CONCRETE PAVEMENT & SPALL REPAIR
- Let date
- Tuesday, October 15, 2013
- CCSJ
- 6262-76-001
- District
- Waco
- County
- McLennan
- Highway
- US 84
- Limits
- VARIOUS ROADWAYS IN to MCLENNAN COUNTY
- Classification
- Local Let
- Project number
- RMC - 626276001
- Working days
- 120
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $245,950 | ||
| 1 | VANN/ELLI, INC. Low bidder | $276,650 | +12.5% | |
| 2 | OMEGA CONSTRUCTION GROUP, LLC | $281,900 | +14.6% | +1.9% |
| 3 | EASTER CONSTRUCTION INC. | $305,000 | +24.0% | +10.2% |
| 4 | TEXAS TREE & LANDSCAPE, LTD. | $329,950 | +34.2% | +19.3% |
| 5 | O. TREVINO CONSTRUCTION, LLC | $355,550 | +44.6% | +28.5% |
| 6 | RAY FARIS, INC. | $370,030 | +50.4% | +33.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 VANN/ELLI, INC. | #2 OMEGA CONSTRUCT… | #3 EASTER CONSTRUC… | #4 TEXAS TREE & LA… | #5 O. TREVINO CONS… | #6 RAY FARIS, INC. |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 361-2003 | FULL-DEPTH REPAIR CRCP (10") | 150 | SY | $168.00 | $149.00 | $130.00 | $175.00 | $240.00 | $250.00 | $171.29 |
| 2 | 361-2009 | FULL-DEPTH REPAIR CPCD (8") | 150 | SY | $120.00 | $97.00 | $120.00 | $200.00 | $240.00 | $194.00 | $182.54 |
| 3 | 361-2020 | FULL-DEPTH REPAIR CPJR (9") | 50 | SY | $165.00 | $165.00 | $125.00 | $200.00 | $240.00 | $252.00 | $221.13 |
| 4 | 361-2028 | FULL-DEPTH REPAIR CRCP (6") | 300 | SY | $135.00 | $120.00 | $115.00 | $150.00 | $240.00 | $157.00 | $167.55 |
| 5 | 429-2010 | CNC STR REP (BRDG DECK)(FULL DEPTH) | 50 | SF | $80.00 | $85.00 | $73.00 | $275.00 | $200.00 | $197.00 | $194.61 |
| 6 | 500-2001 | MOBILIZATION | 1 | LS | $10,000.00 | $25,000.00 | $40,000.00 | $20,000.00 | $24,000.00 | $59,400.00 | $40,703.28 |
| 7 | 720-2003 | SPALLING REPAIR (POLYMERIC)(SEMIRIGID) | 5,000 | GAL | $28.00 | $33.25 | $32.00 | $32.00 | $27.99 | $32.00 | $41.04 |