BRIDGE REPLACEMENT

Let date
Thursday, May 2, 2024
CCSJ
0911-40-030
District
Lufkin
County
Trinity
Highway
CR
Limits
HAMILTON ROAD AT TRIB OF JAMES CREE
Classification
Construction
Project number
BR 2024(071)
Working days
57

Bidders 5

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate$489,153
1 TALBERT COMPANIES LLC Low bidder $499,407 +2.1%
2 DCC CONSTRUCTION AND SERVICES, L.L.C. $509,360 +4.1% +2.0%
3 THK CONSTRUCTION LLC $554,943 +13.4% +11.1%
4 C. E. BARKER, LTD. $649,926 +32.9% +30.1%
5 GARRET SHIELDS INFRASTRUCTURE $723,259 +47.9% +44.8%

Bid tab: unit prices 32 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 TALBERT COMPANI…#2 DCC CONSTRUCTIO…#3 THK CONSTRUCTIO…#4 C. E. BARKER, L…#5 GARRET SHIELDS …
1100-6002 PREPARING ROW3.35STA $3,500.00 $4,025.00 $1,000.00 $18,000.00 $16,000.00 $5,000.00
2110-6001 EXCAVATION (ROADWAY)109CY $25.00 $57.50 $50.00 $40.00 $26.88 $100.00
3132-6003 EMBANKMENT (FINAL)(ORD COMP)(TY B)127CY $25.00 $57.50 $50.00 $40.00 $39.09 $100.00
4160-6003 FURNISHING AND PLACING TOPSOIL (4")1,492SY $3.00 $5.75 $4.00 $5.00 $4.89 $4.00
5162-6002 BLOCK SODDING150SY $8.00 $17.25 $10.00 $7.64 $8.55 $10.00
6164-6009 BROADCAST SEED (TEMP) (WARM)746SY $0.5000 $1.23 $1.00 $0.0100 $1.22 $0.5000
7164-6011 BROADCAST SEED (TEMP) (COOL)746SY $0.5000 $1.22 $1.00 $0.0100 $1.22 $0.5000
8164-6054 BOND FBR MTRX SEED (PERM)(RURAL)(SAND)1,492SY $1.00 $1.78 $5.00 $2.88 $2.44 $0.5000
9168-6001 VEGETATIVE WATERING62.7MG $15.00 $188.90 $1.00 $20.00 $366.48 $200.00
10247-6073 FL BS (CMP IN PLC)(TY D GR 1-2) (6")706SY $45.00 $69.00 $75.00 $60.00 $46.00 $40.00
11400-6005 CEM STABIL BKFL52CY $300.00 $408.14 $300.00 $385.00 $305.40 $300.00
12416-6002 DRILL SHAFT (24 IN)273LF $350.00 $230.00 $275.00 $252.24 $301.49 $350.00
13420-6013 CL C CONC (ABUT)21CY $1,200.00 $1,470.72 $1,900.00 $1,500.00 $1,790.06 $4,000.00
14422-6007 REINF CONC SLAB (SLAB BEAM)1,300SF $25.00 $26.13 $30.00 $35.00 $36.49 $60.00
15425-6012 PRESTR CONC SLAB BEAM (5SB15)247.41LF $300.00 $244.89 $215.00 $313.50 $307.03 $340.00
16432-6033 RIPRAP (STONE PROTECTION)(18 IN)351CY $220.00 $226.45 $200.00 $180.00 $313.95 $250.00
17450-6019 RAIL (TY T631LS)124LF $80.00 $46.00 $100.00 $72.57 $36.65 $100.00
18454-6021 TYPE A JOINT53.8LF $35.00 $23.00 $100.00 $15.00 $36.65 $120.00
19496-6016 REMOV STR (PIPE)2EA $1,000.00 $677.31 $5,000.00 $7,500.00 $1,068.90 $1,000.00
20500-6001 MOBILIZATION1LS $35,000.00 $50,000.00 $50,000.00 $55,000.00 $62,000.00 $60,000.00
21502-6001 BARRICADES, SIGNS AND TRAFFIC HANDLING8MO $3,500.00 $1,868.75 $3,000.00 $1,402.50 $3,664.80 $10,000.00
22506-6002 ROCK FILTER DAMS (INSTALL) (TY 2)75LF $35.00 $46.59 $50.00 $50.00 $67.19 $5.00
23506-6011 ROCK FILTER DAMS (REMOVE)75LF $10.00 $13.12 $1.00 $1.00 $24.43 $1.00
24506-6020 CONSTRUCTION EXITS (INSTALL) (TY 1)112SY $30.00 $17.55 $1.00 $1.00 $46.42 $10.00
25506-6024 CONSTRUCTION EXITS (REMOVE)112SY $10.00 $5.76 $1.00 $1.00 $17.10 $10.00
26506-6038 TEMP SEDMT CONT FENCE (INSTALL)728LF $4.00 $3.70 $10.00 $5.00 $5.50 $6.00
27506-6039 TEMP SEDMT CONT FENCE (REMOVE)728LF $1.00 $1.31 $1.00 $1.00 $2.44 $2.00
28540-6001 MTL W-BEAM GD FEN (TIM POST)113.5LF $35.00 $31.86 $35.00 $30.60 $61.08 $40.00
29540-6016 DOWNSTREAM ANCHOR TERMINAL SECTION2EA $1,800.00 $1,206.44 $1,500.00 $1,551.00 $2,076.72 $2,000.00
30544-6001 GUARDRAIL END TREATMENT (INSTALL)2EA $3,500.00 $3,329.46 $3,850.00 $3,366.00 $4,642.08 $3,500.00
31552-6003 WIRE FENCE (TY C)300LF $25.00 $34.53 $10.00 $30.00 $30.54 $10.00
32658-6062 INSTL DEL ASSM (D-SW)SZ 1(BRF)GF2(BI)6EA $40.00 $29.34 $50.00 $49.50 $48.86 $40.00