Hot Mix FY25
- Let date
- Friday, January 3, 2025
- CCSJ
- 6476-37-001
- District
- Dallas
- County
- Collin
- Highway
- SH0005
- Limits
- Collin County to Maintenance Section
- Classification
- Material Maintenance Project · Maintenance
- Project number
- MMC - 647637001
- Working days
- 180
- DBE goal
- 0%
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $296,500 | ||
| 1 | USA AMTECH, INC. Low bidder | $277,608 | -6.4% | |
| 2 | AUSTIN ASPHALT, INC. | $281,000 | -5.2% | +1.2% |
| 3 | TOUCHSTONE RESOURCES, LLC | $320,300 | +8.0% | +15.4% |