SAFETY IMPROVEMENT PROJECTS
- Let date
- Thursday, October 3, 2019
- CCSJ
- 0920-00-124
- District
- Beaumont
- County
- Jefferson
- Highway
- VA
- Limits
- DISTRICTWIDE
- Classification
- Construction
- Project number
- STP 2020(022)
- Working days
- 100
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | $1,174,628 | ||
| 1 | STRIPE-A-ZONE, INC. Low bidder | $1,289,630 | +9.8% | |
| 2 | INTERSTATE BARRICADES & MARKINGS, INC. | $1,442,191 | +22.8% | +11.8% |
| 3 | CRABTREE BARRICADE SYSTEMS, INC. | $1,460,107 | +24.3% | +13.2% |
| 4 | TOTAL HIGHWAY MAINTENANCE, LLC | $1,503,601 | +28.0% | +16.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 STRIPE-A-ZONE, … | #2 INTERSTATE BARR… | #3 CRABTREE BARRIC… | #4 TOTAL HIGHWAY M… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 500-6001 | MOBILIZATION | 1 | LS | $105,512.00 | $78,500.00 | $50,000.00 | $25,000.00 | |
| 2 | 502-6001 | BARRICADES, SIGNS AND TRAFFIC HANDLING | 7 | MO | $2,000.00 | $3,500.00 | $5,000.00 | $200.00 | |
| 3 | 533-6003 | RUMBLE STRIPS (SHOULDER) ASPHALT | 1,637,185 | LF | $0.1500 | $0.1600 | $0.1800 | $0.2200 | |
| 4 | 533-6004 | RUMBLE STRIPS (CENTERLINE) ASPHALT | 1,796,894 | LF | $0.1500 | $0.1600 | $0.1800 | $0.2200 | |
| 5 | 666-6311 | RE PM W/RET REQ TY I (Y)4"(BRK)(090MIL) | 539,068 | LF | $0.2300 | $0.3000 | $0.3500 | $0.3200 | |
| 6 | 666-6314 | RE PM W/RET REQ TY I (Y)4"(SLD)(090MIL) | 1,437,515 | LF | $0.2300 | $0.3000 | $0.3500 | $0.3200 | |
| 7 | 672-6009 | REFL PAV MRKR TY II-A-A | 15,251 | EA | $2.55 | $2.80 | $3.00 | $2.80 | |
| 8 | 6185-6005 | TMA (MOBILE OPERATION) | 300 | DAY | $155.00 | $5.00 | $5.00 | $10.00 |