Pothole Repair 06 0825
- Let date
- Wednesday, August 13, 2025
- CCSJ
- 6482-40-001
- District
- Dallas
- County
- Kaufman
- Highway
- IH0020
- Limits
- Various Roadways in the Kaufman - to Rockwall Maintenance Section
- Classification
- Routine Maintenance Project - Sealed · Maintenance
- Project number
- RMC - A00214740
- Working days
- 365
- DBE goal
- 0%
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $400,500 | ||
| 1 | AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC Low bidder | $430,875 | +7.6% | |
| 2 | FOUTSCO PAVING COMPANY, LLC | $1,079,500 | +169.5% | +150.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 AMERICAN INFRAS… | #2 FOUTSCO PAVING … |
|---|---|---|---|---|---|---|---|
| 1 | 500-7002 | MOBILIZATION (CALLOUT) | 15 | EA | $2,000.00 | $3,000.00 | $5,000.00 |
| 2 | 500-7033 | MOBILIZATION (EMERGENCY) | 5 | EA | $2,000.00 | $4,000.00 | $5,000.00 |
| 3 | 505-7001 | TMA (STATIONARY) | 15 | DAY | $200.00 | $300.00 | $300.00 |
| 4 | 505-7003 | TMA (MOBILE OPERATION) | 50 | DAY | $300.00 | $300.00 | $300.00 |
| 5 | 700-7005 | POTHOLE REPAIR (STANDARD) | 325 | TON | $325.00 | $380.00 | $1,300.00 |
| 6 | 700-7010 | POTHOLE REPAIR (SAW - CUT) | 500 | TON | $455.00 | $420.00 | $1,050.00 |
| 7 | 700-7012 | EDGE REPAIR | 25 | TON | $375.00 | $515.00 | $500.00 |