$5,563.80Avg low bid / EACH
$10,879.85Avg of all bids
—Avg engineer's estimate
4Jobs · 10 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2025 | 3 | 7 | $3,928.28 | $10,655.76 |
| 2024 | 1 | 3 | $9,380.00 | $11,253.33 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Sep 19, 2025 | 74597 | CumberlandDistrict 7 | 2 EACH | $56.98 | William Charles Construction Company, LLC |
| Jun 13, 2025 | 64R16 | Rock IslandDistrict 2 | 1 EACH | $9,384.00 | Advanced Asphalt Company |
| Mar 7, 2025 | 64N01 | WhitesideDistrict 2 | 4 EACH | $4,500.00 | Civil Constructors, Inc. d/b/a/ Helm Civil |
| Dec 13, 2024 | 64N05 | HenryDistrict 2 | 3 EACH | $9,380.00 | Civil Constructors d/b/a Helm Civil and Phoenix Corporation of the Quad Cities |