Culvert Extension Cross Drainage 07 0425
- Let date
- Wednesday, June 11, 2025
- CCSJ
- 6477-45-001
- District
- Dallas
- County
- Collin
- Highway
- BS0289C
- Limits
- VARIOUS ROADWAYS IN THE COLLIN to COUNTY MAINTENANCE SECTION
- Classification
- Routine Maintenance Project - Sealed · Maintenance
- Project number
- RMC - A00213054
- Working days
- 19
- DBE goal
- 0%
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $205,679 | ||
| 1 | QUALITY EXCAVATION, LLC Low bidder | $170,348 | -17.2% | |
| 2 | GARRET SHIELDS INFRASTRUCTURE | $182,370 | -11.3% | +7.1% |
| 3 | CROSS PLUS CONSTRUCTION, LLC | $183,594 | -10.7% | +7.8% |
| 4 | XIT PAVING AND CONSTRUCTION INC. | $199,910 | -2.8% | +17.4% |
| 5 | JAGOE-PUBLIC COMPANY | $257,390 | +25.1% | +51.1% |
| 6 | PALMER HALL CONSTRUCTION | $391,080 | +90.1% | +129.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 QUALITY EXCAVAT… | #2 GARRET SHIELDS … | #3 CROSS PLUS CONS… | #4 XIT PAVING AND … | #5 JAGOE-PUBLIC CO… | #6 PALMER HALL CON… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 400-7006 | CUT & RESTORING PAV | 148 | SY | $181.67 | $245.00 | $250.00 | $200.00 | $150.00 | $100.00 | $180.00 |
| 2 | 400-7010 | CEM STABIL BKFL | 148 | CY | $280.00 | $135.00 | $250.00 | $259.00 | $150.00 | $50.00 | $105.00 |
| 3 | 402-7001 | TRENCH EXCAVATION PROTECTION | 56 | LF | $26.76 | $18.00 | $10.00 | $25.00 | $50.00 | $15.00 | $150.00 |
| 4 | 432-7041 | RIPRAP (STONE PROTECTION)(12 IN) | 61 | CY | $263.00 | $180.00 | $250.00 | $300.00 | $450.00 | $750.00 | $200.00 |
| 5 | 464-7010 | RC PIPE (CL III)(42 IN) | 112 | LF | $325.00 | $210.00 | $180.00 | $252.00 | $365.00 | $600.00 | $600.00 |
| 6 | 466-7121 | HEADWALL (CH - PW - S) (DIA= 42 IN) | 2 | EA | $20,000.00 | $20,500.00 | $15,000.00 | $7,200.00 | $19,000.00 | $28,000.00 | $30,000.00 |
| 7 | 496-7007 | REMOV STR (PIPE) | 60 | LF | $20.47 | $108.00 | $100.00 | $55.00 | $50.00 | $200.00 | $400.00 |
| 8 | 500-7001 | MOBILIZATION | 1 | LS | $16,982.08 | $17,000.00 | $15,000.00 | $15,000.00 | $10,000.00 | $28,500.00 | $150,000.00 |
| 9 | 502-7001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 2 | MO | $5,000.00 | $2,500.00 | $5,000.00 | $17,500.00 | $16,500.00 | $11,500.00 | $5,000.00 |
| 10 | 505-7001 | TMA (STATIONARY) | 38 | DAY | $400.00 | $240.00 | $300.00 | $1.00 | $10.00 | $50.00 | $450.00 |