19-00265-00-RS
Bidders 8
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Arrow Road Construction Co. Low bidder | $2,086,257 | ||
| 2 | K-Five Construction Corporation | $2,151,797 | +3.1% | |
| 3 | J. A. Johnson Paving Company | $2,192,373 | +5.1% | |
| 4 | Plote Construction, Inc. | $2,195,978 | +5.3% | |
| 5 | Lindahl Brothers, Inc. | $2,216,603 | +6.2% | |
| 6 | Builders Paving, LLC | $2,293,000 | +9.9% | |
| 7 | R. W. Dunteman Company | $2,494,474 | +19.6% | |
| 8 | Brothers Asphalt Paving, Inc. | $2,558,210 | +22.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Arrow Road Cons… | #2 K-Five Construc… | #3 J. A. Johnson P… | #4 Plote Construct… | #5 Lindahl Brother… | #6 Builders Paving… | #7 R. W. Dunteman … | #8 Brothers Asphal… |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | XX008910 | PAVEMENT MARKING SPL | 232 | SQ FT | $50.00 | $20.00 | $50.00 | $50.00 | $22.50 | $50.00 | $25.00 | $22.00 | |
| 2 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $13,500.00 | $25,000.00 | $24,000.00 | $24,000.00 | $12,900.00 | $29,000.00 | $38,000.00 | $32,444.50 | |
| 3 | X0327611 | REM & REIN BRIC PAVER | 125 | SQ FT | $15.00 | $12.85 | $25.00 | $18.00 | $16.00 | $13.00 | $18.00 | $14.14 | |
| 4 | X0327618 | LANDSCAPING, SPECIAL | 1 | L SUM | $1,500.00 | $1,000.00 | $7,500.00 | $1,264.00 | $6,000.00 | $1,100.00 | $1,264.00 | $1,100.00 | |
| 5 | X1400326 | R R FL BEACON A COMP | 3 | EACH | $12,545.00 | $17,000.00 | $7,720.24 | $12,545.00 | $12,545.00 | $12,700.00 | $13,010.30 | $18,700.00 | |
| 6 | X4240800 | DETECTABLE WARN SPL | 1,450 | SQ FT | $30.00 | $30.00 | $30.00 | $30.00 | $40.00 | $31.00 | $43.00 | $45.10 | |
| 7 | X4400500 | COMB C&G REMOV SPL | 4,275 | FOOT | $7.50 | $7.50 | $7.50 | $7.50 | $5.00 | $8.00 | $9.34 | $14.30 | |
| 8 | X4401198 | HMA SURF REM VAR DP | 61,499 | SQ YD | $2.75 | $4.21 | $3.72 | $3.23 | $3.60 | $4.50 | $6.51 | $4.00 | |
| 9 | X6030310 | FR & LIDS ADJUST SPL | 162 | EACH | $635.00 | $635.00 | $665.00 | $635.00 | $665.00 | $650.00 | $665.00 | $731.50 | |
| 10 | X7200075 | REM & REIN SIGN PANEL | 19 | SQ FT | $25.00 | $18.00 | $20.00 | $20.00 | $16.00 | $16.00 | $15.00 | $27.50 | |
| 11 | X8300001 | LIGHT POLE SPECIAL | 2 | EACH | $2,662.00 | $2,662.00 | $6,367.03 | $2,662.00 | $2,662.00 | $2,700.00 | $2,707.60 | $2,387.00 | |
| 12 | Z0030850 | TEMP INFO SIGNING | 62.5 | SQ FT | $17.00 | $15.00 | $15.00 | $15.00 | $15.00 | $20.00 | $15.00 | $22.00 | |
| 13 | Z0033700 | LONG JOINT SEALANT | 40,960 | FOOT | $0.0100 | $0.5000 | $2.00 | $2.26 | $2.10 | $2.40 | $2.59 | $2.27 | |
| 14 | Z0036900 | PARK METERS REMOVED | 2 | EACH | $750.00 | $750.00 | $150.00 | $1,200.00 | $1,100.00 | $2,000.00 | $532.37 | $3,000.00 | |
| 15 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | $0.8000 | |
| 16 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 | |
| 17 | 21101615 | TOPSOIL F & P 4 | 326 | SQ YD | $3.00 | $2.05 | $6.98 | $6.00 | $12.00 | $2.10 | $6.00 | $2.25 | |
| 18 | 25200110 | SODDING SALT TOLERANT | 326 | SQ YD | $14.50 | $14.16 | $15.00 | $9.00 | $12.00 | $14.50 | $9.00 | $15.58 | |
| 19 | 25200200 | SUPPLE WATERING | 17 | UNIT | $0.0100 | $0.0100 | $25.00 | $0.0100 | $200.00 | $0.0100 | $0.0100 | $0.0200 | |
| 20 | 28000510 | INLET FILTERS | 157 | EACH | $140.00 | $140.00 | $120.00 | $140.00 | $120.00 | $140.00 | $120.00 | $132.00 | |
| 21 | 31101200 | SUB GRAN MAT B 4 | 348 | SQ YD | $7.05 | $10.00 | $13.00 | $15.00 | $8.00 | $10.00 | $13.35 | $17.21 | |
| 22 | 35102300 | AGG BASE CSE B 11 | 137 | SQ YD | $11.25 | $20.00 | $20.00 | $20.00 | $18.00 | $25.00 | $36.33 | $47.33 | |
| 23 | 35300510 | PCC BSE CSE 10 1/2 | 47 | SQ YD | $85.00 | $85.00 | $85.00 | $85.00 | $92.00 | $86.00 | $68.00 | $146.85 | |
| 24 | 40201000 | AGGREGATE-TEMP ACCESS | 30 | TON | $100.00 | $35.00 | $25.00 | $50.00 | $40.00 | $28.00 | $74.12 | $28.00 | |
| 25 | 40600290 | BIT MATLS TACK CT | 41,512 | POUND | $1.25 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.0100 | $0.9300 | $0.1000 | |
| 26 | 40600400 | MIX CR JTS FLANGEWYS | 10 | TON | $1,000.00 | $615.00 | $462.65 | $800.00 | $350.00 | $900.00 | $735.71 | $300.00 | |
| 27 | 40600982 | HMA SURF REM BUTT JT | 769 | SQ YD | $6.00 | $8.00 | $5.00 | $15.00 | $15.00 | $18.00 | $14.08 | $5.00 | |
| 28 | 40603200 | P HMA BC IL-4.75 N50 | 3,444 | TON | $90.25 | $95.00 | $99.95 | $91.00 | $88.50 | $95.00 | $95.84 | $95.00 | |
| 29 | 40604062 | HMA SC IL-9.5 D N70 | 6,888 | TON | $81.25 | $85.00 | $78.20 | $79.00 | $78.00 | $75.00 | $83.76 | $83.00 | |
| 30 | 42300500 | PCC DRIVEWAY PAVT 9 | 151 | SQ YD | $81.00 | $81.00 | $81.00 | $81.00 | $85.00 | $82.00 | $55.00 | $67.98 | |
| 31 | 42400200 | PC CONC SIDEWALK 5 | 16,857 | SQ FT | $6.50 | $6.50 | $6.50 | $6.50 | $7.00 | $6.60 | $6.25 | $12.04 | |
| 32 | 44000100 | PAVEMENT REM | 84 | SQ YD | $22.00 | $22.00 | $22.00 | $22.00 | $20.00 | $23.00 | $37.71 | $20.00 | |
| 33 | 44000200 | DRIVE PAVEMENT REM | 151 | SQ YD | $17.60 | $17.60 | $17.60 | $17.60 | $18.00 | $18.00 | $19.98 | $67.98 | |
| 34 | 44000600 | SIDEWALK REM | 16,450 | SQ FT | $2.10 | $2.10 | $2.10 | $2.10 | $2.00 | $2.20 | $1.59 | $3.63 | |
| 35 | 44003100 | MEDIAN REMOVAL | 1,208 | SQ FT | $3.00 | $3.00 | $3.00 | $3.00 | $5.00 | $3.10 | $2.60 | $8.58 | |
| 36 | 44200164 | PAVT PATCH T1 14 | 52 | SQ YD | $205.00 | $65.00 | $100.00 | $125.00 | $145.00 | $164.00 | $183.29 | $140.00 | |
| 37 | 44200168 | PAVT PATCH T2 14 | 436 | SQ YD | $150.00 | $65.00 | $100.00 | $115.00 | $145.00 | $165.00 | $137.55 | $140.00 | |
| 38 | 48301000 | PROTECTIVE COAT | 6,833 | SQ YD | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $0.7500 | $2.20 | |
| 39 | 60250200 | CB ADJUST | 7 | EACH | $350.00 | $350.00 | $400.00 | $350.00 | $400.00 | $360.00 | $400.00 | $440.00 | |
| 40 | 60255500 | MAN ADJUST | 1 | EACH | $500.00 | $500.00 | $515.00 | $500.00 | $515.00 | $540.00 | $515.00 | $566.50 | |
| 41 | 60500205 | FILL CATCH BAS | 1 | EACH | $400.00 | $400.00 | $525.00 | $400.00 | $525.00 | $430.00 | $525.00 | $577.50 | |
| 42 | 60603800 | COMB CC&G TB6.12 | 4,318 | FOOT | $24.00 | $35.00 | $24.00 | $38.00 | $33.50 | $27.00 | $25.00 | $36.52 | |
| 43 | 60618760 | CONC MED TM4.12 | 618 | SQ FT | $17.00 | $17.00 | $17.00 | $17.00 | $20.00 | $18.00 | $16.00 | $32.23 | |
| 44 | 60619600 | CONC MED TSB6.12 | 240 | SQ FT | $18.00 | $18.00 | $18.00 | $18.00 | $20.00 | $19.00 | $19.00 | $34.76 | |
| 45 | 66900200 | NON SPL WASTE DISPOSL | 5 | CU YD | $180.00 | $250.00 | $400.00 | $275.00 | $125.00 | $240.00 | $187.48 | $540.00 | |
| 46 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,700.00 | $1,952.75 | $1,500.00 | $1,700.00 | $1,450.00 | $1,750.00 | $1,500.00 | $1,518.00 | |
| 47 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $3,100.00 | $2,950.00 | $3,200.00 | $2,850.00 | $2,000.00 | $2,500.00 | $3,200.00 | $3,080.00 | |
| 48 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $200.00 | $900.00 | $200.00 | $1,200.00 | $1,330.00 | $2,200.00 | $200.00 | $2,420.00 | |
| 49 | 66901006 | REG SUB MON | 4 | CAL DA | $800.00 | $680.00 | $780.00 | $700.00 | $680.00 | $700.00 | $780.00 | $990.00 | |
| 50 | 67100100 | MOBILIZATION | 1 | L SUM | $135,500.00 | $97,000.30 | $131,000.00 | $130,000.00 | $125,000.00 | $137,400.00 | $149,988.24 | $75,329.00 | |
| 51 | 70102620 | TR CONT & PROT 701501 | 1 | L SUM | $30,000.00 | $25,000.00 | $42,885.00 | $22,795.00 | $45,000.00 | $30,333.95 | $12,999.00 | $13,475.00 | |
| 52 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $2,000.00 | $1.00 | $13,475.00 | |
| 53 | 70102640 | TR CONT & PROT 701801 | 1 | L SUM | $4,000.00 | $1.00 | $1.00 | $1.00 | $1.00 | $2,000.00 | $1.00 | $13,457.00 | |
| 54 | 70300100 | SHORT TERM PAVT MKING | 8,987 | FOOT | $0.4000 | $0.0100 | $0.7500 | $0.0100 | $0.8000 | $1.40 | $1.31 | $1.90 | |
| 55 | 70300150 | SHRT TRM PAVT MK REM | 999 | SQ FT | $2.00 | $0.0100 | $1.00 | $2.99 | $1.00 | $1.50 | $2.39 | $2.00 | |
| 56 | 70300210 | TEMP PVT MK LTR & SYM | 695 | SQ FT | $0.0100 | $0.0100 | $0.0100 | $3.75 | $1.00 | $1.25 | $3.75 | $1.65 | |
| 57 | 70300220 | TEMP PVT MK LINE 4 | 21,472 | FOOT | $0.0100 | $0.0100 | $0.2000 | $0.2000 | $0.4000 | $0.2000 | $0.2000 | $0.3300 | |
| 58 | 70300240 | TEMP PVT MK LINE 6 | 1,776 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.3000 | $0.6000 | $0.2600 | $0.3000 | $0.5500 | |
| 59 | 70300260 | TEMP PVT MK LINE 12 | 5,508 | FOOT | $0.0100 | $0.0100 | $0.0100 | $0.6000 | $1.00 | $0.7000 | $0.6000 | $0.8200 | |
| 60 | 70300280 | TEMP PVT MK LINE 24 | 969 | FOOT | $0.0100 | $0.0100 | $0.0100 | $1.20 | $1.50 | $1.25 | $1.20 | $1.65 | |
| 61 | 72000100 | SIGN PANEL T1 | 50 | SQ FT | $30.00 | $17.50 | $17.50 | $17.50 | $28.00 | $17.00 | $17.50 | $38.50 | |
| 62 | 72400310 | REMOV SIGN PANEL T1 | 25 | SQ FT | $10.00 | $6.00 | $15.50 | $30.00 | $6.00 | $12.00 | $12.00 | $66.00 | |
| 63 | 72800100 | TELES STL SIN SUPPORT | 96 | FOOT | $11.00 | $15.50 | $20.00 | $15.50 | $12.50 | $15.00 | $15.50 | $20.90 | |
| 64 | 78000100 | THPL PVT MK LTR & SYM | 695 | SQ FT | $4.00 | $4.00 | $4.00 | $4.00 | $3.52 | $4.00 | $4.00 | $5.77 | |
| 65 | 78000200 | THPL PVT MK LINE 4 | 21,472 | FOOT | $0.5500 | $0.5500 | $0.5500 | $0.5500 | $0.4200 | $0.5500 | $0.5500 | $0.6600 | |
| 66 | 78000400 | THPL PVT MK LINE 6 | 1,776 | FOOT | $0.7500 | $0.7500 | $0.7500 | $0.7500 | $1.30 | $0.7500 | $0.7500 | $1.21 | |
| 67 | 78000600 | THPL PVT MK LINE 12 | 5,508 | FOOT | $1.50 | $1.50 | $1.50 | $1.50 | $1.20 | $1.50 | $1.50 | $2.42 | |
| 68 | 78000650 | THPL PVT MK LINE 24 | 969 | FOOT | $4.00 | $4.00 | $4.00 | $4.00 | $3.52 | $4.00 | $4.00 | $5.77 | |
| 69 | 85000200 | MAIN EX TR SIG INSTAL | 11 | EACH | $1,050.00 | $1,050.00 | $1,727.55 | $1,050.00 | $1,050.00 | $1,200.00 | $1,376.30 | $2,530.00 | |
| 70 | 88600600 | DET LOOP REPL | 3,726 | FOOT | $15.90 | $15.90 | $18.62 | $15.90 | $15.90 | $16.00 | $15.60 | $18.09 | |
| 71 | 89502376 | REBUILD EX HANDHOLE | 11 | EACH | $2,267.00 | $2,267.00 | $1,681.02 | $2,267.00 | $2,267.00 | $2,300.00 | $1,954.00 | $2,530.00 |