IDOT Bid Averages

13,847 bid codes Sign up free

Average unit prices · Statewide

ExcelCSV
Bid codeDescriptionUnitJobs ▼QuantityAvg low bidAvg all bidsAvg estimateLow rangeLast let
60100070SHOULDER REM & REPLFOOT 502,487,087 $8.24$7.99— $0.0100 – $425.00Sep 18, 2026
60201110CB TA 4 DIA T11V F&GEACH 50477 $3,644.85$3,972.62— $1,585.00 – $8,300.00Jul 31, 2026
60219300MAN TA 4 DIA T11F&GEACH 50204 $3,697.69$3,690.32— $1,450.00 – $7,500.00Jun 12, 2026
60237460INLETS TA T23F&GEACH 50268 $1,972.01$1,917.98— $961.00 – $6,600.00Jun 12, 2026
60920024PIPE CULV CLEANED 24FOOT 5013,729 $40.67$43.23— $5.15 – $171.00Sep 18, 2026
61133200FLD TILE JUN VAULT 3DEACH 50170 $2,508.47$2,380.39— $0.0100 – $5,262.55Jul 31, 2026
66901005ENGINEERED BARRIERSQ YD 5087,756 $14.12$15.23— $0.0100 – $309.83Jun 12, 2026
70101830TRAF CONT-PROT BLR 21L SUM 5050 $3,871.43$4,633.02— $0.0100 – $21,069.96Apr 26, 2019
78003130PREF PL PM TB LINE 6FOOT 50622,603 $3.68$4.02— $3.00 – $26.00Nov 5, 2021
83600365LP F M 15BC 10" X 8'EACH 502,238 $1,969.16$1,886.65— $600.00 – $8,800.00Jul 31, 2026
87702900STL COMB MAA&P 34EACH 5072 $21,282.10$20,554.92— $10,626.84 – $37,500.00Sep 18, 2026
89500120REM EX SERV INSTALLEACH 50117 $1,203.54$1,078.03— $150.00 – $3,000.00Jun 12, 2026
89502400REM EX FB INSTAL COMPEACH 50107 $1,880.15$1,524.87— $137.50 – $11,000.00Jun 12, 2026
AR150530TRAFFIC MAINTENANCEL.S. 5050 $22,287.67$23,763.78— $1,500.00 – $85,000.00Aug 5, 2022
X2080250TRENCH BACKFILL SPLCU YD 5080,795.8 $24.49$40.12— $0.0100 – $500.00Jan 16, 2026
X4060107BIT MATLS FSPOUND 501,783,421 $1.52$1.26— $0.6000 – $11.30Sep 18, 2026
X6020096MH TA 6D W/2 T1FCL RPEACH 5095 $12,803.37$14,003.00— $770.27 – $27,000.00Jul 31, 2026
X7011834TC-PROT CALL OUT WORKEACH 504,782 $1,009.91$1,314.97— $0.0100 – $3,818.06Jul 31, 2026
Z0054500ROCK FILLTON 50102,793 $36.02$38.39— $14.35 – $132.68Jun 12, 2026
30300011AGG SUBGRADE IMPROVETON 49249,472 $23.60$22.63— $14.88 – $122.25Jul 31, 2026
40200900AGG SURF CSE BCU YD 495,446.2 $52.53$55.61— $20.00 – $457.29Jul 31, 2026
51203610TEST PILE ST HP12X63EACH 4996 $11,162.25$10,640.82— $3,100.00 – $48,850.00Jun 12, 2026
542A1081P CUL CL A 2 36FOOT 495,968 $167.78$165.62— $94.00 – $460.87Jul 31, 2026
60240310INLETS TB T11F&GEACH 49474 $2,100.71$2,350.75— $1,436.30 – $5,191.72Jan 16, 2026
61000115TY E INLET BOX 610001EACH 49238 $5,592.87$5,872.54— $2,350.00 – $20,500.00Sep 18, 2026
73300100OVHD SIN STR-SPAN T1AFOOT 498,957.4 $1,078.33$1,083.17— $620.00 – $3,714.00Jan 16, 2026
87501200TS POST 16EACH 49284 $2,742.50$2,660.97— $975.00 – $5,648.20Sep 18, 2026
87702930STL COMB MAA&P 40EACH 4979 $23,218.05$21,031.28— $11,842.09 – $74,681.10Sep 18, 2026
X1400424ECC SNM SN 14 3C SOOWFOOT 4976,591.5 $2.81$3.00— $1.20 – $11.10Jul 31, 2026
X4240440PC CONC SIDEWALK 6 SPSQ FT 49231,822 $10.39$11.55— $6.00 – $69.64Apr 24, 2026
X4403300CONC MEDIAN REMOVSQ FT 49133,376.7 $5.36$6.27— $0.0100 – $116.50Apr 24, 2026
X5040100PREC BRIDGE APP SLABSQ FT 49183,401 $56.02$56.07— $28.00 – $125.00Jun 12, 2026
X5510100STORM SEWER REMOVALFOOT 4934,098 $39.78$32.18— $1.00 – $107.00Sep 18, 2026
Z0012455CONC STEP REMOVEACH 49288 $566.05$523.34— $56.12 – $8,204.85Sep 18, 2026
31102100SUB GRAN MAT C 4SQ YD 48533,594 $6.83$8.33— $4.02 – $86.74Jun 12, 2026
35600708HMA BC WID 8SQ YD 4889,411.8 $46.46$51.49— $7.85 – $289.50Jun 12, 2026
44201025CL B PATCH T4 14SQ YD 4819,816.3 $241.60$245.86— $120.00 – $500.00Jun 12, 2026
50900805PEDESTRIAN RAILFOOT 4811,513 $274.41$291.10— $104.20 – $924.00Feb 27, 2026
52200500MECH ST EARTH RET WLSQ FT 48487,292 $103.56$112.37— $0.0100 – $200.00Jul 31, 2026
55101100STORM SEWER REM 21FOOT 487,340 $27.62$26.16— $1.00 – $192.00Jun 12, 2026
59200108BRIDGE WASHING N8EACH 4848 $14,891.70$14,380.40— $3,987.00 – $94,000.00Feb 27, 2026
60236825INLETS TA T11V F&GEACH 48401 $1,938.27$1,931.48— $990.00 – $4,125.00Jul 31, 2026
60240210INLETS TB T1F OLEACH 48179 $2,658.45$2,849.72— $1,100.00 – $7,632.20Jun 12, 2026
63300575R&R RAIL ELEM EX GDRLFOOT 4842,084 $20.01$21.90— $0.0100 – $177.98Jul 31, 2026
66201120CONC SHLD CURBFOOT 4811,454 $39.16$36.21— $1.50 – $122.58Sep 18, 2026
83050810LT P A 47.5MH 15MAEACH 482,028 $4,869.18$4,944.45— $2,675.00 – $14,972.32Jun 12, 2026
87700300S MAA & P 52EACH 4865 $18,907.23$17,886.40— $10,451.20 – $37,926.90Sep 18, 2026
AR201661CLEAN & SEAL BITUMINOUS CRACKSL.F. 48347,990 $2.77$2.77— $1.10 – $24.80Aug 5, 2022
AR401613BIT. SURF. CSE.-METHOD I, SUPERPAVETON 4846,403 $119.63$119.44— $73.00 – $295.00Mar 11, 2022
X7830072GRV RCSD PVT MRKG 6FOOT 481,428,906 $0.5090$0.6837— $0.2900 – $2.81Nov 5, 2021
XP000003JOURNEY ELECT W OTHOUR 482,840 $159.25$156.72— $76.00 – $283.71Sep 18, 2026
XP000005JOURNEY ELECT SU/H OTHOUR 481,787 $193.78$197.81— $76.00 – $378.21Sep 18, 2026
Z0004538HMA DRIVEWAY PAVT 10SQ YD 4824,755.78 $75.20$81.17— $45.00 – $793.40Nov 8, 2024
40600627LB MM IL-9.5FG N50TON 47135,281.5 $83.92$85.68— $49.00 – $223.00Nov 8, 2019
44201396CL C PATCH T4 13SQ YD 4717,988.7 $198.57$206.84— $99.00 – $526.54Jun 12, 2026
44201773CL D PATCH T1 11SQ YD 475,722 $115.24$97.56— $24.00 – $421.00Sep 18, 2026
54214509PRC FL END S EQ RS 24EACH 47132 $1,792.13$1,977.39— $0.0100 – $3,714.02Jul 31, 2026
542A5473P CUL CL A 1 EQRS 18FOOT 474,123.5 $140.45$138.87— $68.73 – $345.00Jul 31, 2026
55101900STORM SEWER REM 48FOOT 4710,644 $46.67$49.48— $10.00 – $185.00Jan 16, 2026
60248700VV TA 4 DIA T1F CLEACH 47288 $3,463.77$3,601.38— $1,850.00 – $10,000.00Feb 27, 2026
60266100VV RECONSTEACH 47117 $2,062.78$1,680.47— $750.00 – $53,500.00Jan 16, 2026
60920012PIPE CULV CLEANED 12FOOT 4713,596 $11.50$8.51— $2.00 – $165.00Sep 18, 2026
61140000STORM SEWER SPEC 8FOOT 479,883 $43.24$52.09— $0.0100 – $292.00Jul 31, 2026
78003100PREF PL PM TB LTR-SYMSQ FT 4726,767.5 $33.47$36.65— $10.00 – $105.98Nov 5, 2021
81028740UNDRGRD C CNC 1 1/2FOOT 47298,614.8 $10.88$11.79— $4.21 – $50.50Apr 24, 2026
K0026700TREE CAREEACH 476,375 $113.07$142.81— $16.00 – $6,000.00Sep 18, 2026
X0322916PRO SS CONN TO EX SSEACH 47151 $1,855.93$1,682.80— $195.00 – $8,060.00Nov 7, 2025
X0327500ARROWBOARD TRAILR MNTHOUR 4712,268 $2.12$4.70— $0.0100 – $50.00Jun 12, 2026
X1400388VID VEH DET SYS SN APEACH 47160 $10,405.53$10,473.55— $4,618.40 – $18,411.18Apr 26, 2024
X2502024SEEDING CL 4B MODACRE 4752.931 $3,331.56$3,288.61— $1,386.00 – $30,000.00Jun 12, 2026
X4810200AGGREGATE SHLD REMOVLCU YD 4711,781 $40.27$39.62— $10.00 – $824.44Jul 31, 2026
X5630708CONN TO EX W MAIN 8EACH 47167 $4,118.91$4,995.26— $618.40 – $12,840.00Apr 24, 2026
X8950114MOD EX CONTR & CABEACH 47119 $4,487.68$4,580.47— $243.12 – $16,656.30Jul 31, 2026
XX003668PRECONSTRUCT VID TAPL SUM 4747 $2,306.98$2,646.84— $0.0100 – $5,875.00Apr 24, 2026
Z0001110GAS VALVE ADJUSTEDEACH 47176 $892.35$795.36— $36.49 – $3,864.82Sep 18, 2026
Z0012193BR DK TH POLY OVL 3/8SQ YD 47113,596 $62.33$66.17— $23.75 – $1,028.50Jul 31, 2026
Z0052415REPAIR TRBT T1 SP FLREACH 47313 $1,764.32$1,826.73— $554.54 – $5,389.55Jun 14, 2024
Z0055300RUMBLE STRIPEACH 47254 $1,404.92$1,415.64— $0.0100 – $8,550.00Jul 31, 2026
Z0065700SLOPE WALL REPAIRSQ YD 475,655.7 $249.45$278.57— $90.00 – $2,500.00Apr 25, 2025
42101300PROTECTIVE COATSQ YD 46963,171 $0.3563$0.6503— $0.0100 – $79.34Sep 18, 2026
44000162HMA SURF REM 3 1/4SQ YD 461,567,857 $4.65$3.90— $2.22 – $182.33Jun 12, 2026
44200144PAVT PATCH T2 12SQ YD 469,313.7 $197.29$196.25— $80.00 – $668.94Jul 31, 2026
44200559CL A PATCH T4 10SQ YD 4651,780.2 $206.75$213.68— $127.00 – $493.70Jun 12, 2026
44201394CL C PATCH T3 13SQ YD 465,710.6 $209.69$228.24— $137.00 – $526.54Jun 12, 2026
48101498AGGREGATE SHLDS B 4SQ YD 4694,771.9 $10.85$10.68— $2.00 – $60.00Jul 31, 2026
70100325TRAF CONT-PROT 701423EACH 4678 $13,541.55$12,284.36— $0.0100 – $64,000.00Jun 12, 2026
70100430TRAF CONT-PROT 701446EACH 46798 $4,583.80$4,342.48— $0.00 – $99,819.99Sep 18, 2026
73304000OVHD SIN STR BR MTFOOT 461,905.33 $1,183.27$1,091.65— $550.00 – $3,404.95Jun 12, 2026
78004280PREF PL PM TB INL L24FOOT 466,224 $38.98$39.11— $12.88 – $180.00Mar 7, 2025
87702920STL COMB MAA&P 38EACH 4674 $20,268.51$19,778.93— $11,565.00 – $38,500.00Apr 24, 2026
X2503000MAINTENANCE MOWINGACRE 464,893.1 $134.47$155.10— $75.00 – $1,000.00Sep 18, 2026
X2503100MOWINGUNIT 4630,914.3 $28.87$36.43— $0.0100 – $400.00Jul 31, 2026
X5610712WATER MAIN REMOV 12FOOT 4616,798 $23.83$27.79— $1.00 – $189.36Jun 12, 2026
X7800200PAINT PVT MARK CURBFOOT 4635,814 $3.28$3.51— $0.0100 – $29.00Jul 31, 2026
Z0004514HMA DRIVEWAY PAVT 4SQ YD 4612,342 $43.92$47.82— $21.00 – $320.00Mar 7, 2025
Z0065730SLOPEWALL SLUR PUMPNGCU YD 462,136.6 $346.22$357.24— $200.00 – $2,000.00Apr 25, 2025
21101685TOPSOIL F & P 24SQ YD 4599,330.7 $22.79$24.41— $0.0100 – $97.55Jul 31, 2026
31102000SUB GRAN MAT CCU YD 4521,547.8 $68.83$62.70— $25.00 – $1,350.00Apr 24, 2026
35400300PCC BASE CSE W 8SQ YD 4519,902.3 $69.80$79.30— $35.95 – $250.00Jun 12, 2026
40300200BIT MATLS PR CTTON 451,115.81 $552.94$655.21— $0.00 – $3,000.00Jul 30, 2021
1,201–1,300 of 13,847‹ PrevNext ›

Averages are weighted by quantity. "Avg low bid" uses the apparent low bidder's unit prices; "Avg all bids" uses every bidder; "Avg estimate" is TxDOT's engineer's estimate. Built from TxDOT bid tabulations loaded into Bid Potato.