M-W COUNTY O&C 2020
- Let date
- Friday, June 12, 2026
- Contract
- 46918 · job page
- District
- District 4
- County
- Marshall, Woodford
- Highway
- Limits
- Reconstruction of SFWA roads with a Bituminous Surface Treatment_with Fog Seal Surface, the excavation and reconstruction at sinkhole locations in the Woodford State Fish and Wildlife Area (SFWA). Placement of a Bituminous Surface Treatment with Fog Seal Surface on the parking lot and camp road are proposed at the Marshall SFWA. Other necessary work at the two locations is included. 0.9 mile gross length.
- Classification
- ·
- Project number
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Phoenix Corporation of the Quad Cities Low bidder | $923,507 | ||
| 2 | Otto Baum Company, Inc. | $1,069,500 | +15.8% | |
| 3 | Stark Excavating, Inc. | $1,356,536 | +46.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Phoenix Corpora… | #2 Otto Baum Compa… | #3 Stark Excavatin… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0300019 | REM REIN PARKING BLKS | 47 | EACH | $120.00 | $112.47 | $94.00 | |
| 2 | X0301339 | REM EX PARKING BLOCKS | 15 | EACH | $41.00 | $88.98 | $120.00 | |
| 3 | X0301430 | PREC CONC PARK BLOCK | 28 | EACH | $140.00 | $135.83 | $130.00 | |
| 4 | X0326806 | WASHOUT BASIN | 1 | L SUM | $1,500.00 | $4,295.92 | $2,700.00 | |
| 5 | X1500006 | BIT SURF TREATMNT A3 | 12,997 | SQ YD | $13.25 | $21.84 | $21.00 | |
| 6 | X2020410 | EARTH EXCAVATION SPL | 351 | CU YD | $51.50 | $92.41 | $51.00 | |
| 7 | X2600016 | MINOR SIGN COMPLETE | 30 | EACH | $250.00 | $795.00 | $980.00 | |
| 8 | X2800400 | PERIMETER EROS BAR SP | 702 | FOOT | $18.00 | $14.57 | $6.50 | |
| 9 | X4060107 | BIT MATLS FS | 5,850 | POUND | $1.65 | $4.39 | $4.30 | |
| 10 | X6050218 | FILL EX SEPTIC TANK | 3 | EACH | $2,700.00 | $4,793.83 | $3,000.00 | |
| 11 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $8,100.00 | $9,456.22 | $10,000.00 | |
| 12 | Z0007601 | BLDG REMOV NO 1 | 1 | L SUM | $1,850.00 | $2,685.20 | $5,400.00 | |
| 13 | Z0007602 | BLDG REMOV NO 2 | 1 | L SUM | $1,850.00 | $2,685.20 | $3,800.00 | |
| 14 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $10,500.00 | $7,051.14 | $19,500.00 | |
| 15 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 16 | 20100110 | TREE REMOV 6-15 | 60 | UNIT | $65.00 | $61.93 | $69.00 | |
| 17 | 20100210 | TREE REMOV OVER 15 | 221 | UNIT | $81.00 | $95.27 | $76.00 | |
| 18 | 20800150 | TRENCH BACKFILL | 5 | CU YD | $126.00 | $145.64 | $33.00 | |
| 19 | 21001000 | GEOTECH FAB F/GR STAB | 311 | SQ YD | $2.00 | $6.04 | $5.60 | |
| 20 | 21101600 | TOPSOIL F & P VAR DP | 830 | SQ YD | $8.00 | $20.50 | $165.00 | |
| 21 | 21400100 | GRADING & SHAP DITCH | 510 | FOOT | $17.00 | $15.06 | $20.00 | |
| 22 | 25000115 | SEEDING CL 1B | 0.655 | ACRE | $18,000.00 | $9,554.12 | $15,000.00 | |
| 23 | 25000400 | NITROGEN FERT NUTR | 60 | POUND | $10.00 | $13.06 | $3.10 | |
| 24 | 25000600 | POTASSIUM FERT NUTR | 60 | POUND | $10.00 | $13.06 | $3.10 | |
| 25 | 25100105 | MULCH METHOD 1 | 0.655 | ACRE | $8,000.00 | $9,554.12 | $4,700.00 | |
| 26 | 28000250 | TEMP EROS CONTR SEED | 34 | POUND | $5.00 | $5.04 | $5.10 | |
| 27 | 28000305 | TEMP DITCH CHECKS | 24 | FOOT | $23.00 | $31.01 | $12.00 | |
| 28 | 28000500 | INLET & PIPE PROTECT | 5 | EACH | $250.00 | $177.60 | $170.00 | |
| 29 | 28100705 | STONE DUMP RIP CL A3 | 1,140 | SQ YD | $65.00 | $30.46 | $35.00 | |
| 30 | 28200200 | FILTER FABRIC | 1,502 | SQ YD | $2.00 | $3.70 | $2.90 | |
| 31 | 31100300 | SUB GRAN MAT A 4 | 444 | SQ YD | $14.50 | $13.46 | $42.00 | |
| 32 | 31101900 | SUB GRAN MAT C | 371 | TON | $75.00 | $64.08 | $60.00 | |
| 33 | 35100500 | AGG BASE CSE A 6 | 11 | SQ YD | $53.25 | $65.99 | $31.00 | |
| 34 | 35100700 | AGG BASE CSE A 8 | 167 | SQ YD | $44.50 | $32.92 | $51.00 | |
| 35 | 35800100 | PREPARATION OF BASE | 11,975 | SQ YD | $4.50 | $3.06 | $3.00 | |
| 36 | 35800200 | AGG BASE REPAIR | 216 | TON | $48.00 | $54.54 | $55.00 | |
| 37 | 40200800 | AGG SURF COURSE TY B | 2,699 | TON | $56.50 | $70.89 | $84.00 | |
| 38 | 42000200 | PCC PVT 7 | 409 | SQ YD | $102.50 | $108.12 | $180.00 | |
| 39 | 42400200 | PC CONC SIDEWALK 5 | 966 | SQ FT | $17.50 | $16.82 | $29.00 | |
| 40 | 44000100 | PAVEMENT REM | 67 | SQ YD | $14.00 | $38.26 | $32.00 | |
| 41 | 44000600 | SIDEWALK REM | 1,281 | SQ FT | $4.00 | $2.34 | $5.00 | |
| 42 | 50105220 | PIPE CULVERT REMOV | 107 | FOOT | $35.00 | $55.94 | $27.00 | |
| 43 | 50201121 | COFFERDAM TYP 2 LOC 1 | 1 | EACH | $22,500.00 | $0.1100 | $0.0100 | |
| 44 | 50201122 | COFFERDAM TYP 2 LOC 2 | 1 | EACH | $22,500.00 | $0.1100 | $0.0100 | |
| 45 | 542A8245 | P CUL CL A 2 EQRS 60 | 40 | FOOT | $400.00 | $529.33 | $770.00 | |
| 46 | 542C0217 | P CUL CL C 1 12 | 70 | FOOT | $46.00 | $40.43 | $64.00 | |
| 47 | 54213669 | PRC FLAR END SEC 24 | 1 | EACH | $1,500.00 | $1,715.43 | $2,000.00 | |
| 48 | 54214545 | PRC FL END S EQ RS 60 | 2 | EACH | $10,500.00 | $9,596.19 | $12,000.00 | |
| 49 | 54262712 | METAL FL END SEC 12" | 2 | EACH | $400.00 | $750.92 | $1,400.00 | |
| 50 | 59300100 | CONTR LOW-STRENG MATL | 30 | CU YD | $350.00 | $150.97 | $110.00 | |
| 51 | 63000001 | SPBGR TY A 6FT POSTS | 202 | FOOT | $60.50 | $63.14 | $70.00 | |
| 52 | 63200310 | GUARDRAIL REMOV | 85 | FOOT | $7.00 | $10.13 | $52.00 | |
| 53 | 67000500 | ENGR FIELD OFFICE B | 3 | CAL MO | $3,200.00 | $1,700.00 | $2,100.00 | |
| 54 | 67100100 | MOBILIZATION | 1 | L SUM | $52,000.00 | $98,137.25 | $170,000.00 | |
| 55 | 72000100 | SIGN PANEL T1 | 28.4 | SQ FT | $47.00 | $52.24 | $51.00 | |
| 56 | 72400310 | REMOV SIGN PANEL T1 | 4.5 | SQ FT | $18.00 | $184.54 | $29.00 | |
| 57 | 72400710 | RELOC SIGN PANEL T1 | 0.25 | SQ FT | $50.00 | $329.76 | $1,000.00 | |
| 58 | 73000100 | WOOD SIN SUPPORT | 148 | FOOT | $55.00 | $37.61 | $37.00 | |
| 59 | 78001100 | PT PVT MK LTRS & SYMB | 22.4 | SQ FT | $40.00 | $10.45 | $10.00 | |
| 60 | 78001110 | PAINT PVT MK LINE 4 | 1,906 | FOOT | $4.00 | $1.57 | $1.50 |