Bid tab 2121-04-129

Let Mar 4, 2025 · El Paso · El Paso Sign up free

‹ Mar 2025 results

IH10 MBGF (FM 659 | FM 1281)

Let date
Tuesday, March 4, 2025
CCSJ
2121-04-129
District
El Paso
County
El Paso
Highway
IH 10
Limits
FM 659 (ZARAGOZA RD) to FM 1281 (HORIZON BLVD)
Classification
Bridge Maintenance · Construction
Project number
C 2121-4-129
Working days
51
DBE goal
0%

Bidders 9

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$425,202
1 ROSS SA ENTERPRISE LLC Low bidder $276,338 -35.0%
2 APACHE BARRICADE & SIGN $345,620 -18.7% +25.1%
3 DAN WILLIAMS COMPANY $375,631 -11.7% +35.9%
4 B & MS CONSTRUCTION, INC. $387,575 -8.8% +40.3%
5 INTERNATIONAL EAGLE ENTERPRISES, INC. $396,164 -6.8% +43.4%
6 SYNERGY PROJECT CONTRACTORS, INC. $398,924 -6.2% +44.4%
7 ICOS MANAGEMENT, LLC $402,294 -5.4% +45.6%
8 HJC FARMS, INC. $451,324 +6.1% +63.3%
9 Horizone Construction I, Ltd $477,444 +12.3% +72.8%

Bid tab: unit prices 17 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 ROSS SA ENTERPR…#2 APACHE BARRICAD…#3 DAN WILLIAMS CO…#4 B & MS CONSTRUC…#5 INTERNATIONAL E…#6 SYNERGY PROJECT…#7 ICOS MANAGEMENT…#8 HJC FARMS, INC.
1104-7005 REMOV CONC (MOWSTRIP)199LF $8.00 $25.00 $25.00 $7.50 $85.00 $30.00 $23.60 $66.00 $50.00
2432-7013 RIPRAP (MOW STRIP)(4 IN)137CY $803.00 $500.00 $695.00 $650.00 $620.00 $500.00 $472.00 $660.00 $800.00
3500-7001 MOBILIZATION1LS $50,730.00 $25,000.00 $1,000.00 $37,000.00 $35,000.00 $35,000.00 $47,200.00 $15,000.00 $75,000.00
4502-7001 BARRICADES, SIGNS AND TRAFFIC HANDLING3MO $7,852.00 $3,500.00 $8,000.00 $15,000.00 $3,000.00 $15,000.00 $4,720.00 $1.00 $2,200.00
5505-7001 TMA (STATIONARY)51DAY $387.00 $400.00 $325.00 $200.00 $290.00 $150.00 $383.50 $275.00 $50.00
6506-7043 BIODEG EROSN CONT LOGS (INSTL) (8")273LF $9.00 $15.00 $13.95 $6.00 $5.00 $12.00 $5.90 $11.00 $15.00
7506-7046 BIODEG EROSN CONT LOGS (REMOVE)273LF $3.00 $1.00 $9.00 $2.05 $3.00 $1.00 $2.36 $6.00 $3.00
8540-7002 MTL W-BEAM GD FEN (STEEL POST)2,100LF $43.00 $30.00 $38.00 $34.50 $45.00 $38.00 $53.10 $55.00 $50.00
9540-7005 MTL BEAM GD FEN TRANS (THRIE-BEAM)6EA $3,195.00 $2,000.00 $3,045.00 $3,000.00 $1,800.00 $4,900.00 $3,567.14 $4,400.00 $3,500.00
10540-7015 DOWNSTREAM ANCHOR TERMINAL SECTION8EA $1,883.00 $1,500.00 $1,400.00 $1,400.00 $2,750.00 $2,500.00 $1,740.50 $2,200.00 $2,500.00
11542-7001 REMOVE METAL BEAM GUARD FENCE3,325LF $9.00 $1.00 $9.00 $8.00 $7.00 $5.00 $11.80 $5.00 $5.00
12542-7002 REMOVE TERMINAL ANCHOR SECTION1EA $389.00 $1,000.00 $150.00 $350.00 $1,400.00 $1,200.00 $236.00 $550.00 $500.00
13542-7003 REMOVE DOWNSTREAM ANCHOR TERMINAL7EA $408.00 $300.00 $150.00 $350.00 $1,400.00 $1,000.00 $354.00 $1,100.00 $500.00
14542-7004 RM MTL BM GD FENCE TRANS (THRIE-BEAM)6EA $422.00 $250.00 $270.00 $350.00 $1,750.00 $1,000.00 $354.00 $550.00 $500.00
15544-7001 GUARDRAIL END TREATMENT (INSTALL)12EA $3,829.00 $3,500.00 $3,800.00 $4,000.00 $2,800.00 $4,600.00 $4,248.00 $5,500.00 $5,000.00
16544-7003 GUARDRAIL END TREATMENT (REMOVE)12EA $407.00 $200.00 $150.00 $350.00 $1,400.00 $1,000.00 $236.00 $550.00 $500.00
17658-7018 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2109EA $48.00 $30.00 $75.00 $49.00 $19.00 $30.00 $15.34 $44.00 $65.00

Showing the first 8 bidders. The Excel and CSV downloads include all 9.