RAISED PAVEMENT MARKER MAINTENANCE
- Let date
- Thursday, April 9, 2020
- CCSJ
- 6359-41-001
- District
- Waco
- County
- Bell
- Highway
- US 190
- Limits
- DW BELL,BOSQUE,CORYELL,FALLS,HAMILT to HILL,LIMESTONE AND MCLENNAN COUNTIE
- Classification
- Maintenance
- Project number
- RMC - 635941001
- Working days
- 365
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $520,944 | ||
| 1 | BRYDL CONTRACTING, INC. Low bidder | $318,759 | -38.8% | |
| 2 | PAVEMENT MARKINGS INC. | $457,510 | -12.2% | +43.5% |
| 3 | CROSS PLUS CONSTRUCTION, LLC | $483,463 | -7.2% | +51.7% |
| 4 | SELECT MAINTENANCE, L.L.C. | $558,950 | +7.3% | +75.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 BRYDL CONTRACTI… | #2 PAVEMENT MARKIN… | #3 CROSS PLUS CONS… | #4 SELECT MAINTENA… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-6033 | MOBILIZATION (CALLOUT) | 8 | EA | $2,504.54 | $1.00 | $4,500.00 | $2,200.00 | |
| 2 | 672-6006 | REFL PAV MRKR TY I-A | 5,620 | EA | $3.50 | $2.66 | $2.40 | $2.99 | |
| 3 | 672-6007 | REFL PAV MRKR TY I-C | 11,820 | EA | $3.65 | $2.66 | $3.80 | $3.25 | |
| 4 | 672-6008 | REFL PAV MRKR TY I-R | 4,260 | EA | $5.50 | $2.66 | $6.00 | $3.00 | |
| 5 | 672-6009 | REFL PAV MRKR TY II-A-A | 86,000 | EA | $3.50 | $2.66 | $3.20 | $3.00 | |
| 6 | 672-6010 | REFL PAV MRKR TY II-C-R | 10,720 | EA | $4.00 | $3.00 | $4.80 | $2.99 | |
| 7 | 6185-6003 | TMA (MOBILE OPERATION) | 1,089 | HR | $65.00 | $0.1000 | $10.00 | $99.00 |