 79 | 70300260 | TEMP PVT MK LINE 12 | 682 | FOOT | $0.7500 | $0.0100 | $0.0100 | $0.0100 | |
| 80 | 70300280 | TEMP PVT MK LINE 24 | 699 | FOOT | $2.00 | $0.0100 | $0.0100 | $0.0100 | |
| 81 | 70300520 | PAVT MARK TAPE T3 4 | 70,250 | FOOT | $1.15 | $0.0100 | $0.0100 | $0.0100 | |
| 82 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $30.00 | $30.00 | $48.94 | $35.00 | |
| 83 | 78000100 | THPL PVT MK LTR & SYM | 474 | SQ FT | $5.05 | $4.00 | $4.40 | $4.00 | |
| 84 | 78000200 | THPL PVT MK LINE 4 | 65,720 | FOOT | $0.6000 | $0.5500 | $0.6100 | $0.5500 | |
| 85 | 78000400 | THPL PVT MK LINE 6 | 2,728 | FOOT | $1.00 | $0.7000 | $0.8800 | $0.8000 | |
| 86 | 78000500 | THPL PVT MK LINE 8 | 420 | FOOT | $1.20 | $1.00 | $1.10 | $1.00 | |
| 87 | 78000600 | THPL PVT MK LINE 12 | 682 | FOOT | $2.50 | $1.40 | $2.20 | $2.00 | |
| 88 | 78000650 | THPL PVT MK LINE 24 | 699 | FOOT | $5.05 | $4.00 | $4.40 | $4.00 | |
| 89 | 78100100 | RAISED REFL PAVT MKR | 2,400 | EACH | $23.15 | $20.00 | $24.75 | $22.50 | |
| 90 | 78200005 | GRDRAIL REF TYPE A | 4 | EACH | $8.00 | $8.00 | $9.16 | $10.00 | |
| 91 | 78300200 | RAISED REF PVT MK REM | 1,784 | EACH | $0.0100 | $5.00 | $7.00 | $7.20 | |
| 92 | 85000200 | MAIN EX TR SIG INSTAL | 4 | EACH | $500.00 | $500.00 | $2,200.00 | $2,100.00 | |
| 93 | 88600600 | DET LOOP REPL | 2,448 | FOOT | $17.85 | $17.75 | $18.15 | $17.30 | |
| 94 | 89500400 | RELOC EX PED PUSH-BUT | 15 | EACH | $100.00 | $100.00 | $445.50 | $425.00 | |
| 95 | 89502376 | REBUILD EX HANDHOLE | 5 | EACH | $1,475.00 | $1,450.00 | $2,288.00 | $2,180.00 |