Bid tab 2686-01-015

Let Mar 4, 2025 · Austin · Bastrop Sign up free

‹ Mar 2025 results

FM 2571 - AT Gazley Crk - 25 BMIP

Let date
Tuesday, March 4, 2025
CCSJ
2686-01-015
District
Austin
County
Bastrop
Highway
FM 2571
Limits
AT GAZLEY CREEK to .
Classification
Bridge Maintenance · Construction
Project number
BR 2025(554)
Working days
64
DBE goal
0%

Bidders 19

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$277,476
1 TAYLOR CONTRACTING LLC Low bidder $180,204 -35.1%
2 BECK-REIT & SONS, LTD. $182,924 -34.1% +1.5%
3 BK FIELD OPERATIONS LLC $195,344 -29.6% +8.4%
4 GARRET SHIELDS INFRASTRUCTURE $226,250 -18.5% +25.6%
5 DALRYMPLE GRAVEL AND CONTRACTING COMPANY, INC. $228,735 -17.6% +26.9%
6 PREMIER CONTRACTORS LLC $232,414 -16.2% +29.0%
7 ICOS MANAGEMENT, LLC $238,204 -14.2% +32.2%
8 STRUCTURAL INTEGRITY GROUP LLC $238,490 -14.1% +32.3%
9 RESTEK, INC. $250,273 -9.8% +38.9%
10 RHINO EQUITY, LLC $252,700 -8.9% +40.2%
11 MB WESTERN INDUSTRIAL CONTRACTING CO. $256,293 -7.6% +42.2%
12 AAD CONTRACTING INC. $267,595 -3.6% +48.5%
13 DAN WILLIAMS COMPANY $274,545 -1.1% +52.4%
14 BLACKSMITH VENTURES LLC $294,675 +6.2% +63.5%
15 AARON CONCRETE CONTRACTORS, LLC $338,640 +22.0% +87.9%
16 LAKEY, INC. $339,098 +22.2% +88.2%
17 APM INFRASTRUCTURE, LLC $340,820 +22.8% +89.1%
18 BUILT RIGHT CONSTRUCTION OF OKLAHOMA, LLC $341,180 +23.0% +89.3%
19 CROSS PLUS CONSTRUCTION, LLC $399,135 +43.8% +121.5%

Bid tab: unit prices 14 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 TAYLOR CONTRACT…#2 BECK-REIT & SON…#3 BK FIELD OPERAT…#4 GARRET SHIELDS …#5 DALRYMPLE GRAVE…#6 PREMIER CONTRAC…#7 ICOS MANAGEMENT…#8 STRUCTURAL INTE…
1100-7001 PREPARING ROW0.6AC $10,000.00 $7,500.00 $10,000.00 $25,000.00 $8,000.00 $20,000.00 $10,000.00 $5,000.00 $1,500.00
2104-7006 REMOV CONC (RIPRAP)375SY $65.00 $20.00 $55.00 $110.00 $40.00 $90.00 $60.00 $33.00 $30.00
3429-7007 CONC STR REPAIR (VERTICAL & OVERHEAD)40SF $450.00 $900.00 $220.00 $140.00 $200.00 $375.00 $250.00 $275.00 $300.00
4432-7045 RIPRAP (STONE PROTECTION)(24 IN)555CY $247.24 $180.00 $201.00 $194.00 $250.00 $195.00 $250.00 $259.00 $354.00
5438-7004 CLEANING AND SEALING EXIST JOINTS (CL3)144LF $55.00 $45.00 $55.00 $40.00 $50.00 $30.00 $100.00 $110.00 $25.00
6500-7001 MOBILIZATION1LS $39,000.00 $18,000.00 $18,800.00 $15,000.00 $25,000.00 $23,000.00 $20,000.00 $35,000.00 $9,000.00
7502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING4MO $7,500.00 $1.00 $1.00 $1.00 $5,000.00 $5,500.00 $1.00 $1.00 $1,000.00
8506-7022 CONSTRUCTION EXITS (INSTALL) (TY 3)60SY $40.00 $12.00 $50.00 $1.00 $10.00 $50.00 $50.00 $33.00 $1.00
9506-7024 CONSTRUCTION EXITS (REMOVE)60SY $17.62 $1.00 $10.00 $1.00 $1.00 $10.00 $20.00 $11.00 $1.00
10506-7039 TEMP SEDMT CONT FENCE (INSTALL)40LF $4.55 $5.00 $3.00 $2.00 $5.00 $5.00 $2.00 $11.00 $1.00
11506-7041 TEMP SEDMT CONT FENCE (REMOVE)40LF $8.49 $1.00 $1.00 $1.00 $1.00 $1.00 $2.00 $11.00 $1.00
12506-7043 BIODEG EROSN CONT LOGS (INSTL) (8")160LF $4.50 $4.00 $5.00 $1.00 $8.00 $7.50 $20.00 $11.00 $1.00
13506-7046 BIODEG EROSN CONT LOGS (REMOVE)160LF $1.65 $1.00 $1.00 $1.00 $2.00 $2.50 $20.00 $6.00 $1.00
14735-7061 DRIFTWOOD REMOVAL1LS $10,000.00 $6,000.00 $4,500.00 $4,500.00 $5,000.00 $5,000.00 $10,000.00 $11,000.00 $750.00