Asphalts/Oils/Emul-YAO (Materials Only)
- Let date
- Tuesday, March 24, 2026
- CCSJ
- 6494-54-001
- District
- Yoakum
- County
- Fayette
- Highway
- US0077
- Limits
- Fayette, Lavaca, DeWitt, and Gonzales to Counties.
- Classification
- Material Maintenance Project · Maintenance
- Project number
- MMC - A00218616
- Working days
- 365
- DBE goal
- 0%
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $435,000 | ||
| 1 | MARTIN RESOURCE MANAGEMENT CORPORATION Low bidder | $498,447 | +14.6% | |
| 2 | WRIGHT ASPHALT PRODUCTS COMPANY LLC | $527,985 | +21.4% | +5.9% |
| 3 | ERGON ASPHALT & EMULSIONS, INC. | $583,950 | +34.2% | +17.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 MARTIN RESOURCE… | #2 WRIGHT ASPHALT … | #3 ERGON ASPHALT &… |
|---|---|---|---|---|---|---|---|---|
| 1 | 8003-7077 | CRS-2 (DEL)(SITE 1) | 100 | TON | $525.00 | $588.43 | $629.80 | $755.00 |
| 2 | 8003-7078 | CRS-2 (DEL)(SITE 2) | 100 | TON | $525.00 | $595.18 | $629.80 | $755.00 |
| 3 | 8003-7079 | CRS-2 (DEL)(SITE 3) | 100 | TON | $525.00 | $607.79 | $629.80 | $755.00 |
| 4 | 8003-7080 | CRS-2 (DEL)(SITE 4) | 100 | TON | $525.00 | $604.19 | $629.80 | $755.00 |
| 5 | 8003-7133 | CRS-2P (DEL)(SITE 1) | 25 | TON | $600.00 | $646.74 | $688.55 | $825.50 |
| 6 | 8003-7134 | CRS-2P (DEL)(SITE 2) | 25 | TON | $600.00 | $653.49 | $688.55 | $825.50 |
| 7 | 8003-7135 | CRS-2P (DEL)(SITE 3) | 25 | TON | $600.00 | $666.10 | $688.55 | $825.50 |
| 8 | 8003-7136 | CRS-2P (DEL)(SITE 4) | 25 | TON | $600.00 | $662.50 | $688.55 | $825.50 |
| 9 | 8003-7246 | RC-250 (DEL) (SITE 1) | 50 | TON | $825.00 | $955.37 | $1,036.05 | $997.00 |
| 10 | 8003-7247 | RC-250 (DEL) (SITE 2) | 50 | TON | $825.00 | $962.12 | $1,036.05 | $997.00 |
| 11 | 8003-7248 | RC-250 (DEL) (SITE 3) | 50 | TON | $825.00 | $974.73 | $1,036.05 | $997.00 |
| 12 | 8003-7249 | RC-250 (DEL) (SITE 4) | 50 | TON | $825.00 | $971.13 | $1,036.05 | $997.00 |