FLEXIBLE BASE (MATERIALS ONLY)
- Let date
- Wednesday, September 9, 2020
- CCSJ
- 6367-69-001
- District
- Amarillo
- County
- Hartley
- Highway
- FM 998
- Limits
- SEE PLAN SHEETS to SEE PLAN SHEETS
- Classification
- Local Let
- Project number
- MMC - 636769001
- Working days
- 120
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $188,000 | ||
| 1 | J. LEE MILLIGAN, INC. Low bidder | $207,886 | +10.6% | |
| 2 | L A FULLER & SONS CONSTRUCTION, LTD. | $212,456 | +13.0% | +2.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 J. LEE MILLIGAN… | #2 L A FULLER & SO… |
|---|---|---|---|---|---|---|---|
| 1 | 8007-6031 | FL BS (SITE DEL)(TY D GR 4)(SITE 1) | 5,000 | TON | $32.00 | $34.95 | $35.85 |
| 2 | 8007-6032 | FL BS (SITE DEL)(TY D GR 4)(SITE 2) | 350 | TON | $32.00 | $39.25 | $38.70 |
| 3 | 8007-6033 | FL BS (SITE DEL)(TY D GR 4)(SITE 3) | 525 | TON | $32.00 | $36.95 | $37.45 |