CULVERT CLEANING
- Let date
- Wednesday, November 1, 2023
- CCSJ
- 6427-47-001
- District
- Abilene
- County
- Taylor
- Highway
- IH 20
- Limits
- VARIOUS LOCATIONS IN to THE ABILENE DISTRICT
- Classification
- Maintenance
- Project number
- RMC - 642747001
- Working days
- 153
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $760,700 | ||
| 1 | STX CIVIL Low bidder | $710,250 | -6.6% | |
| 2 | AAD CONTRACTING INC. | $844,900 | +11.1% | +19.0% |
| 3 | E.V.G. ENTERPRISE | $910,106 | +19.6% | +28.1% |
| 4 | HJC FARMS, INC. | $923,300 | +21.4% | +30.0% |
| 5 | ICOS MANAGEMENT, LLC | $1,037,715 | +36.4% | +46.1% |
| 6 | FNH CONSTRUCTION, LLC | $1,345,000 | +76.8% | +89.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 STX CIVIL | #2 AAD CONTRACTING… | #3 E.V.G. ENTERPRI… | #4 HJC FARMS, INC. | #5 ICOS MANAGEMENT… | #6 FNH CONSTRUCTIO… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 480-6001 | CLEAN EXIST CULVERTS | 72 | EA | $8,400.00 | $7,350.00 | $8,000.00 | $7,500.00 | $12,000.00 | $13,200.00 | $13,500.00 |
| 2 | 500-6001 | MOBILIZATION | 1 | LS | $75,000.00 | $64,000.00 | $120,000.00 | $320,000.00 | $25,000.00 | $65,000.00 | $120,000.00 |
| 3 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 9 | MO | $3,000.00 | $5,500.00 | $7,000.00 | $200.00 | $1,000.00 | $1.00 | $8,500.00 |
| 4 | 752-6004 | TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 4 | AC | $2,000.00 | $3,500.00 | $10,000.00 | $12,000.00 | $2,500.00 | $5,500.00 | $25,000.00 |
| 5 | 6185-6002 | TMA (STATIONARY) | 306 | DAY | $150.00 | $175.00 | $150.00 | $1.00 | $50.00 | $1.00 | $250.00 |