RPM (Longline US75) 07 0725
- Let date
- Wednesday, August 13, 2025
- CCSJ
- 6482-07-001
- District
- Dallas
- County
- Collin
- Highway
- US0075
- Limits
- SAM RAYBURN TOLLWAY (SRT) to ROSAMOND PARKWAY
- Classification
- Routine Maintenance Project - Sealed · Maintenance
- Project number
- RMC - A00214638
- Working days
- 12
- DBE goal
- 0%
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $379,640 | ||
| 1 | STRIPE LINES, INC. Low bidder | $166,612 | -56.1% | |
| 2 | TRAFFIC HIGHWAY MAINTENANCE, LLC | $183,631 | -51.6% | +10.2% |
| 3 | TRP INFRASTRUCTURE SERVICES, LLC | $271,896 | -28.4% | +63.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 STRIPE LINES, I… | #2 TRAFFIC HIGHWAY… | #3 TRP INFRASTRUCT… |
|---|---|---|---|---|---|---|---|---|
| 1 | 500-7001 | MOBILIZATION | 1 | LS | $34,780.00 | $10,500.00 | $6,500.00 | $10,000.00 |
| 2 | 502-7001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 | MO | $2,500.00 | $2,500.00 | $0.0100 | $500.00 |
| 3 | 505-7003 | TMA (MOBILE OPERATION) | 36 | DAY | $600.00 | $10.00 | $0.0100 | $1.00 |
| 4 | 666-7237 | RE PM TY III (W)(6")(BRK) | 118,800 | LF | $0.6500 | $0.7800 | $0.7900 | $1.20 |
| 5 | 666-7347 | PAVEMENT SLER 6" | 118,800 | LF | $0.6500 | $0.0100 | $0.0010 | $0.2500 |
| 6 | 677-7002 | ELIM EXT PM & MRKS (6") | 118,800 | LF | $1.40 | $0.5000 | $0.7000 | $0.7500 |