SNOW AND ICE CONTROL
- Let date
- Thursday, August 3, 2023
- CCSJ
- 6446-86-001
- District
- Amarillo
- County
- Randall
- Highway
- IH 27
- Limits
- VARIOUS LOCATIONS ~ SEE PLAN SHEETS to VARIOUS LOCATIONS ~ SEE PLAN SHEETS
- Classification
- Maintenance
- Project number
- MMC - 644686001
- Working days
- 120
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $132,239 | ||
| 1 | NSG LOGISTICS, LLC Low bidder | $116,953 | -11.6% | |
| 2 | SOUTHWEST ENVIROTX PARTNERS, LLC | $124,150 | -6.1% | +6.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 NSG LOGISTICS, … | #2 SOUTHWEST ENVIR… |
|---|---|---|---|---|---|---|---|
| 1 | 8042-6230 | COMPLEX CHLORIDE(SLD)(DEL)(SITE 1) | 25 | TON | $406.89 | $354.25 | $382.00 |
| 2 | 8042-6231 | COMPLEX CHLORIDE(SLD)(DEL)(SITE 2) | 100 | TON | $406.89 | $351.33 | $382.00 |
| 3 | 8042-6234 | COMPLEX CHLORIDE(SLD)(DEL)(SITE 5) | 25 | TON | $406.89 | $349.14 | $382.00 |
| 4 | 8042-6237 | COMPLEX CHLORIDE(SLD)(DEL)(SITE 8) | 100 | TON | $406.89 | $374.42 | $382.00 |
| 5 | 8042-6240 | COMPLEX CHLORIDE(SLD)(DEL)(SITE 11) | 25 | TON | $406.89 | $347.93 | $382.00 |
| 6 | 8042-6245 | COMPLEX CHLORIDE(SLD)(DEL)(SITE 16) | 25 | TON | $406.89 | $360.08 | $382.00 |
| 7 | 8042-6247 | COMPLEX CHLORIDE(SLD)(DEL)(SITE 18) | 25 | TON | $406.89 | $363.73 | $382.00 |