IDOT Bid Averages

13,847 bid codes Sign up free

Average unit prices · Statewide

ExcelCSV
Bid codeDescriptionUnitJobs ▼QuantityAvg low bidAvg all bidsAvg estimateLow rangeLast let
X2111000TOPSOIL EXCAVATIONCU YD 912,392 $25.77$23.61— $0.0100 – $50.00Jan 16, 2026
X2111100TOPSOIL EXC & PLAC SPCU YD 925,302.2 $11.69$22.05— $5.00 – $300.00Aug 1, 2025
X2300019REAT/RLGN TRM/RL PLTSEACH 9262 $859.43$820.03— $685.00 – $1,100.00Sep 18, 2026
X2503318INTERSEED CL 4B MODACRE 9119.68 $2,260.08$2,553.57— $1,400.00 – $13,450.00Nov 8, 2024
X2503323INTERSEED CL 5A MODACRE 931.225 $4,488.53$4,320.10— $1,075.00 – $7,363.40Jun 12, 2026
X2700005PREF PL PM TB IL LN 7FOOT 913,302 $5.48$6.93— $4.99 – $17.25Nov 5, 2021
X2810212STONE RIPRAP CL A6 SPTON 97,070 $85.05$132.57— $70.00 – $290.00Jan 16, 2026
X2810228STONE RIPRAP CL B4 SPTON 96,965 $129.04$126.84— $73.50 – $391.77Jun 12, 2026
X3000001RRPM PROTECTIONEACH 93,187 $22.14$22.64— $2.00 – $50.00Apr 24, 2026
X4020900AGG SURF CSE B SPLSQ YD 919,113 $6.17$7.55— $3.00 – $45.00Jan 16, 2026
X4060006P HMA SC SMA 12.5 N80TON 9126,839 $113.01$113.70— $95.00 – $472.62Jan 17, 2020
X4080052INCIDENTL HMA SURF SPTON 91,604 $244.28$259.58— $98.77 – $950.21Apr 25, 2025
X4400060BRICK SIDEWALK REMSQ FT 943,452 $3.28$4.97— $2.00 – $6.05Apr 24, 2026
X4406630PART DEP REM T4 3SQ YD 911,840 $40.32$35.46— $13.00 – $85.00Dec 13, 2024
X4406812PCC SURF REM 1 1/2SQ YD 95,300 $17.86$14.65— $8.50 – $64.82Jul 31, 2026
X4420549CL A PATCH T4 9 SPLSQ YD 932,601 $211.41$253.74— $112.20 – $549.51Apr 25, 2025
X4420587CL A PATCH T4 13 SPLSQ YD 99,609.7 $194.90$238.56— $134.20 – $326.00Apr 24, 2026
X4420624CL A PATCH T3 14 SPLSQ YD 9599 $277.52$282.46— $177.10 – $393.80Apr 24, 2026
X4420630CL A PATCH T2 15 SPLSQ YD 91,123 $272.75$282.06— $180.00 – $1,150.00Feb 27, 2026
X4420684CL B PATCH T4 10 SPLSQ YD 93,060 $127.65$174.06— $61.50 – $355.00Apr 24, 2026
X4421825CL D PTCH T1 9 SPLSQ YD 9387 $171.60$195.00— $75.00 – $500.00Apr 26, 2024
X4510050HFST CRACK FILLINGFOOT 920,049 $5.10$6.05— $0.5000 – $68.25Apr 25, 2025
X4811300AGGREGATE SHLDS B SPLTON 911,409 $31.37$39.43— $18.00 – $132.00Apr 24, 2026
X5020100AGG COLUMN GRND IMPRVL SUM 99 $1,529,249.68$1,258,942.18— $174,554.45 – $5,000,000.00Jul 31, 2026
X5510310SAN SEW REMOV 10FOOT 93,158 $43.84$55.75— $1.00 – $280.00Apr 24, 2026
X5610660WATER MAIN ABANDON 10FOOT 911,565 $12.21$18.77— $4.40 – $115.00Feb 27, 2026
X5620040WAT SER CONN 2EACH 913 $5,166.71$6,134.87— $745.19 – $14,500.00Jun 12, 2026
X5620128ADJ WATER SERV LINESEACH 9170 $849.24$469.39— $1.00 – $3,150.00Mar 7, 2025
X5630716CONN TO EX W MAIN 16EACH 920 $9,642.57$7,665.47— $1,599.00 – $15,500.00Jun 12, 2026
X5800110MEMBRANE WATERPRF SPLSQ FT 971,127 $18.69$21.28— $5.00 – $47.14Sep 19, 2025
X6010302TRENCH DRAINFOOT 91,136 $316.83$342.02— $200.00 – $545.00Jan 16, 2026
X6022055MAN TA 6 DIA T11VF&GEACH 919 $7,909.21$8,121.12— $4,000.00 – $12,900.00Feb 27, 2026
X6022312DROP SAN MAN T1F CLEACH 919 $26,290.85$24,329.21— $8,180.00 – $43,220.00Jun 12, 2026
X6022402MAN TA 4D T1F CL SPLEACH 942 $3,380.61$4,302.52— $1,560.00 – $7,950.00Jun 17, 2022
X6060045COMB CC&G TBV.12 (CDOT)FOOT 95,847.5 $48.56$58.75— $28.92 – $105.00Jun 12, 2026
X6061310CONC MEDIAN SURF 4 SPSQ FT 9134,842 $7.86$10.20— $0.0100 – $20.00Sep 19, 2025
X6300224RETURN END SECTIONEACH 940 $200.30$236.93— $118.67 – $250.00Sep 18, 2026
X6300620THRIE-BM MOD BLOCKEACH 962 $56.42$96.62— $25.00 – $85.00Sep 18, 2026
X6300630THRIE-BEAM POSTEACH 962 $203.14$230.51— $168.00 – $240.00Sep 18, 2026
X6300640THRIE-BM RADI ELE PLTEACH 935 $302.40$316.94— $227.47 – $350.00Sep 18, 2026
X6310163TRAF BAR TERM T1 NOSEEACH 988 $374.68$386.36— $268.00 – $807.81Sep 18, 2026
X6310177TRAF BAR TERM T3 SPLEACH 935 $1,483.21$1,337.54— $800.00 – $2,948.13Sep 18, 2026
X6310203TBT T3 SPL NOSEEACH 926 $358.04$369.80— $250.00 – $541.32Sep 18, 2026
X6310301REP TRAF B TERM T1 SPEACH 91,407 $2,138.69$2,486.71— $1,690.57 – $2,850.00Sep 18, 2026
X6310310REP TB TERM T1 SP RLPEACH 9489 $111.32$134.40— $28.00 – $1,737.07Sep 18, 2026
X6380200REL MOD GLAR SCRN SYSFOOT 991,347 $3.58$4.06— $3.11 – $6.00Jan 16, 2026
X6440116REM HTC MED BAR TERMEACH 930 $2,645.12$2,288.14— $250.00 – $4,927.34Jun 12, 2026
X6440133REP POSTS (GIBRALTAR)EACH 97,775 $309.75$341.56— $123.16 – $403.26Sep 18, 2026
X6640312CH LK GATES REM & REEACH 924 $1,365.03$1,464.85— $300.00 – $2,750.00Apr 25, 2025
X6640550CH LK FENCE 4 SPLFOOT 94,142 $42.30$49.95— $15.60 – $65.81Sep 19, 2025
X6640618ORNAMENTAL FENCEFOOT 91,778 $131.78$157.51— $0.0100 – $391.69Jan 16, 2026
X7010814TRAF CONT-PROT TC14EACH 963 $472.19$608.35— $250.00 – $1,000.00Sep 18, 2026
X7035105TEMP EPOXY PVT MK L5FOOT 9135,245 $0.6735$0.7168— $0.6000 – $1.12Nov 17, 2023
X7035112TEMP EPOXY PVT MK L12FOOT 916,945 $2.42$2.55— $1.20 – $6.60Nov 17, 2023
X7200052RM STOR & RE-E SN PANSQ FT 91,602.4 $23.27$35.92— $18.00 – $250.00Jan 16, 2026
X7200065SIGN PANEL BACKPLATESQ FT 9724 $45.77$44.77— $31.00 – $50.00Jan 17, 2025
X7200080RE-ERECT SIGN PANELSQ FT 938,000 $8.99$8.26— $6.00 – $14.00Jan 17, 2025
X7200350INST SN PAN T3 - XWYSQ FT 94,952 $20.26$18.38— $15.00 – $40.00Nov 7, 2025
X7230203INSTALL SIGN PANEL T3SQ FT 92,074.5 $19.65$18.15— $13.00 – $30.00Nov 7, 2025
X7270020FUR HINGE PLATE SETEACH 9226 $160.84$146.47— $20.00 – $400.00Apr 25, 2025
X7301035SIGN POST S-218FOOT 9166 $78.31$82.24— $41.00 – $100.00Jan 17, 2025
X7330066REP HDRL LOC PIN CONEACH 9180 $217.06$214.23— $65.00 – $394.00Jan 16, 2026
X7330082MTNG BRCKT TY BEACH 972 $1,252.55$1,287.95— $600.00 – $2,500.00Jan 17, 2025
X7800956PREF PL PM TB I C LN 7FOOT 929,860 $4.91$5.85— $4.00 – $35.00Nov 5, 2021
X8030106LOC UNDERGR UTILITIESFOOT 94,780 $22.46$19.61— $0.0100 – $327.46Jul 31, 2026
X8050095SERV INSTALL SPLEACH 958 $3,012.40$2,719.90— $1,400.00 – $6,500.00Aug 2, 2024
X8050204REMOVE ELEC SERVICEEACH 965 $1,884.39$1,570.81— $924.00 – $4,800.00Jul 31, 2026
X8130130JUNCTION BOX ADJUSTEACH 942 $3,083.77$2,805.78— $351.76 – $7,654.73Jul 31, 2026
X8212032LUMINAIRE, TYPE B SPLEACH 9449 $4,508.07$2,885.18— $410.40 – $6,260.00Apr 24, 2026
X8510204PAINT NEW PED P-B PSTEACH 9112 $153.31$206.73— $36.00 – $400.00Sep 18, 2026
X8770139S C MAA&P 44 SPLEACH 918 $41,646.39$39,165.17— $22,172.00 – $64,372.00Jun 13, 2025
X8780200CONC FDN SUR CAB 334EACH 944 $9,633.34$9,520.47— $6,810.00 – $16,500.00Jun 12, 2026
X8820014TS BKPLT LVRD FPL SPLEACH 9426 $528.99$526.78— $340.48 – $755.70Sep 18, 2026
X8870510CONFIRMATION BEACONEACH 961 $571.33$753.00— $354.00 – $1,374.92Jan 16, 2026
X8891104REMOTE CONTR VIDEO SYSEACH 934 $7,381.37$10,035.97— $6,165.55 – $26,250.00Jul 31, 2026
X8891301VID & RAD HYB DET SYSEACH 932 $44,178.68$49,415.44— $29,700.00 – $66,486.00Jun 12, 2026
X8950077REM REL EXIST LT CONTEACH 911 $4,622.78$4,939.91— $450.00 – $18,225.00Jan 16, 2026
X8950100RELOC EX MASTER CONTREACH 911 $2,015.75$1,096.44— $264.69 – $7,000.00Apr 26, 2024
XP000014TRUCK CRANEHOUR 91,592 $2.95$2.94— $0.0100 – $165.00Jun 12, 2026
XP000204AL LP 45 COMP RWTA TBEACH 931 $2,287.52$2,916.91— $0.0100 – $8,775.00Jun 12, 2026
XX000300CONCRETE STEPSSQ FT 91,396 $86.23$127.10— $65.00 – $350.00Jun 12, 2026
XX005431LOC UNDERGR UTILITYEACH 9124 $677.93$603.66— $281.33 – $2,500.00Feb 27, 2026
XX006199STEEL BR RAIL SM SPLFOOT 92,576 $165.37$176.07— $140.00 – $206.80Sep 17, 2021
XX007324RECYCLING RECEPTACLEEACH 9101 $1,895.39$2,080.17— $1,256.72 – $3,100.00Jun 13, 2025
XX008839WATER MAIN ABANDONEDL SUM 99 $10,791.48$13,192.31— $0.0100 – $26,750.00Sep 19, 2025
XX009297LUM LED HM SPLEACH 9100 $799.00$774.64— $425.70 – $1,375.00Mar 8, 2024
Z0007120WELD WIRE FAB 6X6SQ YD 918,080 $8.96$10.51— $6.00 – $30.00Apr 24, 2026
Z0007400BR SIDEWLK REP (PD)SQ FT 91,345 $70.40$94.84— $48.00 – $275.00Jun 14, 2024
Z0007612BLDG REMOV NO 12L SUM 99 $23,622.77$26,421.33— $475.00 – $50,500.00Jun 12, 2026
Z0010512CLEAN & PT STL BR N12L SUM 99 $132,451.67$134,148.27— $19,500.00 – $235,500.00Apr 24, 2026
Z0012140BR DECK SCAR 2SQ YD 911,183.5 $54.40$69.26— $15.00 – $99.82Jun 13, 2025
Z0012148BR DECK SCAR 3SQ YD 932,400 $57.52$62.61— $45.00 – $150.00Mar 7, 2025
Z0018010DRAINAGE SCUPPR DS-33EACH 947 $2,955.47$2,845.95— $2,075.00 – $4,987.55Jun 14, 2024
Z0029662REPL HT CBL POST FDNEACH 94,425 $242.20$242.20— $125.00 – $550.00Jun 12, 2026
Z0030902TIGHTEN FUSE & BSE PLEACH 9435 $54.66$94.06— $18.14 – $363.00Apr 25, 2025
Z0032400JOINT REPAIREACH 9104 $640.83$924.35— $205.00 – $15,627.27Jun 12, 2026
Z0033200LINE POST T1EACH 94,894 $278.10$319.41— $191.88 – $344.45Feb 27, 2026
Z0034212MECH ST EARTH R WL SPSQ FT 985,724 $55.47$61.90— $28.00 – $112.00Apr 26, 2024
Z0034396MODULAR EXPAN JT 12FOOT 9798 $4,024.60$3,797.25— $2,040.00 – $6,500.00Feb 27, 2026
Z0038119PCC SUR REM 1 1/2SQ YD 95,179 $7.69$7.00— $2.27 – $41.87Jul 15, 2022
3,901–4,000 of 13,847‹ PrevNext ›

Averages are weighted by quantity. "Avg low bid" uses the apparent low bidder's unit prices; "Avg all bids" uses every bidder; "Avg estimate" is TxDOT's engineer's estimate. Built from TxDOT bid tabulations loaded into Bid Potato.