$1,815.12Avg low bid / FOOT
$2,327.48Avg of all bids
—Avg engineer's estimate
3Jobs · 86.5 FOOT
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 1 | 30 | $294.00 | $1,698.00 |
| 2025 | 2 | 56.5 | $2,622.79 | $2,658.78 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Feb 27, 2026 | 62R23 | WillDistrict 1 | 30 FOOT | $294.00 | D. Construction, Inc. & Kraemer North America, LLC JV |
| Jun 13, 2025 | 68E44 | Peoria, TazewellDistrict 4 | 27.5 FOOT | $2,225.00 | William Charles Construction Company, LLC |
| Apr 25, 2025 | 62X94 | MchenryDistrict 1 | 29 FOOT | $3,000.00 | Berger Excavating Contractors, Inc. d/b/a Berger Contractors, Inc. |