$2,955.47Avg low bid / EACH
$2,845.95Avg of all bids
—Avg engineer's estimate
9Jobs · 47 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2024 | 2 | 12 | $3,819.77 | $4,027.95 |
| 2023 | 1 | 2 | $2,700.00 | $2,666.67 |
| 2022 | 1 | 10 | $3,000.00 | $2,887.50 |
| 2021 | 2 | 14 | $2,491.08 | $2,448.65 |
| 2020 | 2 | 3 | $2,526.67 | $2,422.50 |
| 2019 | 1 | 6 | $2,535.80 | $2,261.12 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 14, 2024 | 62W48 | CookDistrict 1 | 4 EACH | $3,000.00 | ICC Group Inc. |
| Jun 14, 2024 | 72K98 | SangamonDistrict 6 | 8 EACH | $4,229.66 | Freesen, a div of UCM, Inc. |
| Jun 16, 2023 | 62G41 | KaneDistrict 1 | 2 EACH | $2,700.00 | Martam Construction Incorporated and Dunnet Bay Construction Company JV |
| Jun 17, 2022 | 60W35 | WillDistrict 1 | 10 EACH | $3,000.00 | D. Construction, Inc. and P. T. Ferro Construction Company JV |
| Nov 5, 2021 | 64H58 | Jo DaviessDistrict 2 | 2 EACH | $4,987.55 | Sjostrom & Sons, Inc. |
| Jul 30, 2021 | 99612 | GallatinDistrict 9 | 12 EACH | $2,075.00 | Samron Midwest Contracting, Inc. |
| Nov 6, 2020 | 60W34 | WillDistrict 1 | 2 EACH | $2,540.00 | D. Construction, Inc. and P. T. Ferro Construction Company JV |
| Jun 12, 2020 | 62K49 | CookDistrict 1 | 1 EACH | $2,500.00 | D. Construction, Inc. |
| Mar 8, 2019 | 62C14 | KaneDistrict 1 | 6 EACH | $2,535.80 | Herlihy Mid-Continent Company |