$16,458.60Avg low bid / EACH
$16,901.35Avg of all bids
—Avg engineer's estimate
16Jobs · 29 EACH
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 5 | 9 | $15,402.97 | $15,717.73 |
| 2025 | 11 | 20 | $16,933.64 | $17,477.98 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Jun 12, 2026 | 76U38 | Madison, St.clairDistrict 8 | 2 EACH | $12,500.00 | Gerstner Electric, Inc. |
| Jun 12, 2026 | 80C89 | Cook, LakeDistrict 1 | 3 EACH | $13,986.69 | H & H Electric Co. |
| Apr 24, 2026 | 61L54 | CookDistrict 1 | 1 EACH | $21,166.63 | Martam Construction Incorporated |
| Jan 16, 2026 | 85780 | Rock IslandDistrict 2 | 1 EACH | $15,300.00 | McCarthy Improvement Company |
| Jan 16, 2026 | 62F94 | WillDistrict 1 | 2 EACH | $17,600.00 | D. Construction, Inc. |
| Sep 19, 2025 | 62R22 | WillDistrict 1 | 2 EACH | $16,940.00 | D. Construction, Inc. |
| Sep 19, 2025 | 70F21 | McleanDistrict 5 | 4 EACH | $18,703.61 | Rowe Construction, a div of UCM, Inc. |
| Aug 1, 2025 | 62W57 | CookDistrict 1 | 2 EACH | $17,200.00 | Hecker and Company, Inc. |
| Jun 13, 2025 | 61L34 | CookDistrict 1 | 1 EACH | $17,333.00 | Alliance Contractors, Inc. |
| Jun 13, 2025 | 62N39 | Dupage, CookDistrict 1 | 2 EACH | $19,139.43 | Meade Inc. |
| Apr 25, 2025 | 62N33 | DupageDistrict 1 | 2 EACH | $15,800.00 | John Burns Construction Company |
| Apr 25, 2025 | 70991 | ChampaignDistrict 5 | 1 EACH | $22,000.00 | Cross Construction, Inc. |
| Mar 7, 2025 | 62W61 | VariousDistrict 1 | 2 EACH | $13,203.76 | H & H Electric Co. |
| Mar 7, 2025 | 62N91 | CookDistrict 1 | 2 EACH | $16,600.00 | Dunnet Bay Construction Company & K-Five Construction Corporation |
| Mar 7, 2025 | 62W60 | Cook, DupageDistrict 1 | 1 EACH | $13,758.93 | H & H Electric Co. |
| Jan 17, 2025 | 76T49 | MadisonDistrict 8 | 1 EACH | $13,000.00 | Electrico, Inc. |