Opaque Sealer Finish 771 0825
- Let date
- Wednesday, August 13, 2025
- CCSJ
- 6488-98-001
- District
- Dallas
- County
- Dallas
- Highway
- SH0114
- Limits
- VARIOUS ROADWAYS IN to DALLAS COUNTY
- Classification
- Routine Maintenance Project - Sealed · Maintenance
- Project number
- RMC - A00217254
- Working days
- 68
- DBE goal
- 0%
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $954,872 | ||
| 1 | GIBSON & ASSOCIATES, INC. Low bidder | $1,119,711 | +17.3% | |
| 2 | ICOS MANAGEMENT, LLC | $1,186,540 | +24.3% | +6.0% |
| 3 | FIREMAN EXCAVATING, INC. | $1,614,838 | +69.1% | +44.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 GIBSON & ASSOCI… | #2 ICOS MANAGEMENT… | #3 FIREMAN EXCAVAT… |
|---|---|---|---|---|---|---|---|---|
| 1 | 427-7003 | OPAQUE SEALER FINISH | 626,484 | SF | $1.25 | $0.8500 | $1.67 | $2.21 |
| 2 | 500-7001 | MOBILIZATION | 1 | LS | $86,806.50 | $201,000.00 | $140,000.00 | $150,000.00 |
| 3 | 502-7001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 4 | MO | $6,000.00 | $85,000.00 | $1.00 | $20,000.00 |
| 4 | 503-7001 | PORTABLE CHANGEABLE MESSAGE SIGN | 68 | DAY | $120.00 | $150.00 | $1.00 | $1.00 |
| 5 | 505-7001 | TMA (STATIONARY) | 240 | DAY | $220.00 | $150.00 | $1.00 | $1.00 |