Bid tab 6383-10-001

Let May 5, 2022 · Fort Worth · Parker Sign up free

‹ May 2022 results

GUARDRAIL INSTALLATION & REPAIR

Let date
Thursday, May 5, 2022
CCSJ
6383-10-001
District
Fort Worth
County
Parker
Highway
IH 20
Limits
VARIOUS LOCATIONS IN to PARKER AND PALO PINTO COUNTIES
Classification
Maintenance
Project number
RMC - 638310001
Working days
730

Bidders 2

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$1,196,206
1 SHORT-LINE CORPORATION Low bidder $1,579,568 +32.0%
2 VANN/ELLI, INC. $2,179,920 +82.2% +38.0%

Bid tab: unit prices 31 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 SHORT-LINE CORP…#2 VANN/ELLI, INC.
1500-6033 MOBILIZATION (CALLOUT)48EA $260.21 $1.00 $450.00
2500-6034 MOBILIZATION (EMERGENCY)10EA $655.67 $1,000.00 $2,250.00
3540-6006 MTL BEAM GD FEN TRANS (THRIE-BEAM)20EA $1,946.81 $1,500.00 $2,500.00
4540-6016 DOWNSTREAM ANCHOR TERMINAL SECTION25EA $2,009.35 $1,000.00 $1,620.00
5544-6001 GUARDRAIL END TREATMENT (INSTALL)4EA $3,055.56 $2,500.00 $3,780.00
6770-6001 REPAIR RAIL ELEMENT (W - BEAM)15,000LF $3.71 $15.00 $20.00
7770-6010 REM / REPL TIMBER/STL POST W/O CONC FND1,000EA $15.94 $35.00 $82.00
8770-6011 REM / REPL TIMBER / STL POST W/CONC FND50EA $52.78 $1.00 $82.00
9770-6017 REALIGN POSTS250EA $76.82 $100.00 $20.00
10770-6019 REMOVE & REPLACE BLOCKOUT900EA $81.46 $1.00 $18.00
11770-6021 REPLACE SINGLE GDRAIL TERMINAL RAIL500LF $11.25 $15.00 $40.00
12770-6022 REPLACE SINGLE GDRAIL TERMINAL POST75EA $70.83 $50.00 $100.00
13770-6027 REMOVE GDRAIL END TRT / REPL WITH SGT50EA $3,128.95 $3,000.00 $3,780.00
14770-6028 REPL SINGLE GDRAIL TERM IMPACT HEAD15EA $1,233.33 $1,000.00 $900.00
15770-6029 REM & RESET SGT IMPACT HEAD5EA $24.24 $200.00 $180.00
16770-6030 REPLACE SGT CABLE ASSEMBLY10EA $38.38 $100.00 $100.00
17770-6031 REPLACE SGT CABLE ANCHOR5EA $56.62 $1.00 $100.00
18770-6032 REPLACE SGT STRUT5EA $52.33 $1.00 $100.00
19771-6001 REPLACE POSTS (TL-3)2,100EA $170.53 $200.00 $235.00
20771-6002 REPLACE POSTS (TL-4)2,500EA $95.00 $200.00 $300.00
21771-6003 CABLE SPLICE / TURNBUCKLE (TL-3)5EA $164.81 $1.00 $450.00
22771-6005 REPAIR CONCRETE FOUNDATION (TL-3)5EA $75.00 $1.00 $100.00
23771-6007 REPR OR REPLC CABLE BARR TERM SEC(TL-3)15EA $1,204.05 $1,500.00 $2,000.00
24771-6008 REPR OR REPLC CABLE BARR TERM SEC(TL-4)15EA $1,636.36 $1,500.00 $2,000.00
25771-6009 REPLACE CABLE (TL-3)300LF $4.74 $1.00 $10.00
26771-6011 CHECK / RE-TENSION CABLE50EA $1,035.88 $100.00 $270.00
27771-6012 REPLACE POST HARDWARE (TL-4)300EA $21.88 $100.00 $45.00
28774-6006 REPAIR (TRACC)2EA $3,181.82 $5,000.00 $5,000.00
29774-6008 REPAIR (WIDE TRACC)2EA $3,500.00 $5,000.00 $5,000.00
306001-6001 PORTABLE CHANGEABLE MESSAGE SIGN50DAY $40.45 $100.00 $135.00
316185-6005 TMA (MOBILE OPERATION)150DAY $50.00 $100.00 $180.00