$25,978.21Avg low bid / EACH
$25,541.63Avg of all bids
—Avg engineer's estimate
22Jobs · 30 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 13 | 18 | $25,724.43 | $25,335.21 |
| 2025 | 9 | 12 | $26,358.89 | $26,006.07 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jul 31, 2026 | 61M40 | DupageDistrict 1 | 1 EACH | $21,354.00 | Home Towne Electric, Inc. |
| Jul 31, 2026 | 61K19 | CookDistrict 1 | 2 EACH | $27,559.00 | R. W. Dunteman Company |
| Jun 12, 2026 | 80C89 | Cook, LakeDistrict 1 | 1 EACH | $22,086.13 | H & H Electric Co. |
| Jun 12, 2026 | 62M71 | Kane, KendallDistrict 1 | 1 EACH | $24,611.72 | D. Construction, Inc. |
| Jun 12, 2026 | 62U72 | MchenryDistrict 1 | 1 EACH | $24,863.47 | Martam Construction Incorporated |
| Jun 12, 2026 | 76U38 | Madison, St.clairDistrict 8 | 2 EACH | $16,000.00 | Gerstner Electric, Inc. |
| Jun 12, 2026 | 78B94 | SalineDistrict 9 | 1 EACH | $37,167.00 | Brown Electric, Inc. |
| Apr 24, 2026 | 62K33 | CookDistrict 1 | 3 EACH | $21,724.14 | Plote Construction, Inc. |
| Apr 24, 2026 | 80C85 | MchenryDistrict 1 | 1 EACH | $22,166.23 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. |
| Apr 24, 2026 | 70F20 | McleanDistrict 5 | 1 EACH | $31,000.00 | Stark Excavating, Inc. |
| Feb 27, 2026 | 72295 | AdamsDistrict 6 | 2 EACH | $30,000.00 | Diamond Construction Company |
| Jan 16, 2026 | 68F92 | TazewellDistrict 4 | 1 EACH | $37,500.68 | R. A. Cullinan and Son, a div of UCM, Inc. |
| Jan 16, 2026 | 66R42 | KankakeeDistrict 3 | 1 EACH | $30,000.00 | Van-Mack Electric Co. |
| Nov 7, 2025 | 61L21 | CookDistrict 1 | 1 EACH | $23,257.51 | H & H Electric Co. |
| Sep 19, 2025 | 70F21 | McleanDistrict 5 | 1 EACH | $32,155.20 | Rowe Construction, a div of UCM, Inc. |
| Aug 1, 2025 | 62N97 | CookDistrict 1 | 2 EACH | $28,000.00 | Everlast Blacktop Inc. |
| Aug 1, 2025 | 62W57 | CookDistrict 1 | 2 EACH | $25,800.00 | Hecker and Company, Inc. |
| Aug 1, 2025 | 91653 | McleanDistrict 5 | 1 EACH | $31,890.77 | Rowe Construction, a div of UCM, Inc. |
| Jun 13, 2025 | 62X42 | CookDistrict 1 | 2 EACH | $24,400.00 | Hecker and Company, Inc. |
| Jun 13, 2025 | 76K74 | St.clairDistrict 8 | 1 EACH | $33,596.76 | Keeley & Sons, Inc. Keller Construction Inc. |
| Mar 7, 2025 | 62W61 | VariousDistrict 1 | 1 EACH | $17,256.49 | H & H Electric Co. |
| Jan 17, 2025 | 76T49 | MadisonDistrict 8 | 1 EACH | $21,750.00 | Electrico, Inc. |