US 70 Bridge Repair
- Let date
- Thursday, March 13, 2025
- CCSJ
- 6480-21-001
- District
- Wichita Falls
- County
- Wilbarger
- Highway
- US0287
- Limits
- Bridge at US 70 & US 287 to in Wilbarger County
- Classification
- Bridge Preventative Maintenance - Sealed · Maintenance
- Project number
- BPM - A00214075
- Working days
- 14
- DBE goal
- 0%
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $144,840 | ||
| 1 | TAYLOR CONTRACTING LLC Low bidder | $112,028 | -22.7% | |
| 2 | BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC | $132,650 | -8.4% | +18.4% |
| 3 | GIBSON & ASSOCIATES, INC. | $157,890 | +9.0% | +40.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 TAYLOR CONTRACT… | #2 BUILT RIGHT CON… | #3 GIBSON & ASSOCI… |
|---|---|---|---|---|---|---|---|---|
| 1 | 429-7006 | CONC STR REPR(RAPID DECK REP(FULL DPT)) | 90 | SF | $250.00 | $300.00 | $325.00 | $270.00 |
| 2 | 446-7019 | SPOT CLEAN & PNT EXT STR(SPL PROT SYS) | 1 | LS | $8,000.00 | $1,000.00 | $5,000.00 | $10,000.00 |
| 3 | 500-7001 | MOBILIZATION | 1 | LS | $12,440.00 | $3,000.00 | $20,000.00 | $20,000.00 |
| 4 | 502-7001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 1 | MO | $8,000.00 | $5,000.00 | $3,000.00 | $19,500.00 |
| 5 | 503-7001 | PORTABLE CHANGEABLE MESSAGE SIGN | 14 | DAY | $100.00 | $1.00 | $50.00 | $85.00 |
| 6 | 505-7001 | TMA (STATIONARY) | 14 | DAY | $250.00 | $1.00 | $50.00 | $100.00 |
| 7 | 784-7002 | REP STL BRIDGE MEMBER (BEAM) | 1 | EA | $75,000.00 | $70,000.00 | $60,000.00 | $71,500.00 |
| 8 | 784-7003 | REP STL BRIDGE MEMBER (DIAPHRAGM) | 4 | EA | $3,500.00 | $1,500.00 | $3,500.00 | $2,500.00 |