TREE TRIMMING & TREE AND BRUSH REMOVAL
- Let date
- Tuesday, October 3, 2017
- CCSJ
- 6319-14-001
- District
- Dallas
- County
- Navarro
- Highway
- FM 1394
- Limits
- VARIOUS ROADWAYS IN NAVARRO COUNTY to IN MAINTENANCE SECTION
- Classification
- Maintenance
- Project number
- RMC - 631914001
- Working days
- 730
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $225,182 | ||
| 1 | CATOCON, INC. Low bidder | $193,365 | -14.1% | |
| 2 | CEN-TEX IRRIGATION SYSTEMS, INC. | $194,350 | -13.7% | +0.5% |
| 3 | KASPARIAN UNDERGROUND, LLC | $218,675 | -2.9% | +13.1% |
| 4 | CROSS PLUS CONSTRUCTION, LLC | $224,602 | -0.3% | +16.2% |
| 5 | J & M CONTRACTING, COMPANY | $285,175 | +26.6% | +47.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 CATOCON, INC. | #2 CEN-TEX IRRIGAT… | #3 KASPARIAN UNDER… | #4 CROSS PLUS CONS… | #5 J & M CONTRACTI… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-6033 | MOBILIZATION (CALLOUT) | 6 | EA | $300.00 | $3,000.00 | $1,500.00 | $1,000.00 | $500.00 | $6,000.00 |
| 2 | 752-6003 | TREE TRIMMING / BRUSH REMOVAL | 16 | MI | $2,000.00 | $4,000.00 | $3,800.00 | $3,800.00 | $3,500.00 | $2,000.00 |
| 3 | 752-6004 | TREE TRIMMING / BRUSH REMOVAL(CHANNELS) | 2 | AC | $1,200.00 | $4,000.00 | $2,800.00 | $10,000.00 | $3,500.00 | $5,000.00 |
| 4 | 752-6005 | TREE REMOVAL (4" - 12" DIA) | 405 | EA | $205.68 | $75.00 | $150.00 | $125.00 | $100.00 | $225.00 |
| 5 | 752-6006 | TREE REMOVAL (12" - 18" DIA) | 184 | EA | $218.65 | $160.00 | $180.00 | $225.00 | $300.00 | $350.00 |
| 6 | 752-6007 | TREE REMOVAL (18" - 24" DIA) | 47 | EA | $850.00 | $400.00 | $240.00 | $350.00 | $500.00 | $550.00 |
| 7 | 752-6008 | TREE REMOVAL (24" - 30" DIA) | 21 | EA | $850.00 | $750.00 | $400.00 | $600.00 | $1,200.00 | $800.00 |
| 8 | 752-6009 | TREE REMOVAL (30" - 36" DIA) | 9 | EA | $850.00 | $1,000.00 | $600.00 | $1,200.00 | $1,578.00 | $1,000.00 |