DREDGING
- Let date
- Wednesday, March 8, 2017
- CCSJ
- 6304-96-001
- District
- Houston
- County
- Galveston
- Highway
- SH 87
- Limits
- BOLIVAR FERRY LANDING to BOLIVAR FERRY LANDING
- Classification
- Maintenance
- Project number
- RMC - 630496001
- Working days
- 60
Bidders 5
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $3,625,000 | ||
| 1 | ORION CONSTRUCTION, L.P. Low bidder | $1,762,500 | -51.4% | |
| 2 | CALLAN MARINE LTD | $2,825,000 | -22.1% | +60.3% |
| 3 | LESTER CONTRACTING, INC. | $3,130,000 | -13.7% | +77.6% |
| 4 | MIKE HOOKS, L.L.C. | $3,200,000 | -11.7% | +81.6% |
| 5 | WEEKS MARINE, INC. | $4,875,000 | +34.5% | +176.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 ORION CONSTRUCT… | #2 CALLAN MARINE L… | #3 LESTER CONTRACT… | #4 MIKE HOOKS, L.L… | #5 WEEKS MARINE, I… |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 7084-6001 | DREDGING (SITE A) | 250,000 | CY | $4.00 | $4.75 | $8.00 | $6.70 | $8.00 | $7.00 |
| 2 | 7085-6001 | MOBILIZATION (SITE A) | 1 | EA | $2,625,000.00 | $575,000.00 | $825,000.00 | $1,455,000.00 | $1,200,000.00 | $3,125,000.00 |