6479-62-001 Cement CC Area Office
- Let date
- Tuesday, March 18, 2025
- CCSJ
- 6479-62-001
- District
- Corpus Christi
- County
- Nueces
- Highway
- SH0358
- Limits
- VARIOUS to .
- Classification
- Material Maintenance Project · Maintenance
- Project number
- MMC - A00213885
- Working days
- 180
- DBE goal
- 0%
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $244,830 | ||
| 1 | AKA-MATERIALS Low bidder | $238,180 | -2.7% | |
| 2 | TOUCHSTONE RESOURCES, LLC | $239,755 | -2.1% | +0.7% |
| 3 | SOUTHERN SOURCING SOLUTIONS, LLC | $252,824 | +3.3% | +6.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 AKA-MATERIALS | #2 TOUCHSTONE RESO… | #3 SOUTHERN SOURCI… |
|---|---|---|---|---|---|---|---|---|
| 1 | 8009-7001 | HYDRAULIC CEMENT(TY I)(DEL)(ST 1) | 500 | TON | $225.00 | $215.00 | $220.00 | $225.50 |
| 2 | 8009-7002 | HYDRAULIC CEMENT(TY I)(DEL)(ST 2) | 500 | TON | $225.00 | $215.00 | $220.00 | $225.50 |
| 3 | 8009-7037 | HYDRAULIC CEMENT(TY I)(DEL)(47LB)(ST 1) | 500 | BAG | $8.30 | $9.90 | $8.25 | $11.55 |
| 4 | 8009-7038 | HYDRAULIC CEMENT(TY I)(DEL)(47LB)(ST 2) | 500 | BAG | $8.30 | $9.80 | $8.25 | $11.55 |
| 5 | 8009-7039 | HYDRAULIC CEMENT(TY I)(DEL)(47LB)(ST 3) | 500 | BAG | $8.30 | $9.50 | $8.25 | $11.55 |
| 6 | 8009-7055 | HYDRAULIC CEMENT(TY I)(DEL)(94LB)(ST 1) | 300 | BAG | $12.30 | $14.35 | $12.30 | $16.67 |
| 7 | 8009-7056 | HYDRAULIC CEMENT(TY I)(DEL)(94LB)(ST 2) | 300 | BAG | $12.30 | $14.25 | $12.30 | $16.67 |