REPAIR/REPLACE CONCRETE BARRIER
- Let date
- Tuesday, February 8, 2022
- CCSJ
- 6392-05-001
- District
- Dallas
- County
- Navarro
- Highway
- IH 45
- Limits
- VARIOUS ROADWAYS IN THE to NAVARRO COUNTY MAINTENANCE SECTION
- Classification
- Local Let
- Project number
- RMC - 639205001
- Working days
- 365
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $290,927 | ||
| 1 | GIBSON & ASSOCIATES, INC. Low bidder | $295,394 | +1.5% | |
| 2 | IBCTX, LLC | $313,000 | +7.6% | +6.0% |
| 3 | DIGG COMMERCIAL, LLC | $320,830 | +10.3% | +8.6% |
| 4 | ROY JORGENSEN ASSOCIATES, INC. | $386,550 | +32.9% | +30.9% |
| 5 | O. TREVINO CONSTRUCTION, LLC | $388,478 | +33.5% | +31.5% |
| 6 | FNH CONSTRUCTION, LLC | $496,050 | +70.5% | +67.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 GIBSON & ASSOCI… | #2 IBCTX, LLC | #3 DIGG COMMERCIAL… | #4 ROY JORGENSEN A… | #5 O. TREVINO CONS… | #6 FNH CONSTRUCTIO… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 429-6007 | CONC STR REPAIR (VERTICAL & OVERHEAD) | 1,050 | SF | $200.00 | $181.00 | $190.00 | $50.00 | $165.00 | $200.55 | $325.00 |
| 2 | 496-6099 | REMOVE STR (RAIL) | 100 | LF | $20.00 | $100.00 | $50.00 | $10.00 | $20.00 | $185.00 | $100.00 |
| 3 | 500-6033 | MOBILIZATION (CALLOUT) | 8 | EA | $450.00 | $500.00 | $750.00 | $100.00 | $500.00 | $2,000.00 | $2,000.00 |
| 4 | 500-6034 | MOBILIZATION (EMERGENCY) | 6 | EA | $1,200.00 | $1,000.00 | $1,000.00 | $150.00 | $1,000.00 | $2,500.00 | $5,000.00 |
| 5 | 514-6013 | PERM CTB (F-SHAPE) (TY 1) | 100 | LF | $70.00 | $216.00 | $250.00 | $50.00 | $500.00 | $350.00 | $250.00 |
| 6 | 514-6014 | PERM CTB (F-SHAPE) (TY 2) | 200 | LF | $210.00 | $216.00 | $300.00 | $50.00 | $600.00 | $375.00 | $250.00 |
| 7 | 6001-6001 | PORTABLE CHANGEABLE MESSAGE SIGN | 42 | DAY | $68.50 | $132.00 | $125.00 | $15.00 | $150.00 | $200.00 | $150.00 |
| 8 | 6185-6002 | TMA (STATIONARY) | 50 | DAY | $325.00 | $300.00 | $125.00 | $5,000.00 | $500.00 | $200.00 | $350.00 |