FULL DEPTH CONCRETE REPAIR
- Let date
- Wednesday, August 2, 2023
- CCSJ
- 6439-40-001
- District
- Dallas
- County
- Collin
- Highway
- US 75
- Limits
- VARIOUS ROADWAYS IN THE COLLIN to COUNTY MAINTENANCE SECTION
- Classification
- Maintenance
- Project number
- RMC - 643940001
- Working days
- 36
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $309,015 | ||
| 1 | O. TREVINO CONSTRUCTION, LLC Low bidder | $296,740 | -4.0% | |
| 2 | ROY JORGENSEN ASSOCIATES, INC. | $298,990 | -3.2% | +0.8% |
| 3 | GARRET SHIELDS INFRASTRUCTURE | $327,800 | +6.1% | +10.5% |
| 4 | ICOS MANAGEMENT, LLC | $341,504 | +10.5% | +15.1% |
| 5 | FNH CONSTRUCTION, LLC | $442,000 | +43.0% | +49.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 O. TREVINO CONS… | #2 ROY JORGENSEN A… | #3 GARRET SHIELDS … | #4 ICOS MANAGEMENT… | #5 FNH CONSTRUCTIO… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 361-6065 | FULL-DEPTH REPAIR CRCP (8"-10") | 630 | SY | $325.00 | $323.00 | $325.00 | $360.00 | $425.00 | $400.00 |
| 2 | 361-6084 | FULL DEPTH REPAIR CPCD (8"-10" | 150 | SY | $325.00 | $323.00 | $268.00 | $300.00 | $425.00 | $500.00 |
| 3 | 500-6001 | MOBILIZATION | 1 | LS | $25,515.00 | $29,000.00 | $30,000.00 | $25,000.00 | $1.00 | $45,000.00 |
| 4 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 3 | MO | $2,000.00 | $3,800.00 | $8,000.00 | $5,000.00 | $1.00 | $20,000.00 |
| 5 | 6185-6002 | TMA (STATIONARY) | 40 | DAY | $600.00 | $110.00 | $1.00 | $400.00 | $250.00 | $250.00 |