MATERIALS ONLY: HMCL
- Let date
- Wednesday, November 4, 2020
- CCSJ
- 6369-92-001
- District
- Abilene
- County
- Taylor
- Highway
- IH 20
- Limits
- ABILENE DISTRICT EAST to ABILENE DISTRICT EAST
- Classification
- Maintenance
- Project number
- MMC - 636992001
- Working days
- 120
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,260,000 | ||
| 1 | ZACK BURKETT CO. Low bidder | $1,110,300 | -11.9% | |
| 2 | VULCAN CONSTRUCTION MATERIALS, LLC | $1,229,880 | -2.4% | +10.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 ZACK BURKETT CO. | #2 VULCAN CONSTRUC… |
|---|---|---|---|---|---|---|---|
| 1 | 8013-6009 | HMCL ACP TYPE D (DELIVERY)(SITE 1) | 2,000 | TON | $95.00 | $75.50 | $91.78 |
| 2 | 8013-6010 | HMCL ACP TYPE D (DELIVERY)(SITE 2) | 2,000 | TON | $95.00 | $84.00 | $91.14 |
| 3 | 8013-6011 | HMCL ACP TYPE D (DELIVERY)(SITE 3) | 2,000 | TON | $85.00 | $80.15 | $87.34 |
| 4 | 8013-6012 | HMCL ACP TYPE D (DELIVERY)(SITE 4) | 2,000 | TON | $85.00 | $73.00 | $87.34 |
| 5 | 8013-6013 | HMCL ACP TYPE D (DELIVERY)(SITE 5) | 2,000 | TON | $95.00 | $85.00 | $89.70 |
| 6 | 8013-6014 | HMCL ACP TYPE D (DELIVERY)(SITE 6) | 2,000 | TON | $85.00 | $80.00 | $83.82 |
| 7 | 8013-6015 | HMCL ACP TYPE D (DELIVERY)(SITE 7) | 2,000 | TON | $90.00 | $77.50 | $83.82 |