RAISED PAVEMENT MARKER MAINTENANCE
- Let date
- Wednesday, July 11, 2018
- CCSJ
- 6330-19-001
- District
- Waco
- County
- Bell
- Highway
- US 190
- Limits
- VAR RDWYS IN BELL,BOSQUE,FALLS, HIL to CORYELL,HAMILTON,LIMESTONE & MCLENN
- Classification
- Maintenance
- Project number
- RMC - 633019001
- Working days
- 365
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $384,329 | ||
| 1 | BRYDL CONTRACTING, INC. Low bidder | $298,470 | -22.3% | |
| 2 | CROSS PLUS CONSTRUCTION, LLC | $334,995 | -12.8% | +12.2% |
| 3 | DBI SERVICES, LLC | $368,878 | -4.0% | +23.6% |
| 4 | PAVEMENT MARKINGS INC. | $379,130 | -1.4% | +27.0% |
| 5 | TOTAL HIGHWAY MAINTENANCE, LLC | $396,497 | +3.2% | +32.8% |
| 6 | STRIPE-A-ZONE, INC. | $444,966 | +15.8% | +49.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 BRYDL CONTRACTI… | #2 CROSS PLUS CONS… | #3 DBI SERVICES, L… | #4 PAVEMENT MARKIN… | #5 TOTAL HIGHWAY M… | #6 STRIPE-A-ZONE, … |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-6033 | MOBILIZATION (CALLOUT) | 6 | EA | $4,744.80 | $500.00 | $500.00 | $2,700.00 | $1,800.00 | $2,500.00 | $3,500.00 |
| 2 | 672-6006 | REFL PAV MRKR TY I-A | 5,620 | EA | $2.50 | $2.75 | $2.40 | $2.50 | $2.80 | $2.90 | $3.25 |
| 3 | 672-6007 | REFL PAV MRKR TY I-C | 11,820 | EA | $2.50 | $2.75 | $2.40 | $2.50 | $3.40 | $3.00 | $3.25 |
| 4 | 672-6008 | REFL PAV MRKR TY I-R | 4,260 | EA | $2.50 | $3.00 | $2.40 | $2.50 | $6.20 | $2.90 | $10.00 |
| 5 | 672-6009 | REFL PAV MRKR TY II-A-A | 86,000 | EA | $2.50 | $2.26 | $2.50 | $2.50 | $2.80 | $3.00 | $3.25 |
| 6 | 672-6010 | REFL PAV MRKR TY II-C-R | 10,720 | EA | $3.00 | $2.75 | $2.50 | $2.50 | $3.20 | $3.00 | $3.25 |
| 7 | 6185-6003 | TMA (MOBILE OPERATION) | 1,089 | HR | $50.00 | $10.00 | $35.00 | $52.00 | $10.00 | $25.00 | $9.50 |