Bid tab 6482-00-001

Let Apr 23, 2025 · Amarillo · Potter Sign up free

‹ Apr 2025 results

RPM FY 2025

Let date
Wednesday, April 23, 2025
CCSJ
6482-00-001
District
Amarillo
County
Potter
Highway
IH0040
Limits
see plan sheets to see plan sheets
Classification
Routine Maintenance Project - Sealed · Maintenance
Project number
RMC - A00214631
Working days
45
DBE goal
0%

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$506,948
1 TRP INFRASTRUCTURE SERVICES, LLC Low bidder $329,294 -35.0%
2 CENTERLINE TECHNOLOGIES, LLC $374,411 -26.1% +13.7%
3 TRAFFIC HIGHWAY MAINTENANCE, LLC $470,118 -7.3% +42.8%
4 THE CONFIDENCE GROUP, INC $613,606 +21.0% +86.3%

Bid tab: unit prices 6 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 TRP INFRASTRUCT…#2 CENTERLINE TECH…#3 TRAFFIC HIGHWAY…#4 THE CONFIDENCE …
1500-7001 MOBILIZATION1LS $35,000.00 $1.00 $20,000.00 $20,000.00 $70,000.00
2502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING2MO $5,000.00 $1.00 $1.00 $2,000.00 $2,000.00
3505-7003 TMA (MOBILE OPERATION)80DAY $250.00 $0.5000 $500.00 $250.00 $300.00
4672-7002 REFL PAV MRKR TY I-C10,338EA $6.00 $4.47 $4.15 $6.00 $7.00
5672-7004 REFL PAV MRKR TY II-A-A38,383EA $6.00 $4.47 $4.15 $5.75 $7.00
6672-7006 REFL PAV MRKR TY II-C-R24,937EA $6.00 $4.47 $4.50 $5.75 $7.00