Bid tab 6426-32-001

Let Apr 19, 2023 · San Antonio · Guadalupe Sign up free

‹ Apr 2023 results

EROSION REPAIR

Let date
Wednesday, April 19, 2023
CCSJ
6426-32-001
District
San Antonio
County
Guadalupe
Highway
FM 20
Limits
AT YORK CREEK to AT YORK CREEK
Classification
Local Let
Project number
BPM - 642632001
Working days
20

Bidders 8

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$191,202
1 DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC. Low bidder $152,035 -20.5%
2 BECK-REIT & SONS, LTD. $174,404 -8.8% +14.7%
3 SCOUT 5 CONSTRUCTION LLC $188,499 -1.4% +24.0%
4 GARRET SHIELDS INFRASTRUCTURE $193,596 +1.3% +27.3%
5 DAN WILLIAMS COMPANY $196,719 +2.9% +29.4%
6 SJ&J CONSTRUCTION, LLC $196,745 +2.9% +29.4%
7 TALBRAN ENTERPRISES LLC $203,866 +6.6% +34.1%
8 MB WESTERN INDUSTRIAL CONTRACTING COMPANY $233,785 +22.3% +53.8%

Bid tab: unit prices 17 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 DALRYMPLE GRAVE…#2 BECK-REIT & SON…#3 SCOUT 5 CONSTRU…#4 GARRET SHIELDS …#5 DAN WILLIAMS CO…#6 SJ&J CONSTRUCTI…#7 TALBRAN ENTERPR…#8 MB WESTERN INDU…
1104-6009 REMOVING CONC (RIPRAP)70SY $25.33 $20.00 $50.00 $107.14 $50.00 $30.00 $25.00 $110.00 $50.00
2104-6028 REMOVING CONC (MISC)250SY $43.63 $20.00 $50.00 $48.00 $50.00 $10.00 $40.00 $55.00 $50.00
3161-6017 COMPOST MANUF TOPSOIL (4")112SY $15.37 $10.00 $10.00 $29.46 $5.00 $15.00 $16.00 $30.00 $5.00
4164-6003 BROADCAST SEED (PERM) (RURAL) (CLAY)112SY $2.57 $2.50 $10.00 $4.46 $3.00 $3.00 $1.50 $1.00 $2.00
5169-6001 SOIL RETENTION BLANKETS (CL 1) (TY A)112SY $7.06 $2.50 $5.00 $4.46 $5.00 $6.00 $3.50 $6.00 $3.00
6401-6001 FLOWABLE BACKFILL20CY $383.11 $350.00 $380.00 $650.00 $600.00 $700.00 $220.00 $660.00 $250.00
7432-6022 RIPRAP (STONE COMMON)(DRY)(6 IN)350CY $239.38 $100.00 $144.00 $160.00 $140.00 $135.00 $160.00 $245.00 $250.00
8459-6007 GABION MATTRESSES (GALV)(12 IN)320SY $138.12 $135.00 $144.00 $93.75 $150.00 $134.00 $140.00 $165.00 $200.00
9459-6011 GABIONS (5'X 3')(GALV)70CY $273.63 $385.00 $280.00 $357.14 $400.00 $375.00 $250.00 $310.00 $350.00
10500-6001 MOBILIZATION1LS $6,000.00 $15,000.00 $22,222.00 $17,000.00 $15,000.00 $18,500.00 $40,000.00 $1.00 $20,000.00
11502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLING2MO $1,500.00 $2,500.00 $3,000.00 $250.00 $5,000.00 $14,000.00 $7,000.00 $1.00 $2,500.00
12506-6020 CONSTRUCTION EXITS (INSTALL) (TY 1)112SY $36.44 $25.00 $10.00 $125.00 $10.00 $26.95 $8.00 $1.00 $30.00
13506-6024 CONSTRUCTION EXITS (REMOVE)112SY $3.64 $15.00 $1.00 $31.25 $10.00 $13.00 $6.00 $1.00 $15.00
14506-6041 BIODEG EROSN CONT LOGS (INSTL) (12")75LF $7.63 $10.00 $5.00 $6.67 $8.00 $5.50 $3.50 $11.00 $10.00
15506-6043 BIODEG EROSN CONT LOGS (REMOVE)75LF $3.64 $1.00 $1.00 $2.67 $4.00 $0.8500 $1.50 $6.00 $5.00
16752-6015 TREE AND BRUSH REMOVAL0.1AC $11,323.19 $10,000.00 $20,000.00 $50,000.00 $50,000.00 $40,000.00 $10,000.00 $33,000.00 $5,000.00
176185-6002 TMA (STATIONARY)20DAY $272.85 $275.00 $1.00 $0.0100 $300.00 $180.00 $150.00 $1.00 $200.00