MORAINE VIEW 2021
- Let date
- Friday, March 5, 2021
- Contract
- 46927 · job page
- District
- District 5
- County
- Mclean
- Highway
- Limits
- The work includes HMA resurfacing of roadway and parking areas, striping of of parking areas, sign replacements, aggregate resurfacing of camp sites and hunting lots, guardrail replacement, concrete barrier wall construction, and other misc. improvement items at Moraine View State Recreation Area (IDNR) in LeRoy, McLean County.
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | H. J. Eppel & Co. Low bidder | $2,654,792 | ||
| 2 | Rowe Construction, a div of UCM, Inc. | $3,296,503 | +24.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 H. J. Eppel & C… | #2 Rowe Constructi… |
|---|---|---|---|---|---|---|---|
| 1 | LR631020 | TRAF BAR TERM T1 | 5 | EACH | $2,215.00 | $1,680.00 | |
| 2 | X0300019 | REM REIN PARKING BLKS | 260 | EACH | $75.00 | $106.21 | |
| 3 | X0300266 | WOODEN FENCE REMOV | 1,420 | FOOT | $6.75 | $15.22 | |
| 4 | X0301430 | PREC CONC PARK BLOCK | 70 | EACH | $118.00 | $160.84 | |
| 5 | X1200108 | INLET BOX SPL | 6 | EACH | $1,500.00 | $6,300.00 | |
| 6 | X4401198 | HMA SURF REM VAR DP | 1,462 | SQ YD | $15.00 | $14.52 | |
| 7 | X6060505 | CONC CURB SPL | 30 | FOOT | $40.00 | $110.25 | |
| 8 | X6370050 | CONC BAR WALL SPL | 1,333 | FOOT | $182.00 | $283.50 | |
| 9 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $24,500.00 | $27,162.82 | |
| 10 | X7300105 | WOOD SIN SUPPORT SPL | 256 | FOOT | $72.65 | $74.03 | |
| 11 | X7830070 | GRV RCSD PVT MRKG 5 | 7,276 | FOOT | $2.42 | $2.47 | |
| 12 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $23,000.00 | $18,000.00 | |
| 13 | Z0018500 | DRAINAGE STR CLEANED | 4 | EACH | $1,650.00 | $1,923.59 | |
| 14 | Z0021400 | EXPANSION JOINT SPL | 59 | FOOT | $78.00 | $94.50 | |
| 15 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 16 | 20100110 | TREE REMOV 6-15 | 80 | UNIT | $21.00 | $52.65 | |
| 17 | 20200100 | EARTH EXCAVATION | 645 | CU YD | $56.00 | $39.47 | |
| 18 | 20400800 | FURNISHED EXCAVATION | 337 | CU YD | $58.00 | $59.03 | |
| 19 | 20800150 | TRENCH BACKFILL | 100 | CU YD | $49.00 | $64.18 | |
| 20 | 21400100 | GRADING & SHAP DITCH | 1,070 | FOOT | $10.00 | $5.54 | |
| 21 | 25000210 | SEEDING CL 2A | 0.25 | ACRE | $1,377.00 | $6,300.00 | |
| 22 | 25000400 | NITROGEN FERT NUTR | 14 | POUND | $13.20 | $4.20 | |
| 23 | 25000500 | PHOSPHORUS FERT NUTR | 14 | POUND | $13.20 | $4.20 | |
| 24 | 25000600 | POTASSIUM FERT NUTR | 14 | POUND | $13.20 | $4.20 | |
| 25 | 25100115 | MULCH METHOD 2 | 0.25 | ACRE | $3,621.00 | $2,100.00 | |
| 26 | 28000250 | TEMP EROS CONTR SEED | 16 | POUND | $7.50 | $6.02 | |
| 27 | 28000305 | TEMP DITCH CHECKS | 30 | FOOT | $11.60 | $12.44 | |
| 28 | 28000400 | PERIMETER EROS BAR | 61 | FOOT | $4.50 | $9.89 | |
| 29 | 28000500 | INLET & PIPE PROTECT | 30 | EACH | $150.00 | $155.80 | |
| 30 | 28100205 | STONE RIPRAP CL A3 | 2,084 | TON | $73.00 | $76.32 | |
| 31 | 31100300 | SUB GRAN MAT A 4 | 1,147 | SQ YD | $10.00 | $22.05 | |
| 32 | 35100700 | AGG BASE CSE A 8 | 474 | SQ YD | $21.50 | $41.34 | |
| 33 | 35101582 | AGG BASE CSE B 2 | 49 | SQ YD | $6.00 | $31.41 | |
| 34 | 35101800 | AGG BASE CSE B 6 | 366 | SQ YD | $16.80 | $13.74 | |
| 35 | 40200800 | AGG SURF CSE B | 2,536 | TON | $59.00 | $75.00 | |
| 36 | 40600290 | BIT MATLS TACK CT | 40,363 | POUND | $1.35 | $1.00 | |
| 37 | 40600400 | MIX CR JTS FLANGEWYS | 47 | TON | $190.00 | $561.96 | |
| 38 | 40600982 | HMA SURF REM BUTT JT | 145 | SQ YD | $12.75 | $17.61 | |
| 39 | 40600990 | TEMPORARY RAMP | 61 | SQ YD | $22.00 | $24.09 | |
| 40 | 40602965 | HMA BC IL-9.5FG N50 | 4,371 | TON | $112.00 | $130.00 | |
| 41 | 40604050 | HMA SC IL-9.5 C N50 | 4,203 | TON | $110.00 | $130.00 | |
| 42 | 42100390 | CONT REINF PCC PVT 15 | 1,162 | SQ YD | $145.00 | $176.40 | |
| 43 | 42100615 | PAVT REINFORCEMENT | 1,162 | SQ YD | $85.00 | $84.00 | |
| 44 | 42101300 | PROTECTIVE COAT | 1,640 | SQ YD | $2.50 | $0.0500 | |
| 45 | 42400300 | PC CONC SIDEWALK 6 | 433 | SQ FT | $10.75 | $17.39 | |
| 46 | 42400800 | DETECTABLE WARNINGS | 52 | SQ FT | $20.00 | $43.07 | |
| 47 | 44000100 | PAVEMENT REM | 1,039 | SQ YD | $12.35 | $13.23 | |
| 48 | 44000600 | SIDEWALK REM | 433 | SQ FT | $3.70 | $5.55 | |
| 49 | 44201305 | CL C PATCH T2 6 | 189 | SQ YD | $65.00 | $111.30 | |
| 50 | 44201705 | CL D PATCH T2 5 | 2,238 | SQ YD | $55.00 | $85.00 | |
| 51 | 48102100 | AGG WEDGE SHLD TYPE B | 1,119 | TON | $43.00 | $53.55 | |
| 52 | 50105220 | PIPE CULVERT REMOV | 1,177 | FOOT | $5.60 | $19.72 | |
| 53 | 542A0217 | P CUL CL A 1 12 | 64 | FOOT | $71.00 | $41.24 | |
| 54 | 542A0220 | P CUL CL A 1 15 | 868 | FOOT | $81.00 | $47.74 | |
| 55 | 542A0223 | P CUL CL A 1 18 | 24 | FOOT | $88.50 | $58.41 | |
| 56 | 542A0229 | P CUL CL A 1 24 | 80 | FOOT | $105.00 | $78.40 | |
| 57 | 542A0235 | P CUL CL A 1 30 | 104 | FOOT | $130.00 | $121.24 | |
| 58 | 54213447 | END SECTIONS 12 | 6 | EACH | $500.00 | $525.00 | |
| 59 | 54213657 | PRC FLAR END SEC 12 | 6 | EACH | $910.00 | $1,003.50 | |
| 60 | 54213660 | PRC FLAR END SEC 15 | 42 | EACH | $985.00 | $1,036.36 | |
| 61 | 54213663 | PRC FLAR END SEC 18 | 2 | EACH | $1,125.00 | $1,102.09 | |
| 62 | 54213669 | PRC FLAR END SEC 24 | 6 | EACH | $1,360.00 | $1,228.67 | |
| 63 | 54213675 | PRC FLAR END SEC 30 | 4 | EACH | $1,700.00 | $1,819.06 | |
| 64 | 56109210 | WATER VALVES ADJUST | 1 | EACH | $280.00 | $336.67 | |
| 65 | 60100945 | PIPE DRAINS 12 | 69 | FOOT | $50.00 | $105.00 | |
| 66 | 61000050 | CONC THRUST BLOCKS | 6 | EACH | $360.00 | $735.00 | |
| 67 | 63000001 | SPBGR TY A 6FT POSTS | 1,887.5 | FOOT | $24.75 | $25.20 | |
| 68 | 63000035 | BCK SD PROT OF GRDRL | 62 | FOOT | $31.00 | $12.60 | |
| 69 | 63000370 | LSG OVER CUL 25' SPAN | 100 | FOOT | $36.00 | $26.25 | |
| 70 | 63100045 | TRAF BAR TERM T2 | 5 | EACH | $1,340.00 | $1,260.00 | |
| 71 | 63100085 | TRAF BAR TERM T6 | 2 | EACH | $4,120.00 | $3,360.00 | |
| 72 | 63200310 | GUARDRAIL REMOV | 3,355 | FOOT | $3.25 | $9.78 | |
| 73 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $3,800.00 | $5,994.23 | |
| 74 | 67100100 | MOBILIZATION | 1 | L SUM | $19,850.00 | $100,000.00 | |
| 75 | 72000100 | SIGN PANEL T1 | 109 | SQ FT | $38.10 | $38.85 | |
| 76 | 72400100 | REMOV SIN PAN ASSY TA | 41 | EACH | $56.65 | $57.75 | |
| 77 | 72501000 | TERMINAL MARKER - DA | 10 | EACH | $51.50 | $26.25 | |
| 78 | 78000100 | THPL PVT MK LTR & SYM | 108 | SQ FT | $14.50 | $14.76 | |
| 79 | 78000200 | THPL PVT MK LINE 4 | 7,276 | FOOT | $2.45 | $2.47 | |
| 80 | 78200006 | GRDRAIL REF TYPE B | 36 | EACH | $10.30 | $10.50 |