$5,727,572.12Avg low bid / L SUM
$10,415,281.76Avg of all bids
—Avg engineer's estimate
4Jobs · 4 L SUM
Average low bid by year
| Year | Jobs | Quantity | Avg low | Avg all |
|---|---|---|---|---|
| 2026 | 3 | 3 | $6,291,608.33 | $14,062,075.17 |
| 2025 | 1 | 1 | $4,035,463.47 | $4,580,412.29 |
| Let date | Contract | County / District | Quantity | Unit price | Low bidder |
|---|---|---|---|---|---|
| Feb 27, 2026 | 62R23 | WillDistrict 1 | 1 L SUM | $17,624,825.00 | D. Construction, Inc. & Kraemer North America, LLC JV |
| Feb 27, 2026 | 64R72 | WinnebagoDistrict 2 | 1 L SUM | $350,000.00 | Civil Constructors, Inc. d/b/a/ Helm Civil |
| Jan 16, 2026 | 62F94 | WillDistrict 1 | 1 L SUM | $900,000.00 | D. Construction, Inc. |
| Aug 1, 2025 | 64C24 | WinnebagoDistrict 2 | 1 L SUM | $4,035,463.47 | OHLA Central, Inc. |