INSTALLATION OF WATERBASE STRIPING
- Let date
- Wednesday, August 11, 2021
- CCSJ
- 6383-86-001
- District
- Lufkin
- County
- Angelina
- Highway
- US 59
- Limits
- VARIOUS LOCATIONS to DISTRICT WIDE
- Classification
- Local Let
- Project number
- RMC - 638386001
- Working days
- 365
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $269,400 | ||
| 1 | STRIPING TECHNOLOGY, L.P. Low bidder | $225,560 | -16.3% | |
| 2 | PMI PAVEMENT MARKING, LLC | $245,960 | -8.7% | +9.0% |
| 3 | STRIPE-A-ZONE, INC. | $263,310 | -2.3% | +16.7% |
| 4 | INTERSTATE BARRICADES & MARKINGS, INC. | $299,000 | +11.0% | +32.6% |
| 5 | TOTAL HIGHWAY MAINTENANCE, LLC | $469,500 | +74.3% | +108.1% |
| 6 | TRP CONSTRUCTION GROUP, LLC | $552,500 | +105.1% | +144.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 STRIPING TECHNO… | #2 PMI PAVEMENT MA… | #3 STRIPE-A-ZONE, … | #4 INTERSTATE BARR… | #5 TOTAL HIGHWAY M… | #6 TRP CONSTRUCTIO… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-6033 | MOBILIZATION (CALLOUT) | 6 | EA | $500.00 | $2,000.00 | $1,000.00 | $1,000.00 | $1,500.00 | $4,000.00 | $7,500.00 |
| 2 | 666-6167 | REFL PAV MRK TY II (W) 4" (BRK) | 50,000 | LF | $0.1400 | $0.1200 | $0.1500 | $0.1250 | $0.1600 | $0.2500 | $0.2500 |
| 3 | 666-6170 | REFL PAV MRK TY II (W) 4" (SLD) | 1,050,000 | LF | $0.1000 | $0.0900 | $0.1000 | $0.1100 | $0.1200 | $0.1800 | $0.2000 |
| 4 | 666-6178 | REFL PAV MRK TY II (W) 8" (SLD) | 8,000 | LF | $0.3000 | $0.5000 | $0.3000 | $0.2500 | $0.2500 | $0.7500 | $0.5000 |
| 5 | 666-6205 | REFL PAV MRK TY II (Y) 4" (BRK) | 100,000 | LF | $0.1400 | $0.1000 | $0.1500 | $0.1250 | $0.1600 | $0.2500 | $0.2500 |
| 6 | 666-6207 | REFL PAV MRK TY II (Y) 4" (SLD) | 1,100,000 | LF | $0.1200 | $0.0900 | $0.1000 | $0.1100 | $0.1200 | $0.1800 | $0.2000 |
| 7 | 6185-6005 | TMA (MOBILE OPERATION) | 60 | DAY | $100.00 | $1.00 | $1.00 | $1.00 | $100.00 | $250.00 | $600.00 |