Baylor ROW Mowing FY25
- Let date
- Wednesday, March 19, 2025
- CCSJ
- 6476-07-001
- District
- Wichita Falls
- County
- Baylor
- Highway
- US0082
- Limits
- Baylor County to various roadways
- Classification
- Routine Maintenance Project · Maintenance
- Project number
- RMC - A00212744
- Working days
- 60
- DBE goal
- 0%
Bidders 7
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $220,340 | ||
| 1 | ABESCAPE GROUP LLC Low bidder | $185,145 | -16.0% | |
| 2 | A M FABRICATION INC. | $205,646 | -6.7% | +11.1% |
| 3 | CLAW CONTRACTORS, LLC | $211,892 | -3.8% | +14.4% |
| 4 | CROSS PLUS CONSTRUCTION, LLC | $219,523 | -0.4% | +18.6% |
| 5 | CEHAND SERVICES LLC | $261,480 | +18.7% | +41.2% |
| 6 | ANTHONY SERVICES | $284,376 | +29.1% | +53.6% |
| 7 | ArborTrue LLC | $472,980 | +114.7% | +155.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 ABESCAPE GROUP … | #2 A M FABRICATION… | #3 CLAW CONTRACTOR… | #4 CROSS PLUS CONS… | #5 CEHAND SERVICES… | #6 ANTHONY SERVICES | #7 ArborTrue LLC |
|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 505-7003 | TMA (MOBILE OPERATION) | 42 | DAY | $351.20 | $1.00 | $300.00 | $10.00 | $1.00 | $1,000.00 | $500.00 | $1,411.76 |
| 2 | 730-7020 | STRIP MOWING | 1,001 | AC | $40.33 | $13.50 | $36.00 | $32.00 | $40.00 | $40.00 | $48.00 | $51.39 |
| 3 | 730-7022 | FULL - WIDTH MOWING | 4,486 | AC | $36.83 | $38.25 | $35.00 | $40.00 | $40.00 | $40.00 | $48.00 | $80.75 |