BRIDGE PREVENTATIVE MAINTENANCE

Let date
Thursday, December 15, 2022
CCSJ
6407-39-001
District
Laredo
County
Val Verde
Highway
US 277
Limits
VARIOUS to VARIOUS
Classification
Local Let
Project number
BPM - 640739001
Working days
120

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$290,758
1 TALBRAN ENTERPRISES LLC Low bidder $281,460 -3.2%
2 AAD CONTRACTING INC. $369,981 +27.2% +31.5%
3 BECK-REIT & SONS, LTD. $389,220 +33.9% +38.3%
4 SCR CIVIL CONSTRUCTION, LLC $563,033 +93.6% +100.0%
5 AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC $611,238 +110.2% +117.2%

Bid tab: unit prices 14 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 TALBRAN ENTERPR…#2 AAD CONTRACTING…#3 BECK-REIT & SON…#4 SCR CIVIL CONST…#5 AMERICAN INFRAS…
1401-6001 FLOWABLE BACKFILL1CY $600.00 $400.00 $250.00 $300.00 $1,100.00 $9,500.00
2429-6007 CONC STR REPAIR (VERTICAL & OVERHEAD)718.5SF $165.00 $160.00 $150.00 $235.00 $245.00 $425.00
3432-6001 RIPRAP (CONC)(4 IN)10CY $550.00 $900.00 $900.00 $1,500.00 $2,000.00 $750.00
4459-6007 GABION MATTRESSES (GALV)(12 IN)75SY $200.00 $200.00 $200.00 $140.00 $200.00 $125.00
5467-6004 SET (REPLACE PIPE RUNNER)3EA $600.00 $3,500.00 $3,000.00 $2,000.00 $4,500.00 $2,500.00
6480-6001 CLEAN EXIST CULVERTS8EA $2,400.00 $4,000.00 $2,000.00 $13,000.00 $22,200.00 $2,500.00
7500-6001 MOBILIZATION1LS $23,705.25 $25,000.00 $111,656.00 $36,000.00 $56,200.00 $60,000.00
8502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLING6MO $5,000.00 $4,000.00 $7,000.00 $2,000.00 $3,000.00 $6,000.00
9760-6001 DITCH CLEANING AND RESHAPING (FOOT)100LF $50.00 $20.00 $10.00 $100.00 $90.00 $20.00
10780-6004 CONC CRCK REPR(DISCRETE)(ROUT AND SEAL)10LF $100.00 $200.00 $50.00 $10.00 $200.00 $1,000.00
11780-6010 CNC CRACK REPAIR (DISCRETE)(SURF SEAL)100LF $320.00 $80.00 $50.00 $100.00 $50.00 $200.00
126001-6002 PORTABLE CHANGEABLE MESSAGE SIGN2EA $10,000.00 $4,500.00 $15,000.00 $200.00 $8,000.00 $25,000.00
136185-6002 TMA (STATIONARY)72DAY $200.00 $300.00 $150.00 $1.00 $300.00 $1,000.00
147212-6002 CLEANING SUBSTRUCTURE (ABUT)8EA $500.00 $1,000.00 $1,500.00 $2,000.00 $4,000.00 $250.00