6489-48-001 Tree Trim. Brush Removal
- Let date
- Tuesday, October 21, 2025
- CCSJ
- 6489-48-001
- District
- Corpus Christi
- County
- Karnes
- Highway
- US0181
- Limits
- VARIOUS to .
- Classification
- Routine Maintenance Project - Sealed · Maintenance
- Project number
- RMC - A00217441
- Working days
- 365
- DBE goal
- 0%
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $639,100 | ||
| 1 | ALLIES LAND CLEARING Low bidder | $348,000 | -45.5% | |
| 2 | AUSTIN BARRICADE COMPANY, L.L.C. | $421,962 | -34.0% | +21.3% |
| 3 | CROSS PLUS CONSTRUCTION, LLC | $552,333 | -13.6% | +58.7% |
| 4 | PREMIER CONTRACTORS LLC | $573,602 | -10.2% | +64.8% |
| 5 | JCW CONSTRUCTION, LLC | $586,014 | -8.3% | +68.4% |
| 6 | S FOWLER SERVICES LLC | $700,500 | +9.6% | +101.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 ALLIES LAND CLE… | #2 AUSTIN BARRICAD… | #3 CROSS PLUS CONS… | #4 PREMIER CONTRAC… | #5 JCW CONSTRUCTIO… | #6 S FOWLER SERVIC… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 100-7008 | PREP ROW (TREE REMOVE) (>61" DIA) | 85 | EA | $2,000.00 | $500.00 | $748.00 | $1,298.00 | $1.00 | $1,000.00 | $2,800.00 |
| 2 | 500-7003 | MOBILIZATION (CALLOUT 1) | 1 | EA | $1,500.00 | $0.0010 | $150.00 | $1.00 | $1.00 | $500.00 | $0.0100 |
| 3 | 500-7004 | MOBILIZATION (CALLOUT 2) | 1 | EA | $1,500.00 | $0.0010 | $150.00 | $1.00 | $1.00 | $500.00 | $0.0100 |
| 4 | 500-7005 | MOBILIZATION (CALLOUT 3) | 1 | EA | $1,500.00 | $0.0010 | $150.00 | $1.00 | $1.00 | $500.00 | $0.0100 |
| 5 | 505-7001 | TMA (STATIONARY) | 14 | DAY | $150.00 | $2,000.00 | $2,468.00 | $2,500.00 | $1.00 | $1.00 | $0.0100 |
| 6 | 752-7001 | TREE TRIMMING / BRUSH REMOVAL | 185 | MI | $2,500.00 | $1,500.00 | $1,748.00 | $2,200.00 | $3,100.00 | $2,700.00 | $2,500.00 |